City of Georgetown Building Abatement and Demolition FY 2014-15 Project
City of Georgetown Building Abatement and Demolition FY 2014-15 Project
1. Perform asbestos, lead, and hazardous material investigation
a. Certified inspector required
b. Report shall submitted to City Engineer’s office prior to abatement
2. Perform asbestos, lead, and hazardous material abatement (if required)
a. Abatement shall be performed per all current regulations and standards by a certified remediation expert
b. Prior to abatement, project work area shall be secured by construction fencing.
c. Report stating abatement complete shall be submitted to the City Engineer’s office prior to demolition
3. Perform demolition of structures
a. Work includes: demolishing structures, removing material from the site, hauling, disposing, and any other incidental activities required.
b. In addition, the completed work shall include any recommendations as provided by the Cardno letter dated 9/11/2014 (attached).
c. Contractor is encouraged to salvage building materials to the extent practical.
d. Salvaged materials remain the property of the City of Georgetown.
e. Building and deleterious materials shall be removed from all basement and subgrade areas in preparation for filling.
4. Perform backfill of basement and subgrade areas
a. All work shall be performed in full per the Cardno recommendations letter dated 9/11/2014 (attached).
b. Prior to filling, representative samples of proposed fill materials shall be collected and tested per the Cardno letter. (note the lead time)
c. Contractor shall communicate with Cardno regarding scheduling of tests and inspections.
d. Earthwork shall be graded to drain and rolled with a smooth drum roller.
e. The site shall be then proofrolled where any unsuitably soft subgrade zones shall be undercut until stable soils are encountered and replace with suitable fill
f. The final surface shall be a 6”