RFB-66-27 DMA – RICHMOND AFRC INTERIOR LIGHTING

RFB-66-27 DMA – RICHMOND AFRC INTERIOR LIGHTING

Estimate:
$637,872.00

Estimated Length of Project:
150 (Substantial Completion) + 30 (Final Completion)

This project is a one for one lighting replacement of the Army Forces Reserve Center Facility Buildings and site on the Bluegrass Army Depot Campus. In the Buildings and site, all existing light fixtures will be replaced with new LED light fixtures.

Project Location: Richmond

More Details

RFB-61-27 DJJ-Lake Cumberland YDC Electrical Kitchen & Generator Upgrades

RFB-61-27 DJJ-Lake Cumberland YDC Electrical Kitchen & Generator Upgrades

Estimate:
$175,824.00

Estimated Length of Project:
90 (Substantial Completion) + 15 (Final Completion)

The Contractor shall provide all of the materials and perform all the work described in the Specifications and/or shown on the Drawings. The Federal Pacific Switchgear including panels, contractors and disconnects of the Lake Cumberland YDC Facility will be removed and replaced per the National Electrical Code. In addition, a standby emergency generator will be installed to provide backup power of the Old Weld Shop Building which serves power for the Sewage Treatment Plant. The Contractor shall provide new concrete for access to the Generator, as well as the Propane Storage Tank with concrete-filled pipe bollard protection.
The Owner’s preferred daily work schedule shall be Monday-Friday 8 hour/day. There are no Contractor working days on Saturday-Sunday. A 48 hour notification is required for any outage of any existing utility including the Chilled Water and Heating Water Systems. Any damaged utility by the Contractor must be put back into service immediately.

Project Location: Monticello

More Details

RFB-64-27 DMA – BURLINGTON RC INTERIOR LIGHTING

RFB-64-27 DMA – BURLINGTON RC INTERIOR LIGHTING

Estimate:
$764,137.00

Estimated Length of Project:
180 (Substantial Completion) + 30 (Final Completion)

Lighting: Replace all interior & exterior lighting with new LED lights. Replace room by room occupancy sensor controls with new controls (local only, no integration to BAS).

Project Location: Burlington

More Details

RFB-63-27 DOC – KSP REPAIR REPLACE HVAC SYSTEM 4 CELL HOUSE

RFB-63-27 DOC – KSP REPAIR REPLACE HVAC SYSTEM 4 CELL HOUSE

Estimate:
$3,089,000.00

Estimated Length of Project:
180 (Substantial Completion) + 30 (Final Completion)

The Project involves the replacement of the HVAC systems that serve the KSP 4 Cell House. A phased work approach is specified that includes the initial installation of an RTU at grade and an ERV unit in the Attic, removal of the AHU from the Basement, selected removal/ modification of ductwork throughout the building, installation of ductwork in the Basement and Attic, and replacement of supply air ductwork to each Cell. Structural work includes Attic slab framing, supports, and slab penetration reinforcement. Architectural work includes repair and modification of selected windows, revisions to windows for mounting of exhaust fans. Installation of a natural gas line to the RTU and electrical services to HVAC equipment. A new smoke evacuation system will be provided. The work of the Project is considered within the KSP security boundary. All work must be performed in a sequenced effort coordinated with the KSP.

Project Location: Eddyville

More Details

RFB-65-27 DJJ – Adair Emergency Chiller Replacement

RFB-65-27 DJJ – Adair Emergency Chiller Replacement

Estimate:
$415,345.00

Estimated Length of Project:
120 (Substantial Completion) + 30 (Final Completion)

The Contractor shall provide all of the materials and perform all the work described in the Specifications and/or shown on the Drawings. The Chiller and Chilled Water System of the ADAIR YDC Facility will be removed and replaced per the International Mechanical Code, ASHRAE, Kentucky Building Code with Current Revisions, Americans with Disabilities Act, International Building Code, and National Electrical Code.
The Contractor shall remove and take ownership of the existing chiller. The contractor shall disconnect the existing chiller from power and control and, disconnect the existing chiller from piping and mounting. Remove the existing chiller from its installed location and make the location ready for the new chiller described in the following. Make legal and lawful disposal of the chiller, which involves recycling of the unit beginning with refrigerant recovery and dismantling of the assembly for recycling or other appropriate disposition.
The Contractor shall provide a temporary Chiller while the existing Chiller is removed and a new Chiller including the Microprocessor controlled, multiple-scroll compressor, air-cooled, chiller of the scheduled capacities as shown and indicated on the Drawings, including but not limited to: chiller package, electrical power and control connections, and chilled water connections.
The Owner’s preferred daily work schedule shall be Monday-Friday 8 hour/day. There are no Contractor working days on Saturday-Sunday. A 48 hour notification is required for any outage of any existing utility including the Chilled Water and Heating Water Systems. Any damaged utility by the Contractor must be put back into service immediately.

Project Location: Columbia

More Details

KCTCS – Somerset Community College Replace Laurel South Building

KCTCS – Somerset Community College Replace Laurel South Building

Re-bid of Bid Package #9 Ceramic Tile and Bid Package #10 Resinous Terrazzo Flooring only.

The KCTCS – Somerset Community College Replace Laurel South Building project consists of a new technical
education building on a mostly cleared site located on the existing London Campus of Somerset Community
College. The building will be approximately 53,000 square feet and will include Automotive and Diesel
Technology, Construction Technology, HVAC, Electrical and Electronics, Industrial Maintenance Technology, and
Welding labs as well as classrooms, administration, and building support spaces. The building exterior will include a
mix of masonry, including some stone accents, insulated metal panel systems, and curtain wall framing. The roofing
will be a two-ply modified bitumen system. The project is designed with the intent to achieve LEED Silver
certification. Commissioning of the building systems and building envelope are included in the scope of work.
Plumbing systems consist of domestic water, sanitary sewer, and storm sewer. Compressed air and welding gas
systems are also present in labs. The HVAC system is largely geothermal water-source heat pumps and energy
recovery units. Electric heaters, mini-split heat pump systems, and direct gas fired heater with exhaust ventilation
will also be utilized. The electrical system will include incoming utility infrastructure and an emergency natural gas
generator. Other related systems include fire alarm, data, access controls infrastructure, local sound system
infrastructure, and infrastructure for classroom technology equipment.

Project Location: London, Kentucky

More Details

RFB-51-27 DMA – PRESTONSBURG RC ROOF

RFB-51-27 DMA – PRESTONSBURG RC ROOF

Estimate:
$482,215.25

Estimated Length of Project:
90 (Substantial Completion) + 30 (Final Completion)

Demo all existing layers of SBS roof system and insulation down to the deck.
Demo all existing edge metal and downspouts.
Provide new roof system consisting of new cap sheet and base sheet over min 4.5 inches or polyisocyanurate rigid insulation over existing deck.
Existing metal deck is assumed to be undamaged. Consider an allowance to replace discovered conditions of metal deck.
Keep existing any and all existing roof top equipment and curbs. Flash new around curbs.
Provide new sealants in areas needed at brick joints above roof.
Tuckpoint select areas of existing mortar joints adjacent to new roof areas.
Provide new edge metal and downspouts.

Project Location: Prestonsburg

More Details

RFB-46-27 KSU – Betty White Building Roof Replacement

RFB-46-27 KSU – Betty White Building Roof Replacement

Estimate:
$260,000.00

Estimated Length of Project:
60 (Substantial Completion) + 30 (Final Completion)

1. Betty White Health Center:
A. Tear off existing built-up roof membrane, sheet metal, metal counter flashings, and roof
components as indicated.
B. Install new tapered insulation system with insulation adhesive.
C. Install new 2-Ply SBS-Modified Bituminous Membrane system (Cold/Cold).
D. Demo skylights, screen wall and associated electrical conduit and boxes.
E. Install new lightning protection system; use existing grounding locations.

Project Location: Frankfort

More Details

RFB-44-27 Parks – JW Conference Center Upgrades

RFB-44-27 Parks – JW Conference Center Upgrades

Estimate:
$907,522.00

Estimated Length of Project:
120 (Substantial Completion) + 30 (Final Completion)

The interiors of the existing Conference Center at Jenny Wiley State Park are being upgraded with new finishes and other improvements throughout the public spaces. Work includes selective demolition throughout, with most existing finishes being completely removed. New work includes new flooring, painting, wallcoverings and window treatments. As an Alternate, the men’s restroom will receive new tile floors and new acoustic ceilings.
Mechanical work includes the replacement of many of the existing grilles. A new drinking fountain will replace the existing. All lighting in the public spaces will be new. A new audio-visual system includes projector, motorized screen, sound system and lighting controls.

Project Location: Prestonsburg

More Details

RFB-49-27 EDU – KSD Demo of Various Buildings

RFB-49-27 EDU – KSD Demo of Various Buildings

Estimate:
$175,376.00

Estimated Length of Project:
90 (Substantial Completion) + 30 (Final Completion)

The project involves demolition of the former Boiler House and Laundry Building at the Kentucky School for the Deaf in Danville, KY. The approximately 6,300 square foot masonry building, including the chimney, foundations, floor slabs, and associated site improvements, will be demolished and removed. Work includes removal of existing trees, stumps, fencing, site lighting, miscellaneous concrete pads, and other appurtenances within the project limits. Masonry and concrete demolition debris will be crushed on-site and reused as compacted fill for backfilling excavated areas. The site will be restored with final grading, positive drainage, and seeding upon completion of the demolition work.

Project Location: Danville

More Details

RFB-50-27 EEC-AML-Vogue Refuse Reclamation Project

RFB-50-27 EEC-AML-Vogue Refuse Reclamation Project

Estimated Length of Project:
(Substantial Completion) + 420 Calendar Days (Final Completion)

The 25034AMLBAML (Vogue Slurry AML Reclamation Project) is in Muhlenberg County, Kentucky, at North 37°16’52.68″, West 87°20’50.79″ and will reclaim approximately 44 acres adversely affected by previous coal mining operations. The total project viewshed is 180 acres, and only 44 acres proposed for construction will be within those 180 acres. The entire 180 acres has been disturbed by previous pre-law surface mining activities. The project consists of eliminating approximately 1.1 acres of an acid pit which will be backfilled with adjacent onsite mine spoil material (12 acres) and capped with the best material
available on site. The water in the pit will be treated and raised to a pH of 6 or greater prior to release and backfilling of the pit in accordance with KYDAML Technical Specifications. Water tests taken on December 5, 2025, show the water in the pit with a pH of 6.7 and iron over 10 mg/l. Acidic spoils adjacent to the pit shall be used first in backfilling the pit to eliminate the acid forming potential of these materials. This effort will require additional effort and may require double handling of some soils. Spoil ridges in the designated areas will be graded at a maximum 3:1 slope with the best available material brought to the surface. Payment for this work will be by the cubic yard for “Mine Spoil Excavation”

Project Location: Muhlenberg

More Details

FW-001-27 – KDFWR – FILO Middle Creek I

FW-001-27 – KDFWR – FILO Middle Creek I

Estimate:
$3,173,834.00

Estimated Length of Project:
1/1/2029 (Substantial Completion) + 30 (Final Completion)

The proposed work consists of restoration and enhancement, using Natural Channel Design techniques, of approximately 23,539 linear feet of stream including a portion of Middle Creek and related tributaries. Tasks to be performed to achieve project goals include reshaping of existing channels; re-establishment of new channels with stable dimensions; construction of in-stream structures; preparation of soil for seeding; native planting and seeding; installation of erosion control fabric and mulch; and harvesting, transporting, installing, and maintaining live stake and vegetative materials. Middle Creek and the related tributaries are first through fifth order streams with ephemeral, intermittent, and perennial flow regimes. The restoration project will re-establish approximately 8,671 feet of channel, rehabilitate 7,025 feet, enhance 5,569 feet, and provide riparian habitat enhancement along approximately 2,274 feet. Restoration will include in-stream structures such as wood toe, brush toe, rock riffles, brush riffles, brush runs, woody debris drops, headwater channel, and log vanes, as well as vegetation of the stream banks and improvement to the forested riparian corridor along the streams. In addition, this project will re-establish 0.68 acres of wetland, rehab 1.31 acres, enhance 0.33 acres, and preserve 0.33 acres.

Project Location:

More Details

RFB-45-27 DMA – RUSSELLVILLE RENOVATIONS

RFB-45-27 DMA – RUSSELLVILLE RENOVATIONS

Estimate:
$1,964,103.00

Estimated Length of Project:
325 (Substantial Completion) + 30 (Final Completion)

Renovation of approximately 16,400 SF of existing Armory facility. This renovation includes renovations of existing restrooms & showers, classrooms, office spaces, storage, personnel lockers, new office and IT spaces, and food service area. Work includes replacement of existing HVAC units, replacement of storm and sanitary sewer piping, and obsolete lighting fixtures.

Project Location: Russellville

More Details

RFB-40-27 KSP-KET Tower Site Electrical Upgrades – E1

RFB-40-27 KSP-KET Tower Site Electrical Upgrades – E1

Estimate:
$570,000.00

Estimated Length of Project:
150 (Substantial Completion) + 30 (Final Completion)

This project includes modifications to existing electrical systems serving Kentucky State Police facilities located at four existing KET sites. Electrical renovations at each site generally include:
1. New 50 kVA transformer.
2. New 200 amp panelboard.
3. New 200 amp manual transfer switch.
4. New surge protection panel.
5. Miscellaneous circuit breakers, conduit and conductors.

Project Location: Various

More Details

RFB-10-27 DMA – Leitchfield RC Interior Upgrade

RFB-10-27 DMA – Leitchfield RC Interior Upgrade

Estimate:
$1,909,575.00

Estimated Length of Project:
160 (Substantial Completion) + 30 (Final Completion)

The project consists of an interior renovation of the existing building. The restrooms will have updated finishes and the men’s side will include the demolition and reconstruction of new showers and drying areas and adding an ADA accessible shower. The project includes repurposing space for a new lactation room. Most interior doors in the building are to be replaced with new doors, and new door hardware. Interior finishes include new ceilings,
wall paint, and flooring. New resinous flooring, and carpet will be included. Installation of additional OCIE storage lockers is included in the project. MEP scope of this project includes major renovations of the building systems. Replacing plumbing DWV and water line piping as well as replacing plumbing fixtures. All HVAC systems and related infrastructure are to be replaced. Lighting will be replaced with new LED, electrical distribution systems modified to accommodate new layouts and equipment, new cable trays and cable will be installed, all existing cables will be replaced, wireless access point will be installed in all areas, and the life safety systems will be replaced.

Project Location: Leitchfield

More Details

RFB-43-27 Parks – CO – East Wastewater Collections Upgrades-Natural Bridge – PH II

RFB-43-27 Parks – CO – East Wastewater Collections Upgrades-Natural Bridge – PH II

Estimate:
$1,050,000.00

Estimated Length of Project:
180 (Substantial Completion) + 30 (Final Completion)

The project includes the following:
1. Renovate two existing duplex submersible wastewater pump stations.
2. Renovate existing 6-ft diameter pump station wet wells.
3. Install new 8-inch PVC gravity sewer and associated manholes utilizing open excavation.
4. Install new 4-inch PVC sewer lateral.

Project Location: Slade

More Details

RFB-41-27 KYTC – D-9 Carter County East Bound Renovation

RFB-41-27 KYTC – D-9 Carter County East Bound Renovation

Estimate:
$668,152.00

Estimated Length of Project:
150 (Substantial Completion) + 30 (Final Completion)

The Work includes extensive interior and exterior renovations to the East Bound Rest Area facility on I-64 Mile Marker 173.5 in Carter County, Kentucky. All plumbing fixtures and piping (including below slab waste) will be replaced. HVAC system including duct work will be replaced. Electrical and Data Voice wiring and devices will be replaced. Various exterior site improvements will be included. Floor and wall base will receive new M.M.A. coating system at Restroom Building. Restroom walls will receive new ceramic tile. Restroom building will receive new FRP doors and frames. See drawings and specifications for additional information.

Project Location: Carter County

More Details

RFB-39-27 RE-AD of RFB-281-26 KAC- Roof Replacement

RFB-39-27 RE-AD of RFB-281-26 KAC- Roof Replacement

Estimate:
$835,006.00

Estimated Length of Project:
150 (Substantial Completion) + 30 (Final Completion)

The Work includes replacing the existing roof systems on the Kentucky Artisan Center in Berea, Kentucky. Roof systems to be replaced include SBS Modified Bitumen membrane system, slate shingles replaced with asphalt shingles with a slate shingle appearance, and standing seam copper roofing replaced with concealed clip, pre-finished standing seam metal roofing. Cut limestone capstones will be cleaned throughout the entire facility. Small amount of aluminum storefront system will be replaced at roof gables.

Project Location: Berea

More Details

RFB-42-27 DOC – NTC – Restricted Housing Unit Stairs

RFB-42-27 DOC – NTC – Restricted Housing Unit Stairs

Estimate:
$103,116.00

Estimated Length of Project:
90 (Substantial Completion) + 14 (Final Completion)

Project is for the Stair replacement of the Restrictive Housing Unit Located at the Northpoint Training Facility in Danville, Kentucky
Project Program:
Replacement of three( 3) stairs. Two of the stairs are exterior fire escape stairs at the end of each dormitory wing. One stair is an exterior stair to the mechanical room.
A pre-construction phase will be included prior to actual construction for submittals, material ordering and delivery. All materials must be on-site or available at the start of construction. Contractor shall provide temporary stair out of each dormitory between the demolition of the existing stair and the installation of the new stair.
All personnel on the project site must pass background checks before being allowed to work within the facility. Contractors and subcontractors must adhere to the Department of Corrections rules for construction which are indicated in the specifications.

Project Location: Danville

More Details

Jeffersonville Board of Public Works – Allison Lane HAWK Signal

Jeffersonville Board of Public Works – Allison Lane HAWK Signal

The Project includes the following Work:

The installation of a HAWK signal at the intersection of Allison Lane and Wooded Way. The
work shall include all items necessary to construct the HAWK signal and all other services
required to complete this project, including asphalt roadway restoration, grass restoration and
all other items shown in the plans and mentioned in these specifications for a complete project.

Project Location: Jeffersonville, Indiana

More Details

RFB-36-27 KYTC – Clark Co EB Rest Area Remodel

RFB-36-27 KYTC – Clark Co EB Rest Area Remodel

Estimate:
$5,495,482.00

Estimated Length of Project:
280 (Substantial Completion) + 30 (Final Completion)

The project consists of a full renovation of the existing Rest Area & Vending Structures along with approximately 2 miles of off-site utilities. The primary architectural intervention in the existing design is the addition of two new accessible restrooms and an entry vestibule for the existing restrooms at the ends of the existing entry concourse. The existing concrete slabs are being removed as part of the structural stabilization which includes new grade beams, helical piles, and new floor slabs. All areas will receive a new epoxy terrazzo floor, and the entry shall include wall bases. The curved, structural CMU wall surrounding the restrooms will remain and receive new plaster finish and paint. The tile mural of the state of Kentucky will be left in place and protected during construction. Soffits and ceilings will be rebuilt to match the existing design. All existing single glazed windows will be removed and replaced with insulated storefront units that match the mullion layout of the original design and will include the lateral reinforcing at the mullions over the concrete wall panels that were part of the original design. Glazing at the new, accessible restrooms and vestibules will have a translucent film of the third surface of the glazing units for privacy. The design will be altered to add two roll-up doors connecting the maintenance area in back to each of the restrooms. In the restrooms, the existing masonry partitions will be removed and replaced with new ceiling-braced, stainless steel toilet partitions. New ADA toilet walls shall be porcelain glazed CMU (both double and single faced units). A 2” veneer of the same glazed faced units will be used in the restroom interiors. The existing opening through the 8” CMU wall will have new steel frame to accommodate the new wall thickness and support the new opening for the roll-up doors. Damaged concrete wall panels will be repaired to match the existing finishes. The existing roof will be replaced and the drum on top will be capped. The existing Vending Shed will have its trusses removed to bearing level. A wood framed storage addition with masonry veneer will be constructed at the rear of the shed, replacing the free-standing prefab shed on site. The new storage room behind the vending shed will be insulated and electric heat to prevent freezing of stored items. The entire vending shed will receive new hipped trusses with a prefinished standing seam metal roof, fascia trim, soffit panels, and ceiling panels.
Plumbing work consists of the following: Demolition of existing sanitary piping back to the main line outside of the building. All new PVC sanitary piping will be provided and connected back to this point. Removal of all existing domestic water piping with new copper piping and insulation. Removal of existing plumbing fixtures and replaced with new “low flow” fixtures. Removal the existing well tank and connected accessories. A new pressure tank / pump
system will be provided. Removal of the existing water heater and replaced with new water heater. The HVAC system will need to be replaced in order to meet the required recommendations of the existing structure, roof, and floor slabs. A new 5-ton heat pump will be located in same location as existing in Mechanical Room. If approved, the heat pump will be specified as a water source heat pump with piping to two geothermal wells. New ductwork will serve all areas to provide heating and cooling. New exhaust fans in restrooms will have new duct routed to an exterior wall to avoid roof penetration. Test and balance costs for new exhaust fan and HVAC unit have been included. Electrical work includes the following: A new Main Distribution Electrical Panel and new sub panels as required. All new electrical circuits to receptacles, equipment, HVAC lighting and vending machine area as required. New LED lighting system throughout. New lighting controls – Digital time clock, occupancy sensors and keyed light switches as required to best end user control. New LED exit signs, new LED dual head emergency lighting and new LED exterior egress lighting to create a path of egress from the interior spaces to the outside of the building. New lighting and lighting controls systems will be compliant with the currently adopted International Energy Conversation Code (IECC).
Site & off-site utility work includes the following: All existing asphalt will be replaced with heavy duty asphalt beginning at the outer edges of the highway shoulder and extending throughout the parking areas. In some areas a full profile replacement may be required and in other areas a mill and overlay may meet KYTC highway specifications. The asphalt elevation on the south side of the car parking lot will be raised to facilitate a normative curb height of 6 inches. Currently the curb height is closer to 10 inches which is a trip hazard for pedestrians. New concrete curb and gutter on the south side of the parking lot will be replaced along with existing pedestrian walkways. All concrete walkways and stairs will be replaced. A new pedestrian connection will join the circular and vending machine buildings. Old handrails will be replaced to meet current building code standards. Signs that interfere with demolition and construction will be removed and replaced according to the Owner’s preference for placement. One pair of bollards that protect the flagpole will be removed and replaced with new concrete-filled bollards. The current dumpster site (asphalt and wood fence) is dilapidated and will be demolished. A more attractive and secure dumpster area will be relocated east of the buildings consisting of a new 8-inch heavy duty concrete dumpster pad, 8-foot height CMU screen wall, two chain link gates at the opening and two concrete-filled bollards to protect the wall. The current storage shed next to the vending machine building will be demolished and replaced with an addition built onto the back of the building. To improve pedestrian circulation, a new concrete walk will connect the vending machine and circular buildings. The aging water and sanitary sewer line that extend to nearby Winchester will be replaced in their entirety. Both lines are approximately two miles long. The sanitary sewer lift station will be replaced as well. Utilities within the site—both sanitary sewer and water—will be replaced.

Project Location: Clark County

More Details

RFB-22-27 CO-Multi-Park Structural Investigation East -GB

RFB-22-27 CO-Multi-Park Structural Investigation East -GB

Estimate:
$960,300.00

Estimated Length of Project:
180 (Substantial Completion) + 30 (Final Completion)

The project consists of the repair and replacement of various deteriorated concrete elements including concrete retaining walls, slabs-on-grade, and elevated slabs. The top of a portion of the existing concrete retaining wall is to be removed to allow new slab-on-grade to extend over the wall, allowing for expanded views from the bar area. Sidewalks / ramps are to be modified on the north side of the building to address varying finish floor elevations.
The project also includes removal and replacement of three sets of stairs. Two sets of existing wooden stairs at the far north and south ends of the building will be removed and replaced with new steel stringers with precast concrete treads. An existing timber-framed stair on the west side of the building will be removed and replaced with a similar timber-framed stair.

Project Location: Carrollton

More Details

Bullitt Hills and Hillview #1 WWTP Eliminations

Bullitt Hills and Hillview #1 WWTP Eliminations

INVITATION TO BID

Sealed Bids will be received electronically by Louisville and Jefferson County Metropolitan Sewer District, for the construction of Contract No. 17257 Bullitt Hills and Hillview #1 WWTP Eliminations, Budget ID No. Y22146, Drawing Sheet No. 1-59, until 11:00am, Local Time, Tuesday August 18th, 2026, and will be publicly opened and read at that time. The public may attend the bid opening via teleconference call at 502-654-8113 (Dial-in Number) Conference ID: 707 341 584#.

MSD is using a web-based portal for accepting and evaluating bid proposals digitally at http://louisvillemsd.bonfirehub.com/portal for this Invitation to Bid. Documents may be uploaded at any time during the open period indicated for each proposal.

Description and location of Project: The project includes the construction of the new Zoneton Road Pump Station near the intersection of Preston Highway and Zoneton Road in Bullitt County, Kentucky. The pump station will receive flows via new gravity sewers from both the Bullitt Hills WWTP and Hillview #1 WWTP and pump flow through a 14-inch force main to the Derek R. Guthrie WQTC via the new Mud Lane Interceptor (by others). The project includes the elimination and decommissioning of the Bullitt Hills WWTP, Hillview #1 WWTP, and existing Zoneton Road Pump Station.

Procurement for this project will be subject to DOW Procurement Guidance including the Davis Bacon Act. This project is being funded in part by an SRF loan. Bidders must comply with Title VI of the Civil Rights Act of 1964, the Anti-Kickback Act, and the Contract Work Hours Standard Act. Bidders must comply with the President’s Executive Order No. 11246 as amended, which prohibits discrimination in employment regarding race, creed, color, sex or national origin. This project will be in compliance with Executive Order 11246 (Equal Employment Opportunity) as amended. Contractor/Subcontractors will comply with 41 CFR 60-4, in regard to affirmative action, to insure equal opportunity to females and minorities and will apply the time tables and goals set forth in 41 CFR 60-4. Bidder will make positive efforts to use small, minority, women owned and disadvantaged businesses.

All work shall be done in accordance to MSD’s Standard Specifications.

There will be a mandatory pre-bid meeting held for this project via Teams on Tuesday, July 14th, 2026 at 9:00am local time. There will be an optional site visit to the project area following the mandatory pre-bid Teams meeting.

Microsoft Teams meeting:
Join: https://teams.microsoft.com/meet/281913816625540?p=CwaaGMf5hLMfch7POG

Meeting ID: 281 913 816 625 540
Passcode: gv3B9iN2

The Engineer’s Construction Cost Estimate for this project is between $15,000,000.00 and $17,000,000.00.

Proposal forms, including Specifications and Instructions for Bidders, may be obtained from MSD’s designated web portal at http://louisvillemsd.bonfirehub.com/portal.

Persons wishing to view the bid documents may do so online at http://louisvillemsd.bonfirehub.com/portal or at the following locations: Builders Exchange of Louisville, Inc., 2300 Meadow Drive; Associated Builders & Contractors of Kentuckiana, 1810 Taylor Avenue; and F. W. Dodge, 1812 Taylor Avenue; all located in Louisville, Kentucky; and the Associated General Contractors of Kentucky, 2321 Fortune Drive, Suite 112, Lexington, Kentucky.

The Project Manager for this Invitation to Bid is Joey Ashby. All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s designated web portal at http://louisvillemsd.bonfirehub.com/portal. Questions received less than ten (10) days prior to the date for opening of bids may not be answered. Only answers by formal written Addenda posted on MSD’s designated web portal will be binding. Oral and other interpretations or clarifications will be without legal effect. All inquiries and questions between the bid opening and the contract awarding shall be directed, in writing, to MSD’s Chief Engineer, David W. Johnson, P.E.

MSD SUPPLIER DIVERSITY MINORITY AND WOMAN BUSINESS ENTERPRISE PROGRAM POLICY AND PROCEDURES MANUAL (MBE/WBE PROGRAM) – FOR CONSTRUCTION CONTRACTS $200,000 AND GREATER for Minority Business Enterprise (MBE) and Woman Business Enterprise (WBE) subcontracting participation. Effective January 1, 2025, MSD has adopted and implemented the revised MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual, modifying the MBE and WBE participation goals on construction services and construction-related services, in accordance with the MSD Disparity Study (Study). The Study provided the factual predicate for MSD to establish new MBE and WBE goals in MSD contracting. The MSD MBE\WBE Program modified subcontracting goals are listed below:

If selected as applicable below, the Contractor must subcontract at least 18.0% of the total amount of the Contract Bid price to certified African American minority-owned businesses, at least 2.0% of the total amount of the Contract Bid price to a certified Asian-Indian American minority-owned businesses, and at least 15.0% total amount of the Contract Bid price to certified Caucasian Female businesses. If the Contractor is unable to meet the goals, they must demonstrate adequate “GOOD FAITH EFFORTS” in accordance with the MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual (MBE/WBE Program) – (see MSD MBE/WBE Program – Construction Subcontracting Goal Documents and Forms at http://louisvillemsd.org/SupplierDiversity/forms.

All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s designated web portal at http://louisvillemsd.bonfirehub.com/portal.

MSD SUPPLIER DIVERSITY PROGRAM: Applicable

The revised MSD Supplier Diversity Minority and Women Business Enterprise Program Policy and Procedures Manual (MBE/WBE Program) is effective January 1, 2025. If selected as “Applicable” or “Applicable, Partial Waiver” above, the goals are as follows:

18.0% MBE – African American participation
2.0% MBE – Asian-Indian American participation
15.0% WBE – Caucasian Female participation

MBE and WBE businesses are encouraged to bid on this project as a prime contractor.

MSD BID DISCOUNT: Applicable

This MSD construction project is bid and advertised as: check applicable below

Construction Services: x
Construction-related Services:

LOCAL LABOR COMMITMENT PREFERENCE: Yes

COMMUNITY BENEFITS PROGRAM: Yes

The contract will be awarded on the basis of the lowest, responsive, responsible bid, subject to the approval of the MSD Board. MSD reserves the right to reject any or all bids or waive any informality in any bid.

LOUISVILLE AND JEFFERSON COUNTY

METROPOLITAN SEWER DISTRICT

David Johnson, P.E.
Chief Engineer

Rene’ Lindsay, CPPO
One Water Chief Procurement Officer

Project Location: Louisville, KY

More Details

Pennsylvania Run Road Pump Station

Pennsylvania Run Road Pump Station

INVITATION TO BID

Sealed Bids will be received electronically by Louisville and Jefferson County Metropolitan Sewer District, for the construction of Pennsylvania Run Road Pump Station, Contract No. 17418, Budget ID No. H20021, Drawing Record No. / Sheet No. 17418 / 1-116, until 10am, Local Time, September 1st, 2026, and will be publicly opened and read at that time. The public may attend the bid opening via teleconference call at 502-654-8113 (Dial-in Number) Conference ID: 892 740 470#.

MSD is using a web-based portal for accepting and evaluating bid proposals digitally at http://louisvillemsd.bonfirehub.com/portal for this Invitation to Bid. Documents may be uploaded at any time during the open period indicated for each proposal.

Description and location of Project: This Contract provides for the demolition of the existing Admiral Way Pump Station, as well as the construction of the new Pennsylvania Run Road Pump Station with ancillary support structures, new 5.5-milliongallon circular concrete storage tank, new sanitary sewers to reroute flows to new pump station site, and new access road. This contract also provides for all site clearing, earthwork, and other appurtenant work. All work shall be done in accordance to MSD’s Standard Specifications.

There will be a mandatory pre-bid meeting held for this project. The mandatory pre-bid meeting will be held on Microsoft Team for this project at 11:00AM, Local Time, on Tuesday July 21, 2026.

https://teams.microsoft.com/meet/270442232297501?p=NzqmTJuqmYQtkIlW30

Meeting ID: 270 442 232 297 501
Passcode: o5uL6zA2
+1 502-654-8113,,138038782#
A voluntary site visit may take place following the mandatory pre-bid meeting at MSD’s discretion. Contractors are responsible for providing their own personal protective equipment.

The Engineer’s Construction Cost Estimate for this project is between $25,000,000.00 and $30,000,000.00.

Proposal forms, including Specifications and Instructions for Bidders, may be obtained from MSD’s designated web portal at http://louisvillemsd.bonfirehub.com/portal.

Persons wishing to view the bid documents may do so online at http://louisvillemsd.bonfirehub.com/portal or at the following locations: Builders Exchange of Louisville, Inc., 2300 Meadow Drive; Associated Builders & Contractors of Kentuckiana, 1810 Taylor Avenue; and F. W. Dodge, 1812 Taylor Avenue; all located in Louisville, Kentucky; and the Associated General Contractors of Kentucky, 2321 Fortune Drive, Suite 112, Lexington, Kentucky.

The Project Manager for this Invitation to Bid is Quinn Corcoran. All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s designated web portal at http://louisvillemsd.bonfirehub.com/portal. Questions received less than ten (10) days prior to the date for opening of bids may not be answered. Only answers by formal written Addenda posted on MSD’s designated web portal will be binding. Oral and other interpretations or clarifications will be without legal effect. All inquiries and questions between the bid opening and the contract awarding shall be directed, in writing, to MSD’s Chief Engineer, David W. Johnson, P.E.

MSD SUPPLIER DIVERSITY MINORITY AND WOMAN BUSINESS ENTERPRISE PROGRAM POLICY AND PROCEDURES MANUAL (MBE/WBE PROGRAM) – FOR CONSTRUCTION CONTRACTS $200,000 AND GREATER for Minority Business Enterprise (MBE) and Woman Business Enterprise (WBE) subcontracting participation. Effective January 1, 2025, MSD has adopted and implemented the revised MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual, modifying the MBE and WBE participation goals on construction services and construction-related services, in accordance with the MSD Disparity Study (Study). The Study provided the factual predicate for MSD to establish new MBE and WBE goals in MSD contracting. The MSD MBE\WBE Program modified subcontracting goals are listed below:

If selected as applicable below, the Contractor must subcontract at least 18.0% of the total amount of the Contract Bid price to certified African American minority-owned businesses, at least 2.0% of the total amount of the Contract Bid price to a certified Asian-Indian American minority-owned businesses, and at least 15.0% total amount of the Contract Bid price to certified Caucasian Female businesses. If the Contractor is unable to meet the goals, they must demonstrate adequate “GOOD FAITH EFFORTS” in accordance with the MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual (MBE/WBE Program) – (see MSD MBE/WBE Program – Construction Subcontracting Goal Documents and Forms at http://louisvillemsd.org/SupplierDiversity/forms.

All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s designated web portal at http://louisvillemsd.bonfirehub.com/portal.

MSD SUPPLIER DIVERSITY PROGRAM: Applicable

The revised MSD Supplier Diversity Minority and Women Business Enterprise Program Policy and Procedures Manual (MBE/WBE Program) is effective January 1, 2025. If selected as “Applicable” or “Applicable, Partial Waiver” above, the goals are as follows:

18.0% MBE – African American participation
2.0% MBE – Asian-Indian American participation
15.0% WBE – Caucasian Female participation

MBE and WBE businesses are encouraged to bid on this project as a prime contractor.

MSD BID DISCOUNT: Not Applicable

This MSD construction project is bid and advertised as: check applicable below

Construction Services:
Construction-related Services:

LOCAL LABOR COMMITMENT PREFERENCE: Yes

COMMUNITY BENEFITS PROGRAM: Yes

The contract will be awarded on the basis of the lowest, responsive, responsible bid, subject to the approval of the MSD Board. MSD reserves the right to reject any or all bids or waive any informality in any bid.

LOUISVILLE AND JEFFERSON COUNTY

METROPOLITAN SEWER DISTRICT

David Johnson, P.E.
Chief Engineer

Rene’ Lindsay, CPPO
One Water Chief Procurement Officer

Project Location: Louisville, KY

More Details

RFB-37-27 KVA – THVC Replace Exterior Lighting

RFB-37-27 KVA – THVC Replace Exterior Lighting

Estimate:
$851,000.00

Estimated Length of Project:
150 (Substantial Completion) + 30 (Final Completion)

Removal of existing exterior building mounted lighting and ground mounted light poles throughout campus. Provide all new pole foundations, poles, lighting, and circuitry for new lighting systems. Selected exterior soffits in porte-cochere and other locations will be replaced with new. Front porte-cochere shall have existing masonry wrap columns removed and new column wraps installed along with new ceiling to hide conduit and camera system conduits.

Project Location: Wilmore

More Details