Estimated Length of Project:
(Substantial Completion) + 180 Calendar Days (Final Completion)
The scope of work involves repairing a driveway slide at the Keen residence. The slide area will be excavated, and the material will be transported to a designated waste area site. To stabilize the driveway, a concrete wall on pilings, 50 feet long and 10 feet tall, will be installed as the primary support structure. To construct the concrete wall, a steel rail wall 100 feet long will be placed below, if needed. Additionally, a 9-foot-high, 54-foot-long gabion wall will be constructed along the upper hillside to provide further support. A 100-foot-long Class 2 flat-bottom ditch will be built to control water runoff from the hillside. To manage water flow across the driveway, an 18-inch HDPE pipe, 24 feet long, will be installed beneath the roadway. A silt trap will be installed at the project’s lower end near Wendover Rd. and will be maintained throughout the duration of the project. The roadway ditch will also need cleaning and any possible areas on ditch side of project if needed. The slide area beneath the driveway will be excavated and the material transported to the waste area. The total project area spans 2.92 acres, with a maximum disturbed area of 1.02 acres. Of this, 0.60 acres consists of trees greater than 3 inches in diameter at breast height that will be affected. All disturbed areas will be quickly revegetated at the conclusion of construction, appropriate residential or wildlife seed.
Work of the Project includes a new single story district Materials Lab for the Kentucky Transportation Cabinet – District 11 in Clay County Kentucky. The property is underlain by mine/roadway spoils. The building is supported on a mat foundation system. The new building consists of load bearing masonry with steel beams and metal roof deck. Exterior walls have brick veneer or metal panels with insulation. Interior partitions are metal studs with gypsum on both sides and batt insulation. The roof is standing seam metal roof. Interior finishes include gypsum, epoxy flooring, ceramic wall tile, and acoustical ceiling tile. Plastic laminate casework is located in the break area. HVAC systems consist of two 4-ton split systems connected to indoor units. All lighting will be LED.
RFB-26-010 RE-AD of RFB-26-002 Henderson CC Elevator Upgrades
RFB-26-010 RE-AD of RFB-26-002 Henderson CC Elevator Upgrades
This project will modernize the existing elevator in the Administration Building (1990s) at Henderson Community College. Scope of work for modernization includes upgrades to the pumps, controllers, door equipment, operating panels, rollers, clutch, interlocks, closers, and associated items. Materials, Labor, Tools, permitting, and testing to bring the elevators up to current building codes is to be included, as well as cosmetic upgrades to the elevator cabs.
An Add alternate is provided to also modernize the Hartfield Library (1970s) elevator.
Construct a new 7,988 sq. ft. post-frame building for crop protection research at the UK
Research and Education Center in Princeton, KY. The building is comprised of a drivethrough
bay, prep room, bathrooms and storage. Construction drawings with specifications
have been supplied by Albert & Associates, Yeiser Structural and E-Tech Consultants.
Building to be located on the UK Research and Education Center in Princeton, KY. The
project address is 101 University Access Drive, Princeton, KY 42445.
****ADD ALTERNATES****
There will be three additive alternates and one deductive alternate for this project. List of
alternates and priority order are explained on the attached form of proposal list.
The Kentucky Community and Technical College System (KCTCS), Office for Facilities Support Services through the Office of Capital Project Services (CPS), is soliciting sealed proposals from qualified firms to establish Master Agreement contracts to provide Job Order Contracting (JOC) Services for indefinite delivery/ indefinite quantity (IDIQ) for each of the following trades:
The Project is located in Hartford, KY. The Project entails remediation of arsenic impacted media (soils) at the site. The media has been contaminated via historic illegal powered arsenic dumping on the property and associated migration by surface water drainage.
Previous investigations at the site have determined that environmental media is contaminated with arsenic. Arsenic has been detected in soil surrounding an old barn structure and along a downhill slope from the old barn. The impacted hill is both cleared and tree covered.
Soil will be excavated and removed for off-site disposal. All soil excavations will be accomplished at various depths as specified. Following excavation activities, the soil ground surfaces will be restored to match original grades, and the areas will be vegetated.
Jefferson County Public Schools – Iroquois High School Chiller Replacement
Jefferson County Public Schools – Iroquois High School Chiller Replacement
This project consists of a chiller replacement at Iroquois
High School in the Jefferson County Public School
District. The existing chillers will be replaced as part of
this project. The existing piping will be reworked to
support these replacements.
The electrical scope is also limited to supporting this
replacement.
The chillers will be contractor-furnished and installed
and JCPS will be doing their own controls installation.
City of Cynthiana – Cynthiana Fire Station #1 Addition
City of Cynthiana – Cynthiana Fire Station #1 Addition
A 3216 sq. ft. One-Story Addition to the City’s Fire Station #1. The addition is of masonry
construction (CMU with a brick façade) with two double stacked truck bays. The addition will
include a new Break Area and ADA restrooms as part of an ICC 500 Storm Shelter inside the
addition.
CCK-3187.10-1-26 Kroger Field Repairs 2026- Lower Bowl Concrete & Waterproofing
CCK-3187.10-1-26 Kroger Field Repairs 2026- Lower Bowl Concrete & Waterproofing
• The Lower Seating repairs occur between stadium Gate 1 and Gate 4.
• The work focuses on the precast concrete seating units at Row 1 through Row 51 in Section
1 through Section 11.
• Repairs include removal and replacement of the waterproofing membrane and all sealants at
the precast seating units.
• Rewelding and repairs of steel connections between precast seating units, repairs at rails, and
installation of supplemental steel brackets.
• Repair of concrete deterioration at the precast seating units and support framing.
• Installation of new drains at the lower row and repairs at existing drains.
• Preparation and painting of steel framing, support members, and concrete wall panels.
• The existing bleacher-style seats will be temporarily removed and reinstalled upon
completion of the work in the Lower Seating.
Mountain Comprehensive Health Corporation – MCHC – Pharmacy Drive-Thru Alteration
Mountain Comprehensive Health Corporation – MCHC – Pharmacy Drive-Thru Alteration
The project site is located at 226 Medical Plaza Ln, Whitesburg, KY. The bid is to furnish all
necessary labor, materials, tools, machinery, warranties, and all other items required to meet
the plans and specifications. Work to include, but not limited to: Interior and exterior concrete,
brick masonry, structural steel framing, interior finishes, 60 mil rubber roofing, aluminum
doors/windows, Electric, Plumbing, HVAC, casework, earthwork, grading, asphalt paving, and
storm drainage.
Laurel County Board of Education – Laurel County Day Treatment – Phase 2
Laurel County Board of Education – Laurel County Day Treatment – Phase 2
The Phase 2 Project at the Laurel County Day Treatment campus in the Bush community is
centered on renovation of the Existing Gymnasium and associated spaces. The main
gymnasium will receive new windows, HVAC equipment, lighting and electrical fixtures,
repaired flooring, and refreshed finishes. The existing stage area will be demolished and
replaced with new floor structure at the same elevation as the main gymnasium. That space will
then contain new restrooms, janitorial, and storage spaces. The space between in the existing
stage opening will receive new infill framing and casework. The existing basement floor will
be reworked to accommodate new footings and mechanical equipment. New double doors and
exterior access will be provided for this unoccupied space at the back of the gymnasium.
Existing abandoned openings on the rear and side of the gymnasium will be infilled with
matching stone finishes. All existing exterior walls associated with Phase 2 will be cleaned. A
new canopy and ramp will be constructed at the existing exterior gymnasium door. A new
decorative main entrance gate will be constructed at the southern entrance, and a non-decorative
gate constructed at the southern entrance. Some selective ceiling demolition and replacement in
the existing Phase 1 corridor to facilitate Domestic Water, Sprinkler, and Power services to be
extended to Phase 2 will be required. This work will allow the campus to utilize this space in
day-to-day instructional activities and preserve the historical space for the community.
DeSales High School will receive sealed bids for the furnishing of all labor and materials and the performance of
all work required for the
DeSales High School
Innovation Center Addition.
CCK-3187.20-1-26 Kroger Field 2026 Repairs- Upper Bowl Concrete & Waterproofing
CCK-3187.20-1-26 Kroger Field 2026 Repairs- Upper Bowl Concrete & Waterproofing
PROJECT DESCRIPTION
Includes:
• Upper Concourse Concrete & Waterproofing Repairs.
• Prepare and install a waterproofing membrane on the structural slab, stairs, and
bridges. Work includes replacement of sealants.
• Repair of concrete deterioration and rebuild the slab edge at concourse expansion
joints.
• Replace concourse expansion joints.
• North Loft Club Seating Concrete & Waterproofing Repairs.
• The Loft Club Seating repairs occur between stadium Gate 1 and Gate 4.
• The work focuses on the precast concrete seating units at Row 1 through Row 7 in
Section 101 through Section 210.
• Repairs include removal and replacement of the waterproofing membrane and all
sealants at the precast seating units.
• Rewelding and repairs of steel connections between precast seating units, repairs at
rails, and installation of supplemental steel brackets.
• Repair of concrete deterioration at the precast seating units and support framing.
• Preparation and painting of steel framing, support members, and concrete wall
panels.
• Installation of new drains at the lower row and repairs at existing drains.
• The existing bleacher-style and regular seats will be temporarily removed and
reinstalled upon completion of the work in the Loft Club Seating.
Estimated Length of Project:
(Substantial Completion) + 90 Calendar Days (Final Completion)
Drainage from eligible works are located upslope of the citizen’s residence impacting the residence and yard area. A slide has also occurred on the slope behind/beside the citizen’s residence impacting yard drainage. This project addresses the slide removing a quantity of material and grading the remainder in place in a stable configuration. The existing ditch adjacent to the slide area will be excavated to rock. A Concrete Block-Tied Mat ditch will be installed from the top end of the excavated rock ditch to a planned drop box at the toe. Drainage will also be collected by installation of subdrain along the toe of the highwall. All collected drainage will be routed to a second drop box installed on the existing pipe crossing KY-194 and ultimately the roadside ditch. Concrete Block-Tied Mat ditches will also be installed to control surface drainage from the adjacent roadway and conduct drainage down the slope to the drop box and existing culvert. A culvert with inlet headwall will be installed between the concrete block-tied mat adjacent to the state roadway and drop box to allow access. All material generated by construction activities will be wasted onsite
Clark County Project Development Board – A/E RFP Documents
Clark County Project Development Board – A/E RFP Documents
The Clark County Project Development Board (PDB) proposes to
construct a new judicial center to be located in Winchester,
KY. The PDB invites interested architectural firms to
electronically submit a Court of Justice Architect-Engineer and
Related Services Questionnaire to the Administrative Office of
the Courts.
Cawood Water District – US 421/KY 3001 Waterline Replacement – Contract 2
Cawood Water District – US 421/KY 3001 Waterline Replacement – Contract 2
The project consists of replacing approximately 5,750 L.F. of 8″ and 3″ waterline, one
pressure reducing station, and all necessary appurtenances along US 421 and KY 3001
in Harlan County.
The project involves roof work at the Hazard Community and Technical College on the Heavy Equipment, Devert Owens, Walter Prater, and First Federal buildings.
The Heavy Equipment and Devert Owens buildings will both have their existing roofs completely removed and replaced with a new two-ply SBS modified bitumen roofing system installed over new insulation and cover board.
The Walter Prater building will receive a recover roof system, with a new two-ply SBS modified bitumen roof installed over a cover board set above the existing roof. Any surface defects in the existing roof will be repaired before the new system is installed.
The First Federal building will have all four gutter roof areas replaced with a new fluid-applied roofing system. The standing seam metal roof will also be prepped and repainted, with a new coping cap installed over the existing stone coping cap on the metal roof sections to match the low-slope roof areas, along with miscellaneous tuckpointing of the stone cornice.
The Devert Owens building will also include repainting the scupper/downspout boots, the canopies, the metal siding and siding at the higher building section.
All work includes new flashings, accessories, and related sheet-metal components.
Jefferson County Public Schools – Chiller Replacement – Jeffersontown High School
Jefferson County Public Schools – Chiller Replacement – Jeffersontown High School
The primary scope of work for this project is to replace the chillers
and pumps serving Jeffersontown High School, including electrical
upgrades required.
Jefferson County Public Schools – Boiler & Chiller Replacement – Barret Traditional Middle School
Jefferson County Public Schools – Boiler & Chiller Replacement – Barret Traditional Middle School
This project consists of a central plant replacement at
Barret Traditional Middle School in the Jefferson
County Public School District. The existing gas-fired
hot water boilers and chillers will be replaced along
with all existing chilled water, hot water, and building
pumps. The existing piping will be reworked to support
these replacements, and the chiller enclosure will be
expanded to accommodate the new equipment.
The electrical scope is also limited to supporting these
replacements.
The existing chillers shall be delivered and turned over
to JCPS and all new equipment shall be furnished and
installed by the contractor.