RFB-210-13
Bluegrass Oakwood Community Center
Estimate:
$109,815.00
These specifications and the accompanying drawings describe the work to be provided and the materials to be furnished under this contract for the modification and installation of an existing 250 KW generator. The generator is located at Glasgow State Nursing Facility in Glasgow, Kentucky. The generator is to be transported to Bluegrass-Oakwood Community Center, Somerset, Kentucky. The 250 KW generator will be installed on a new concrete pad adjacent to the main electrical room in Building 600. A new 1,000 ampere automatic transfer switch (ATS) shall be furnished and installed on a pedestal on the new generator pad. A new 2,000 gallon bulk diesel fuel storage tank with dispenser shall be furnished and installed on a second concrete pad adjacent to the generator and ATS concrete pad. Building 600 houses the kitchen, laundry, and maintenance shops.
North Gratz Street Sidewalk Project
Includes removing and replacing the sidewalk and retaining wall along west side of North Gratz Street between East Main Street and East Bruen Street.
Midway, KY
13-70 / Lower Hunters Trace Water Main Replacement Project
13-70 / Lower Hunters Trace Water Main Replacement Project
Louisville Water Company is requesting Bids for the installation of 1,225 linear feet of eight (8)-inch PVC water main and 20 linear feet of six (6)-inch DPW water main along Lower Hunters Trace between 6501 Lower Hunters Trace and Maravian Drive. Also included with the project is the installation of two (2) fire hydrants, the relocation/renewal/transfer of fifteen (15) customer services, five (5) meter exchanges and two (2) service discontinues.
13-78 / Bullitt County Water Improvement Program Two-Thirds Majority Petition North and South Summit Drive 4-Inch Water Main Extension
13-78 / Bullitt County Water Improvement Program Two-Thirds Majority Petition North and South Summit Drive 4-Inch Water Main Extension
Louisville Water Company is requesting Bids for the furnish and installation of 2,390 +/- lineal feet of four (4)-inch PVC DR 18 water main, 655 +/- lineal feet four (4)-inch Ductile Iron Pressure Class 350 restrained and non-restrained joint water main and 30 +/- lineal feet six (6)-inch Ductile Iron Pressure Class 350 restrained and non-restrained joint water main and appurtenances. Restoration of the site and all of the above made ready for use in accordance and compliance with the Contract Documents.
Magoffin County School Site Clearing
Magoffin County School Site Clearing
Salyersville, KY Click Here for More Details
Eubank Elementary School Waste Water Treatment Plant
Eubank Elementary School Waste Water Treatment Plant
This project includes installation of a new waste water treatment plant and the disconnect of the existing waste water treatment system.
Eubank, KY Click Here for More Details
Miscellaneous Metal Replacement and Welding, Abrasive Blasting and Painting of one (1) Clarifier, one (1) Oxidation Ditch, one (1) Digester, to include, piping and accessory equipment; and also structural concrete improvements to expansion joints on the Oxidation Ditch located at the DISTRICT’s Radcliff Wastewater Treatment Plant.
Remove three existing gate valves, valve boxes, extension stems, floor stands and associated piping, as shown on the drawings. Furnish and install three resilient seat gate valves and associated piping. Furnish and install three 5′ diameter precast concrete valve vaults complete with base, top slab, casting, floor stand and extension stems. Backfill excavation with crushed stone and restore asphalt surface in accordance with the contract documents.
Demolish the metal and wood rake facilities in two unused basins of the digester structure.
13-72 / Sherwood Avenue Area Lead Service Renewals
13-72 / Sherwood Avenue Area Lead Service Renewals
Louisville Water Company is requesting Bids for the renewal of lead services on Sherwood Ave., Eastern Parkway, Alta Ave., Bonnycastle Ave., Parsons Pl., Edgewood Pl., Cowling Ave., Barney Ave., and Cherokee Rd. Design information indicates a total of 122 customer service renewals, seven (7) customer service relocates, fourteen (14) customer service discontinues and thirty-one (31) meter exchanges.
WKU-PDC-2013-069 HVAC Upgrade — Ivan Wilson Recital Hall
WKU-PDC-2013-069 HVAC Upgrade — Ivan Wilson Recital Hall
This project shall be for the upgrade of the HVAC system for the Ivan Wilson Recital Hall as directed by the terms and conditions of the bid. Services needed for this job will be mechanical, electrical, and controls.
Grayson Co High School Major Renovations Phase 1
Furnish all labor, materials, equipment and services for the Major Renovations at Grayson County High School – Phase 1.
Leitchfield, KY Click Here for More Details
HW Wilkey Elementary School – Toilet, Plumbing and Kitchen Renovation
HW Wilkey Elementary School – Toilet, Plumbing and Kitchen Renovation
Furnish all labor, materials, equipment and services for the HW Wilkey Elementary School – Toilet, Plumbing and Kitchen Renovation
Contract 2 100,000 Gallon Elevated Tank Mt Olivet KY
Contract 2 100,000 Gallon Elevated Tank Mt Olivet KY
A 100,000 gallon elevated water storage tank including tank, tank foundation, site preparation, excavation, valve vault, access road and all related appurtenances.
Jessie Clark Middle School Addition and Renovation
Jessie Clark Middle School Addition and Renovation
The work includes the completion renovation of the existing school with new 2-story Addition for a total of 124,966 SF. The existing school has approximately 99,371 SF and the 2-story Addition will have 25,595 SF. Jessie Clark Middle School was originally built in 1962 with major building additions in 1990. The scope of work for this current major construction project includes but is not limited to: selective and building demolition, removal and replacement of mechanical systems including installation of variable refrigerant volume systems, replacement of existing electrical systems, fire protection, fire alarm systems, interior finishes (walls, ceilings, floors and base), door hardware, site improvements and paving, replacement of kitchen equipment and the additional 25,595 SF of new administrative area, interior corridor connection to gym, music & art department, enrichment classrooms, elevator and secondary entry vestibules. The Owner shall be responsible for all asbestos abatement with the exception that existing roofing system components containing asbestos shall be removed by the contractor. The work effort will be executed in three Phases beginning in July 2013 and ending July 2015. The building will be occupied and in-use during all phases of construction work. The site work is designed to interface with LFUCG road and utility work along Clays Mill Road while allowing the school to continue its primary functions during the regular academic calendar years of 2013-14 and 2014-15. The contractor shall be required to coordinate the contract work with daily school activities, as well as between phases with the FCPS-provided activities related to: moving of occupants; asbestos abatement; and the installation of casework (not-in-contract).
Lexington, KY
Middle Creek Battlefield Walking Trail Improvements
Middle Creek Battlefield Walking Trail Improvements
Middle Creek Battlefield / Walking Trail Improvements
Floyd County, KY Click Here for More Details
Tates Creek HS Synthetic Turf
Tates Creek HS Synthetic Turf
Removal and partial recycling of the existing synthetic turf athletic field, reworking the existing perimeter drainage, addition of storm drain piping, installation on concrete pole vault runway and landing area, installation of new football field goal posts, installation of discus pole sleeve supports, reworking of the existing gravel sub base and final laser grading, installation of geotextile fabric, shock drainage pad, and synthetic turf system with rubber/sand mix infill. The area of field replacement is the total area inside the existing perimeter track system – totaling approximately 119,500 SF EACH. All existing track surfaces, and other existing appurtenances shall be protected and not damaged during construction of the turf replacement.
Lexington, KY Click Here for More details
Paul Laurence Dunbar High School Synthetic Turf Replacement – Athletic Field
Paul Laurence Dunbar High School Synthetic Turf Replacement – Athletic Field
Removal and partial recycling of the existing synthetic turf athletic field, reworking the existing perimeter drainage, addition of storm drain piping, installation on concrete pole vault runway and landing area, installation of new football field goal posts, installation of discus pole sleeve supports, reworking of the existing gravel sub base and final laser grading, installation of geotextile fabric, shock drainage pad, and synthetic turf system with rubber/sand mix infill. The area of field replacement is the total area inside the existing perimeter track system – totaling approximately 119,500 SF EACH. All existing track surfaces, and other existing appurtenances shall be protected and not damaged during construction of the turf replacement.
Lexington, KY Click Here for More Details
RFB-208-13 Site Drainage Phase III
RFB-208-13
Bowling Green Technical College
Estimate:
$315,910.00
The work located at the Bowling Green Technical College, Bowling Green, Kentucky and consists of (1) trenching and backfilling for underground schedule 40 PVC communications conduits, empty with pull wires,(2) repair of walkway, roadway, concrete, and asphalt surfaces to match existing conditions, (3) new communications pullboxes, and (4) new building enclosures. The project also consist of storm water drainage updates and repairs with new drop box inlets, yard drains and downspout collection extensions to provide an updated storm sewer and tie to existing storm drainage structures.
RFB-209-13 HVAC Renovation Eastern Kentucky Veterans Center
RFB-209-13
Estimate:
$527,033.00
This project involves the removal of the existing outside air fans, duct work and the installation of new 100% outside air make up air unit to condition the incoming air so that it will be introduced to the building at a neutral air temperature and appox. 50% RH.This project has Automated Logic DDC control system that exist and it will be expanded to accept the four new make-up air units. The two systems will communicate over the BACNET system being supplied with the new make-up air units.