Electrical And SCADA Improvements — Fort Knox WWTP
Electrical And SCADA Improvements — Fort Knox WWTP
The work shall generally consist of: Installation of conduit, electrical and control wiring to connect with existing electrical panels, supply of electrical actuators to operate gate valves at various locations within the facility.
The scope of the project includes a roof replacement of approximately 59,175 square feet. The demolition includes removing the existing asphalt shingles, gutters and downspounts. New work includes installing a vented nailbase insulated panel along with felt and asphalt shingles.
Somerset, KY
Click Here to View
Whitley Co Water District Lot-Mud Creek Water Line Extension
Whitley Co Water District Lot-Mud Creek Water Line Extension
This contract consists of approximately 38,270 LF od 4″ Water Line, 7,485 LF of 3″ Water Line and appurtenances
Shelby County Board of Education will receive sealed bids for the furnishing of all labor, materials and the performance of all work required for the Northside Early Childhood Center general construction, site work, mechanical, electrical, fire protection and plumbing construction.
An 8,520 SF Fire Station, containing a five bay equipment garage, and a tornado community safe area housing the ready room, training, kitchen, toilets and offices. The building is a one story pre-engineered metal building containing a masonry and concrete aprons at overdoor doors and street entrance, and the parking area shall be gravel.
WKU-PDC-2013-005: Bids are requested by Western Kentucky University, from eligible firms located within a 125 mile radius of Bowling Green, KY (licensed and insured) to establish price contracts for the furnishing of labor, materials, and services for General Repair, Renovation, or Construction work on facilities utilized by Western Kentucky University. The contractor shall be capable of providing qualified and skilled tradesman as may be required. All jobs are to include but are not limited to the Contractor acquiring any necessary permits, inspections, and Performance Bonds where required.
Preston Highway 16″ Transmission Main — Hwy. 245 to Belmont Road
Preston Highway 16″ Transmission Main — Hwy. 245 to Belmont Road
Louisville Water Company is requesting Bids for the installation of approximately 10,800 L.F. of 16″ ductile iron water main along Preston Hwy (Hwy 61) between Clermont Rd (Hwy 245) and Belmont Rd.
Including General Construction of walks, curbs, earthwork, storm drainage, asphalt pavement, seed and straw and other work as indicated along portions of South Main Cross Street, Fox Spring Avenue & Mt Sterling Ave, a total combined distance of approximately 0.33 miles.
The stabilization of approximately 900 linear feet of an Unknown Tributary to Eastland Park Tributary that parallells Roland Avenue in the Eastland Neighborhood.
Louisville Water Company is requesting Bids for the installation of +/- 430 lineal feet of 12-inch DPW water main and +/- 40 lineal feet of 6-inch DPW water main. The project also includes two (2) customer services and mill & pave of approximately 6,862 square feet.
12-152 / Outer Loop and Melda Drive Main Replacement Project
12-152 / Outer Loop and Melda Drive Main Replacement Project
Louisville Water Company is requesting Bids for the installation of +/- 230 lineal feet of 8-inch DPW water main and +/- 730 lineal feet of 8-inch PVC water main and 1,200 lineal feet of (six) 6-inch PVC water main along Outer Loop and Melda Drive. The project also includes forty (40) customer services and three (3) fire hydrant assemblies.
27th Street Flood Pump Station Dry Weather Overflow Elimation Project
27th Street Flood Pump Station Dry Weather Overflow Elimation Project
Louisville, KY
The scope of work includes installation of a new electric gate actuator and appurtenances, dual hydrostatic level sensors, electrical, and instrumentation and controls. Major components of the project include, but are not limited to, the following:
1) Provide new electric actuator, stem, stem nut, and housing for Gate 65 to replace the existing manual actuator.
2) Provide RTU at Gate 65 and 68 to send / receive information via a cell network to the SCADA RTU located at the 27th Street Flood Pump Station.
3) Provide SCADA RTU at the 27th Street Flood Pump Station
4) Provide SCADA interface wiring between Gates 58, 59, 62 and 64, and the SCADA RTU.
5) Install new water level sensors located in the gatewell at Gate 65 for integration into MSD’s SCADA system.
6) Replace the existing switch gear at the 27th Street Flood Pump Station.
The scope of work includes the construction on Shortline Pike of approximately 600 feet of two-lane urban roadway with sidewalk and related storm drainage improvements.
Wellness Center Addition of approx. 2800 SQ FT addition over partial basement. The structure is a stick frame brick veneer with some structural steel components. Reinforced concrete/masonry foundations and basement walls. Slab on grade and concrete on metal deck over steel bar joist floors over basement section of the project. Lean concrete fill for trench foundations.
Foundation drain system and stone fill. Dimensional shingle roofing over 30 LBS underlayment and 5/8″ plywood roof deck. Alum gutters and down spouts. Roof trusses and portions of stick frame gable framing components. 2×6 exterior wall framing and finish carpentry – casework and wood trims, solid core doors and hollow metal door frames, aluminum clad wood windows, fiberglass insulation, aluminum facia and trim. Drywall systems, acoustic ceiling systems, painting, carpet, vct tile, ceramic tile. Forced air HVAC heat pump, plumbing and fixtures, electrical service and fixtures. Minor site development, excavation. Minor site utility connections. Site concrete, minor landscaping.
Work is to include installation of approximately 6,800 LF of 8-inch, 46,000 LF of 6-inch, 36,000 LF of 4-inch, 1,500 LF of 2-inch waterline with 2,500 LF of various sized directionally drilled creek/river crossings and other appurtenances.
KY 199 Waterline Relocation KDOT Item No 12-298.40
KY 199 Waterline Relocation KDOT Item No 12-298.40
This contract consists of approximately 2,100 linear feet of eight inch waterline, 110 linear feet of four inch waterline, bore and case crossings for eight inch and four inch waterline, and appurtenances.
This contract consist of approximately 1,000 linear feet of 8-inch PVC waterline, 60 linear feet of 8-inch HDPE pipe (directional drilled), 36 linear feet of ductile iron pipe, 40 linear feet of 3-inch PVC pipe, 30 linear feet of bored steel encasement and associated appurtenances.