Spencer County Fiscal Court – Spencer County Pavilion/Farmers Market
Spencer County Fiscal Court – Spencer County Pavilion/Farmers Market
Provide all labor and
materials necessary to complete the construction of the existing building at the pavilion/farmers
market site as well as construct the second building.
Town of Clarksville – Access Roads for Pump Station 24 and Appleleaf Sewer
Town of Clarksville – Access Roads for Pump Station 24 and Appleleaf Sewer
This project involves the installation of approximately:
• Approx. 3,120 LF of 15’ Permanent Access Gravel Roadway
• Associated clearing, grading, and sitework.
• Installation of 9ft x 6ft Box Culvert at Plum Run Creek crossing
Town of Clarksville – Pump Station 32 Force Main Diversion & Renovations
Town of Clarksville – Pump Station 32 Force Main Diversion & Renovations
This project involves the installation of approximately:
• 1,370 LF 6” Force Main installation
• Associated air release valve/manholes.
• 270 LF Directional Drill under Silver Creek
• Pump Station 32 upgrades-including new pumps, controls, generator, valve vault
• Pump station entrance drive and site work
Jessamine County Fiscal Court – Jessamine County Business Center Phase 2- Renovation Sitework
Jessamine County Fiscal Court – Jessamine County Business Center Phase 2- Renovation Sitework
The Jessamine County Business Center Phase 2 – Renovation Sitework and Interior Demolition project includes
upgrades to the existing site storm sewer system, construction of a new retaining wall, and interior demolition of a
substantial portion of the existing interior fit-up, including designated general construction, plumbing, HVAC, and
electrical components.
Jefferson County Public Schools – Fern Creek ES Boiler & Chiller Replacement
Jefferson County Public Schools – Fern Creek ES Boiler & Chiller Replacement
This project consists of a central plant replacement at
Fern Creek Elementary School in the Jefferson County
Public School district.
The existing gas-fired boilers and boiler pumps will be
replaced. The existing air-cooled chiller will be
replaced and the previously abandoned chilled water
pumps will be removed. An alternate will be included
to replace the existing building pumps. The existing
piping will be reworked to support these replacements.
The electrical scope is limited to supporting these
replacements as well.
JCPS will be pre-purchasing the chiller for the
contractor to receive and install in Fall of 2027 after
summer/winter changeover. All other equipment will
be contractor-furnished and installed. JCPS will also be
performing the controls work themselves, so no
temperature controls contractor is required for this
project.
Jefferson County Public Schools – Coleridge-Taylor Montessori ES Boiler & Chiller Replacement
Jefferson County Public Schools – Coleridge-Taylor Montessori ES Boiler & Chiller Replacement
This project consists of a central plant replacement at
Coleridge-Taylor Montessori Elementary School in the
Jefferson County Public School District.
The existing gas-fired boilers and boiler pumps will be
replaced. The existing split chillers, condensing units, and
chilled water pumps will be replaced with two groundmounted
air-cooled chillers and new chilled water pumps.
The existing building pumps will also be replaced and all
of the piping in the mechanical room will be reworked to
support these replacements.
A new chiller enclosure and boiler room egress door will
also be added, and the existing roof hatch will be replaced.
The electrical scope is limited to supporting these
replacements.
All equipment is contractor-furnished and installed, but
JCPS will be performing their own controls work so a
temperature controls contractor is not required for this
project.
Hardin County Water District No. 1 – Clarifier Rake Replacement Project
Hardin County Water District No. 1 – Clarifier Rake Replacement Project
The Project includes the following Work:
The installation of items to be replaced in the Secondary Clarifiers which include rake arms, scum
boxes, influent well, drive cage, all necessary hardware, and related equipment to meet existing
service demands and work with existing equipment and systems at the Fort Knox Wastewater
Treatment Plant, Fort Knox, Kentucky.
The Project consists of one contract
constructing of approximately 2,500 LF of 36-inch PVC gravity sewer, 800 LF of 8-inch gravity
sewer, 13 precast manholes, and other appurtenances.
The scope of work includes the construction of approximately 2,430 linear feet of new concrete
sidewalk and entrances, intersection curb ramps, and drainage.
Project Description:
This project consists of the replacement of the existing cooling tower, condenser water pumps, condenser water filtration unit, and modifications to the existing piping. The work generally consists of, but is not limited to, the following: a new cooling tower on a structural platform, new condenser water pumps, new condenser water filtration unit modifications to condenser water piping, installation of isolation valves for a temporary chiller, and building automation controls for the new equipment. The trades involved include, but not limited to, the following: demolition, concrete, structural steel, electrical, mechanical, mechanical insulation, chemical treatment, temperature controls.
The Expand Patient Care Facility project will involve the construction of a 2.08 million
SF, 895-bed facility, with the focus on the expansion of the Expand Patient Care
Facility. The building will accommodate additional inpatient beds and clinical support
services. General services targeted for this location include, but are not limited to,
adult and pediatric inpatient rooms, observation spaces, operating rooms, minor
procedures, diagnostic services, imaging services, pharmacy, retail, lab,
administration, support, and meeting spaces.
The ESP-3.3 scope of work includes expanding the infrastructure within the existing
Substation #1 with a new transformer and switchgear building with all associated
equipment as well as work in Substation #3. The scope of work also includes
underground electrical duct banks throughout the EPCF, CUP, and Garage sites,
along with wire, terminations, and energization. The electrical infrastructure provided
in this ESP will provide the main normal and emergency power distribution for the
new projects on site. See schedule, schedule & logistics narrative, and logistics plans
for detailed information.
The goal of this project is to remove the existing roofing system down to the existing roof deck and install a new roofing system consisting of new tapered insulation, gypsum roof cover board, and a new 2-ply modified bitumen asphalt roof system. All new prefinished metal coping caps, gutters, downspouts, metal roof splashes, flashings, accessories, and terminations are included.
Sealed Bids will be received electronically by Louisville and Jefferson County Metropolitan Sewer District, for the construction of N 32nd Street Sanitary Sewer Improvements, Contract No. 17383, Budget ID No. E26158, Drawing Record No. / Sheet No. 17383 / Sheet No 1-2, until 10:00 AM, Local Time, Tuesday November 17, 2026, and will be publicly opened and read at that time. The public may attend the bid opening via teleconference call at 502-654-8113 (Dial-in Number) Conference ID: 104
204 936#.
MSD is using a web-based portal for accepting and evaluating bid proposals digitally at http://louisvillemsd.bonfirehub.com/portal for this Invitation to Bid. Documents may be uploaded at any time during the open period indicated for each proposal.
Description and location of Project: The Contract provides for the installation of approximately 211 linear feet of 8-inch sanitary sewer, 2 sanitary manholes, and approximately 100 linear feet of 6-inch property service connections with the connection of 4 existing structures; pavement restoration; erosion prevention and sediment control; and appurtenant work. The project is generally located along the properties at 609 to 617 N 32nd Street. All work shall be done in accordance to MSD’s Standard Specifications.
There will be a non-mandatory pre-bid meeting held for this project. The non-mandatory pre-bid meeting will be held via Microsoft Teams Meeting at 10:00 AM, Local Time, Tuesday November 3, 2026. A site visit will be held immediately following the pre-bid meeting.
The Contractor is encouraged to attend. Anybody participating will be required to provide their own PPE.
Persons wishing to view the bid documents may do so online at http://louisvillemsd.bonfirehub.com/portal or at the following locations: Builders Exchange of Louisville, Inc., 2300 Meadow Drive; Associated Builders & Contractors of Kentuckiana, 1810 Taylor Avenue; and F. W. Dodge, 1812 Taylor Avenue; all located in Louisville, Kentucky; and the Associated General Contractors of Kentucky, 2321 Fortune Drive, Suite 112, Lexington, Kentucky.
The Project Manager for this Invitation to Bid is Karina Henson, P.E. All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s designated web portal at http://louisvillemsd.bonfirehub.com/portal. Questions received less than ten days prior to the date for opening of bids may not be answered. Only answers by formal written Addenda posted on MSD’s designated web portal will be binding. Oral and other interpretations or clarifications will be without legal effect. All inquiries and questions between the bid opening and the contract awarding shall be directed, in writing, to MSD’s Chief Engineer, David W. Johnson, P.E.
MSD SMALL BUSINESS ENTERPRISE PROGRAM POLICY AND PROCEDURES MANUAL (SBE PROGRAM) – FOR CONSTRUCTION CONTRACTS $300,000 AND GREATER for Small Business Enterprise (SBE) subcontracting participation. Effective July 1, 2026, MSD has adopted and implemented the MSD Small Business Enterprise Program Policy and Procedures Manual (SBE Program), The MSD SBE Program subcontracting goals are listed below:
If selected as applicable below, the Contractor must subcontract at least 35.0% of the total amount of the Contract Bid price to certified Small Business Enterprise Businesses. If the Contractor is unable to meet the goals, they must demonstrate adequate “GOOD FAITH EFFORTS” in accordance with the MSD Small Business Enterprise Program Policy and Procedures Manual (SBE Program) – see MSD SBE Program – Construction Subcontracting Goal Documents and Forms at https://louisvillemsd.org/EconomicInclusion.
MSD SMALL BUSINESS ENTERPRISE PROGRAM: Not Applicable
The Small Business Enterprise Program Policy and Procedures Manual (SBE Program) is effective July 1, 2026. If selected as “Applicable” or “Applicable, Partial Waiver” above, the goals are as follows:
35.0% SBE – Small Business Enterprise participation
SBE businesses are encouraged to bid on this project as a prime contractor.
This MSD construction project is bid and advertised as: check applicable below
Construction Services: x
Construction-related Services:
LOCAL LABOR COMMITMENT PREFERENCE: No
COMMUNITY BENEFITS PROGRAM: No
The contract will be awarded on the basis of the lowest, responsive, responsible bid, subject to the approval of the MSD Board. MSD reserves the right to reject any or all bids or waive any informality in any bid.
LOUISVILLE AND JEFFERSON COUNTY
METROPOLITAN SEWER DISTRICT
David Johnson, P.E.
Chief Engineer
Rene’ Lindsay, CPPO
One Water Chief Procurement Officer
Improvements to stormwater drainage conditions which include 967 linear feet of storm sewer with
associated inlets and junction structures, 185 linear feet of new concrete sidewalk and incidental
repairs/replacement of concrete pavement, asphalt pavement, sidewalks and curbs.
South Woodford Water District – Troy Pike Master Meter Replacement
South Woodford Water District – Troy Pike Master Meter Replacement
The work to be bid upon is described as follows:
• Replace the existing Master Meter Connection with the City of Versailles and installation of
approximately 610 l.f. of 8” and 12” water line, including miscellaneous appurtenances.
Project Description:
The project consists of approximately 3,385 SF of selective demolition and construction to renovate the existing electronic labs and classroom space on the First Floor of Blakely Hall to create a new Simulation Lab at the KCTCS campus in Somerset, KY.
The BASE BID Work shall include the excavation of a large portion of the Big Bone Lake Dam embankment which will be replaced by a roughened channel. The BASE BID Work shall also include clearing of trees and vegetation, installing erosion control
measures, staged drawdown and excavation of the Big Bone embankment, construction of a roughened channel with a cross vane placed at the start, grading of three tributaries with woody debris drop structures, construction of a wood toe for stream bank
protection, placement of excavated material in five designated spoil embankments, and site restoration and planting.
Demolition Work shall include full or partial demolition of the following existing structures: Piezometers, Water Valve, Stormwater Structures, and the Low Level Draw Down Pipe.
RFB-108-27 EEC-AML-25035AMLBAML Drakes Creek AML Reclamation Project
RFB-108-27 EEC-AML-25035AMLBAML Drakes Creek AML Reclamation Project
Estimated Length of Project:
(Substantial Completion) + 380 Calendar Days (Final Completion)
The 25035AMLBAML Drakes Creek AML Reclamation Project is in Hopkins County, Kentucky, at 3714’6.37″N”, 8725’31.90″W and will reclaim approximately 74 acres adversely affected by previous coal mining operations. The total project viewshed shown on the plans is 400 acres. Only 74 acres are proposed for construction, and it will be within those 400 acres. The entire 400 acres has been disturbed by previous pre-law surface mining and/or deep mining activities. There are multiple access points from public roads for the project. The project consists of backfilling approximately 2000 linear feet of mining highwall and eliminating approximately 14 acres of mine pits. Some pits will be backfilled with adjacent onsite mine spoil material as part of eliminating the mining highwall. The designated highwall areas will be backfilled at slopes no steeper than 3h:1v using adjacent mine spoil. The pits will be capped with the best material available on site. Some pits will be used in the construction of long-term water treatment cells to reduce acid mine drainage. The water in all pits will be treated and raised to a pH of 6 or greater prior to release in accordance with KYDAML Technical Specifications. Acidic spoils adjacent to the pit shall be used first in backfilling the pit to eliminate the acid forming potential of these materials. This effort will require additional effort and may require double handling of some soils. The final grade of spoil ridges will be no steeper than a 3:1 slope, and the highwall backfill will be no steeper than a 3:1 slope.
Acid mine drainage treatment cells will be constructed in the northern number nine coal seam mine bench utilizing the existing mine pits. The treatment cells will be built according to AML technical specifications and will include limestone sand, straw/hay, compost/manure and hardwood bark mulch or equivalents. Barren coal refuse, unvegetated fireclay and/or coal slurry pits are included in this project and will be reclaimed. Adjacent spoil piles will be graded, and spoil material will be pushed over the refuse/slurry/fireclay areas. Limestone Sand and/or Agricultural Lime will be applied to some areas prior to covering with spoil. A borrow pit is shown on the plans for borrow material and this material will be
transported by truck to the #11 mine bench and used as final cover material. These borrow areas will be developed as shown unless exploration pits determine the borrow unsuitable. In which case, the borrow areas will shift slightly but still will lie within the 400-acre project footprint. The total acreage of disturbance will not increase, only change location slightly to make use of better borrow material. AML representatives will make the final determination
whether the borrow material is suitable. Borrow Material will be paid for as shown on the bid schedule for Earthwork Borrow Material on a cubic yard basis for material hauled in a truck from the designated borrow area to the final placement area. This yardage is not included in EARTHWORK – MINE SPOIL, REFUSE. The volume will be estimated by truck count then measured by a before and after survey. This material will be used as a final cover
material in areas where spoil material is not conducive to supporting vegetative growth. Blasting will not be permitted in any work areas. Work for this project will involve the removal of trees measuring over 3-5 inches in diameter at breast height (DBH) at the project location. This cutting shall occur from November 15th March 31st, when the imperiled forest-dwelling bats are either within or in the immediate vicinity of their winter hibernacula. The contractor can burn cleared trees, or in some cases may windrow them. The landowners have been given the opportunity to harvest timber prior to the project, and timber remaining within the 74-acre project limits can be removed from the site by the contractor under this contract.
This project will consist of a new restroom building expansion to provide 1,500 sq ft of additional restroom space. There will also be an exterior shower rinse off area. The site work will consist of providing one new ADA compliant picnic area. There will be some storm water mitigation around the site to help prevent erosion to the picnic areas. Listed as a bid alternate is the replacement of the existing wooden dock with a linear low-density polyethylene dock.
City of Jackson – TopCat Way Housing Development – Contract 2
City of Jackson – TopCat Way Housing Development – Contract 2
Work is generally to include: Construction of streets, storm drainage network, sanitary
sewer network with lift station, water line and other utilities. The installation of
approximately 1239 LF of 8-inch gravity sanitary sewer piping with manholes, one 3
horsepower duplex submersible lift station with telemetry to a second existing lift station.
Installation of approximately 1,940 LF of 8, 15, 18 and 24-inch gravity storm piping that
includes surface inlets, yard drains and manholes. Installation of 1,278 LF of 6-inch
waterline with flushing hydrants, and water meters for 15 house sites. Removal and offsite
disposal of approximately 1,100 cubic yards of existing asphalt road surface and
excess material. Installation of new underground utilities, approximately 2,942 LF of
curb and gutter, and several asphalt streets.
Estimated Length of Project:
(Substantial Completion) + 75 Calendar Days (Final Completion)
The property of Tommy Newman has been impacted by several prelaw mine portals, one of which is partially open with a very large volume of flowing water at the top of the road. Water is making access to home di??icult and is eroding the slope significantly. The property is located at 5142 US- 119 Mayking KY 41837. To reach the site, From intersection of US-119 and KY 15 at Whitesburg travel east approximately 5.192 miles. Make a right turn onto an unmarked gravel road and follow the road to the house site. Site Coordinates: 37.14742603962726° -82.7385113696852°
An off-site PRIOIR DISTURBED waste area included to received excess material. It is a previously disturbed site and was designated as a waste area for a previous AML project, Wendell Fields Phase II which has received ATP. Waste Area Coordinates: 37.134072° -82.767047°
Project limits include 5.2 acres, with an expected disturbance of 1.00 acres within project boundaries; tree disturbance of 0.5 Acres in a stable area. Project limits for the offsite waste area(s) include 2.7 acres, with an expected disturbance of 0.5 acres. No tree disturbance is anticipated at the Waste Area.
The Newman project will be reclaiming Mine Portals on the property. These portals have cause drainage issues along with the washing out of the driveway that connects the residence with the main road below. The property has 4 mine portals behind the bench where the home is located that are affecting the homeowner. Four standard Closures will be installed on the existing mine portals at the appropriate locations. 3 portals will be closed with AML standard wildlife closure.
Landscape Allowance is included to address “in kind”, any shrubbery that is disturbed due to
normal reclamation activities. Structure Removal/Replacement is included to relocate/replace features “in kind” to facilitate normal reclamation activities. Site prep is included as needed to clear existing vegetation. Silt Control is included as an erosion control measure. Earthwork is
included for excavation and transportation to the waste area. This also include all final grade at the site and waste area.
The solution presented for the Newman project includes installing 3 Standard Wildlife Closures to the open mine portals (with 40 linear feet of subdrain beneath the closures) and to open the collapsed mine portal and install 8” HDPE for Drainage. To prevent future drainage problems, the plans are to install 20 linear feet of 18” HDPE with a concrete headwall under the driveway where the mine portal is producing water. Also subdrain behind the Newman residence to ensure drainage moving away from the home. At the outlet of all HDPE pipes, class III backfill will be placed to help with erosion control and washout.
There are no disturbances of streams or bodies of water on this project