Masonry Tuckpointing, Hazelwood Center, Building 101
RFB-80-12
The project consists of miscellaneous re-pointing of masonry joints, replacing various
damaged concrete lintels, installing expansion joint fillers, cleaning and re-sealing of
window perimeters & cleaning and sealing of masonry walls. Alternate #1 consists of
miscellaneous repairs to EIFS, cleaning and re-sealing of control joints and window
perimeters, re-pointing various masonry joints and cleaning and sealing of EIFS and
masonry.
Highway Maintenance Garage, KY Transportation Cabinet
RFB-89-12
8,000 sq. ft. Maintenance Garage facility for the Transportation Cabinet near
Hodgenville, Kentucky. Sitework includes perimeter chain link security fence, erosion
control, rough and finish grading, storm water collection and detention structures and
off-site tie in to local sanitary sewer system. The building structure is pre-engineered
metal with insulated metal wall panels and concealed fastener, standing seam metal
roof. Interior partitions are light gauge metal stud framing with 5/8” GWB each side and
batt insulation. Facilities includes two restrooms and a handicap accessible shower
compartment, plumbing fixtures and accessories. Kitchen area in Crew Room includes
base and wall cabinets and kitchen appliances. Finishes include paint on gypsum
panels, vinyl floor tile, suspended acoustic ceiling tile, and densified ground concrete.
Re-Roof District #6 Office Building, Kentucky Transportation Cabinet
RFB-74-12
This project consists of the complete demolition and removal of the roof at the District
Office Building, District #6 located in Kenton Co., Covington, Ky. and the replacement
with a thermo plastic membrane roof, over tapered insulation, all flashings, drip edges,
anchors and accessories for a water tight system. The building is approximately 10,300
square feet.
Emergency Generator District 12 Office, Kentucky Transportation Cabinet
RFB-87-12
This project consists of installing a 175 KW, 208/120 volt, three phase, four wire, wye, emergency standby diesel generator with a 322 gallon base fuel tank and an 600 amp, four pole, automatic transfer switch (ATS) for the Pikeville District Twelve Office located at 109 Loraine Street, Pikeville, Kentucky 41501. The generator and ATS will be provided by the Commonwealth of Kentucky through a Master Agreement with Whayne Power Systems. The contractor will furnish and install a concrete pad for the generator and ATS. The generator and ATS will be delivered FOB to the District Twelve Office. The contract includes unloading and installing the new generator and ATS. The new generator will serve all building loads when utility power is lost. The District Office is served from pole mounted transformers. The underground service will be rearranged at the riser pole to include the ATS. A short duration outage will be used to cutover to the new service arrangement. Coordination with American Electric Power, Whayne Power Systems, and District Twelve Office personnel is required. All work will be preformed outside the District Twelve Office building and in the main electrical/mechanical equipment room. Eighty calendar days will be allowed for the construction. Generator and ATS have been ordered. Experience in the construction of underground and overhead electrical systems is required.
Emergency Generator District 12 Office, Kentucky Transportation Cabinet
RFB-87-12
This project consists of installing a 175 KW, 208/120 volt, three phase, four wire, wye, emergency standby diesel generator with a 322 gallon base fuel tank and an 600 amp, four pole, automatic transfer switch (ATS) for the Pikeville District Twelve Office located at 109 Loraine Street, Pikeville, Kentucky 41501. The generator and ATS will be provided by the Commonwealth of Kentucky through a Master Agreement with Whayne Power Systems. The contractor will furnish and install a concrete pad for the generator and ATS. The generator and ATS will be delivered FOB to the District Twelve Office. The contract includes unloading and installing the new generator and ATS. The new generator will serve all building loads when utility power is lost. The District Office is served from pole mounted transformers. The underground service will be rearranged at the riser pole to include the ATS. A short duration outage will be used to cutover to the new service arrangement. Coordination with American Electric Power, Whayne Power Systems, and District Twelve Office personnel is required. All work will be preformed outside the District Twelve Office building and in the main electrical/mechanical equipment room. Eighty calendar days will be allowed for the construction. Generator and ATS have been ordered. Experience in the construction of underground and overhead electrical systems is required
Emergency Generrator District 10 Office, Kentucky Transportation Cabinet
RFB-85-12
This project consists of installing a 150 KW, 208/120 volt, three phase, four wire, emergency standby diesel generator with a 284 gallon base fuel tank and an 600 amp, four pole, automatic transfer switch (ATS) for the Jackson District Ten Office located at 473 Highway 15 South, Jackson, Kentucky 41339. The generator and ATS will be provided by the Commonwealth of Kentucky through a Master Agreement with Whayne Power Systems. The contractor will furnish and install a concrete pad for the generator and a separate concrete pad for the ATS. The generator and ATS will be delivered FOB to the District Ten Office. The contract includes unloading and installing the new generator and ATS. The new generator will serve all building loads when utility power is lost. The District Office is served from pole mounted transformers. The underground service will be rearranged at the riser pole to include the ATS. A short duration outage will be used to cutover to the new service arrangement. Coordination with Kentucky Power Company, Whayne Power Systems, and District Ten Office personnel is required. All work will be preformed outside the District Ten Office building and in the main electrical/mechanical equipment room. Eighty calendar days will be allowed for the construction. Generator and ATS have been ordered. Experience in the construction of underground and overhead electrical systems is required
Emergency Generator District 8 Office, Kentucky Transportation Cabinet
RFB-83-12
This project consists of installing a 150 KW, 480/277 volt, three phase, four wire, emergency standby diesel generator with a 284 gallon base fuel tank and a 400 amp, four pole, automatic transfer switch (ATS) for the Somerset District Eight Office located at 1660 South US Hwy 27, Somerset, Kentucky 42502. The generator and ATS will be provided by the Commonwealth of Kentucky through a Master Agreement with Whayne Power Systems. The contractor will furnish and install a concrete pad for the generator and ATS. The generator and ATS will be delivered FOB to the District Eight Office. The contract includes unloading and installing the new generator and ATS. The new generator will serve all building loads when utility power is lost. The existing overhead utility service from pole mounted transformers dips underground before entering the building. The service at the riser pole will be rearranged to include the ATS. A short duration outage will be used to cutover to the new service arrangement. Coordination with Kentucky Utilities, Whayne Power Systems, and District Eight Office personnel is required. All work will be preformed outside the District Eight Office building and in the main electrical/mechanical equipment room. Eighty calendar days will be allowed for the construction. Generator and ATS have been ordered. Experience in the construction of underground electrical systems is required.
Highway Engineer Section Office Clay County, Transportation Cabinet
RFB-79-12
This Work includes the construction of a 2,000 sf office building at 2037 US 421, Manchester, KY 40962. The building is slab-on-grade with wood framed walls, vinyl clad double hung wood windows, R-19 batt insulation, shop-fabricated wood trusses, asphalt shingle roofing, and fiber cement siding. Typical floor finish to be vinyl composition tile, typical wall finish to be painted gypsum board, typical ceiling to be suspended acoustical tiles. Typical ceiling height to be 8’-0″, typical bearing wall to be 10’-1″. The HVAC system is an electric heat pump. The building will accommodate an occupancy of 21 and house the following rooms and functions: a large workroom with kitchenette, four private offices, a small conference room, men’s and women’s restrooms, mechanical room, custodial room, communications room, and reception room. The Work also includes a small asphalt parking area (1 space, accessible). Consult project documents for information regarding connecting to site utilities.
Re-Roof District #9 Office Building, Kentucky Transportation Cabinet
RFB-75-12
This project consists of the complete demolition and removal of the roof at the District
Office Building, District #9 located in Fleming Co., Flemingsburg, Ky. and the
replacement with a thermo plastic membrane roof, over tapered insulation, all
flashings, drip edges, anchors and accessories for a water tight system. The building is
approximately 9,200 square feet.
Emergency Generator District 9 Office, Kentucky Transportation Cabinet
RFB-84-12
This project consists of installing a 150 KW, 208/120 volt, three phase, four wire, emergency standby diesel generator with a 284 gallon base fuel tank and an 800 amp, four pole, automatic transfer switch (ATS) for the Flemingsburg District Nine Office located at 822 Elizaville Road, Flemingsburg, Kentucky 41041. The generator and ATS will be provided by the Commonwealth of Kentucky through a Master Agreement with Whayne Power Systems. The contractor will furnish and install a concrete pad for the generator and a separate concrete pad for the ATS. The generator and ATS will be delivered FOB to the District Nine Office. The contract includes unloading and installing the new generator and ATS. The new generator will serve all building loads when utility power is lost. The District Office is served from pole mounted transformers. The underground service will be rearranged at the riser pole to include the ATS. A short duration outage will be used to cutover to the new service arrangement. Coordination with Fleming-Mason Energy RECC, Whayne Power Systems, and District Nine Office personnel is required. All work will be preformed outside the District Nine Office building and in the main electrical/mechanical equipment room. Eighty calendar days will be allowed for the construction. Generator and ATS have been ordered. Experience in the construction of underground electrical systems is required.
Electrical Distribution Upgrades, Kentucky State Reformatory
RFB-67-12
This project includes the removal of the existing 4KV electrical distribution at KSR and
installation of a new 15KV electrical distribution system. Included in the new 15KV distribution
system is new above ground 15KV fused distribution switches, new 15KV cables, new 15KV
transformers, and work inside some of the buildings as required. Also included in the project is
the upgrade of the existing 4KV emergency distribution system, and replacement and upgrade of
the existing overhead 4KV distribution system that is mainly outside the prison fence.
The scope of work includes the construction of a concrete bridge, 80 feet in lenght and 14 feet wide, for the future construction of a paved bike trail. Additional earthworks and grading will also be performed at each bridge abutment.
City of Greenup Phase 8 Waterline Extension Contract 4
City of Greenup Phase 8 Waterline Extension Contract 4
City of Greenup Phase 8 Water line Extension, Contract 4, Coal Branch Booster Station Upgrades, as shown on the plans, base bid, alternates, and unit price section.
Emergency Generators Installation Project — Bid Package C
Emergency Generators Installation Project — Bid Package C
Furnish all labor, materials and necessary equipment for the Emergency Generators
Installations Project – Bid Package C (Install emergency generators at: 4th & 5th
Division of LMPD stations and at Haz-Mat 5, Truck 2 and Engine 11, Truck 7 of
Louisville Metro Fire Stations) for Public Works & Assets, per the attached
specifications (a portion of this project will be utilizing FEMA funds).
#2488 Emergency Generators Installation Project — Bid Package B
#2488 Emergency Generators Installation Project — Bid Package B
Furnish all labor, materials and necessary equipment for the Emergency Generators Installations Project – Bid Package B (Install emergency generators at: 1st,2nd Division of LMPD stations and Engine 22, Truck 4 of Lou Metro Fire Station)for Public Works & Assets.
#2487 Emergency Generators Installation Project — Bid Package A
#2487 Emergency Generators Installation Project — Bid Package A
Furnish all labor, materials and necessary equipment for the Emergency Generators Installation Project – Bid Package A (Install generators at: 3rd, 6th,7th, and 8th Division LMPD stations)for Public Works & Assets.
Scott Fork Industrial Park Roadway Improvements Pikeville KY
Scott Fork Industrial Park Roadway Improvements
The project includes the widening of the existing Scott Fork Access Road to a minimum of 20 ft. the constructin of an intersection at the end of the existing road, and the construction of a right turn lane from northbound U.S. 119.
Pulaski County High School Bid Pack 3 1982 Building Renovation
Pulaski County High School Bid Pack 3 1982 Building Renovation
The scope includes renovation of approximately8,867 square feet of the existing 1982 building. The project includes reworking and renovating spaces on the main floor of this building along with new finishes and rebovated toilets on the lower level. Mechanical, electrical and plumbing work for this renovation includes a new makeup air unit, fire suppression, lighting and plumbing. In addition, there are multiple locations throughout the school that will have new HVAC and new electrical systems.