Murray-Calloway County Airport – Taxiway Overlay and LED Lighting Project
Murray-Calloway County Airport – Taxiway Overlay and LED Lighting Project
PROJECT DESCRIPTION:
Furnishing all labor, materials and equipment and performing all work necessary for the Taxiway Overlay and LED Lighting Project at the Murray-Calloway County
Airport
Sealed Bids addressed to the Louisville and Jefferson County Metropolitan Sewer District, 700 West Liberty Street, Louisville, Kentucky 40203 for the construction of CMF Roof Areas ‘E’ & ‘F’ Replacement Project Contract No. 16,031, Budget ID No. C17027, Drawing Record No. 16031, Sheet No. 1-20, will be received at the office of MSD until 10:00 AM, Local Time, August 2, 2018, and will be publicly opened and read at that place and time.
Description and location of Project: This lump sum construction order is for the removal and replacement of roof ‘E’ & ‘F’ and its appurtenances of the Center Maintenance Facility (CMF) located at 3050 Commerce Center Place. All contractors interested in access to the roof shall be responsible for providing their own ladders, MSD shall not provide ladders for access to the roof areas.
All work shall be done in accordance to MSD’s Standard Specifications.
There will be a non-mandatory pre-bid meeting held for this project at MSD’s CMF, 3050 Commerce Center Place, Louisville, KY at 10:00 am Local Time on, July 19th, 2018.
The Engineer’s Construction Cost Estimate for this project is between $2,000,000.00 to $3,000,000.00.
The bid documents will be available on, July 2nd, 2018, online at www.msdbids.com. The charge for each set of bid documents is outlined on the above-referenced web site.
Persons wishing to view the bid documents may do so online at www.msdbids.com or at the following locations: Builders Exchange of Louisville, Inc., 2300 Meadow Drive; Associated Builders & Contractors of Kentuckiana, 1810 Taylor Avenue; and F. W. Dodge, 1812 Taylor Avenue; all located in Louisville, Kentucky; and the Associated General Contractors of Kentucky, 2321 Fortune Drive, Suite 112, Lexington, Kentucky.
The Project Manager for this Invitation to Bid is Joseph S Exely. All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s Project Manager, Joseph Exely E-mail: joseph.exely@louisvillemsd.org. Questions received less than five days prior to the date for opening of bids may not be answered. Only answers by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. All inquiries and questions between the bid opening and the contract awarding shall be directed, in writing, to MSD’s Chief Engineer, Angela Akridge, P.E.
IF THE ENGINEER’S CONSTRUCTION COST ESTIMATE IS $50,000 OR MORE, the Minority Business Enterprise and Woman Business Enterprise (MBE/WBE) participation goals shall be applicable to all contracts and comply with MSD’s Interim Supplier Diversity Policy and Guidelines (Interim Policy). The Interim Policy is considered as one of the elements of responsiveness in a bid. Bidders must subcontract at least 15.0% of the total amount of the Contract Bid price to a certified MBE and 6.0% to a certified WBE, or if the Contractor is unable to meet the goals, must demonstrate adequate “GOOD FAITH EFFORTS” in accordance with the Interim Policy. – (see MSD Construction Related MBE/WBE Documents and Forms at http://www.msdlouky.org/insidemsd/diverse ). Each bidder is responsible for careful review of the Interim Policy requirements contained in the bid documents. Failure to comply with the Interim Policy may be grounds for rejection of the bid as non-responsive.
All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s Project Manager, Joseph S Exely.
MSD Interim Supplier Diversity Policy and Guidelines for this project is as follows:
15% MBE and 6% WBE participation is required for this project.
LOCAL LABOR PREFERENCE: No
The contract will be awarded on the basis of the lowest, responsive, responsible bid, subject to the approval of the MSD Board. MSD reserves the right to reject any or all bids or waive any informality in any bid.
LOUISVILLE AND JEFFERSON COUNTY
METROPOLITAN SEWER DISTRICT
Angela Akridge, P.E.
Chief Engineer
Rene’ Thomas
Director of Procurement & Supplier Diversity
MSD Procurement Department
Goodnight Memorial Public Library – Additions & Renovations-2018
Goodnight Memorial Public Library – Additions & Renovations-2018
Please note: Addendum 02 has changed the Bid Date!
Geotechnical Report can be downloaded free by clicking on the spec tab above
PROJECT DESCRIPTION
The Project consists of the Base Bid Scope of Work CONSTRUCTION of an approximately 1,352 SF, Ground + Lower level addition to the existing Auditorium (Area #1), including new accessible male + female toilets and a connecting stairway, with lower level mechanical area. The existing 7,300 SF Ground + 3,610 SF Upper level Auditorium with
stage will be completely renovated with new seating, flooring, mechanical, electrical, lighting, power, fire suppression, and plumbing systems. The existing stairways will also have renovation for finishes.
The Base Bid Scope of Work will also include the Exterior masonry rework and window replacement for Area #1 as well as a portion of the South & North Walls of the Existing Library portion of the building for Area #2. Site related work including the rework of the parking lot and expansion of the existing asphalt parking area will also be part of the Base Bid Scope of Work. Alternate #1 – will incorporate the removal of the roof from the one story portion of the Library Building – Area #2, addition of an upper
level floor 2,391 SF in area and new roof structure to expand the library, as well as renovation of the lower level, with stairway, ground level, and upper levels of the remainder of the Library in Area #2. The project shall include but not limited to concrete slab on grade, concrete footings and foundation
walls, CMU reinforced exterior walls, steel framed beams, metal stud wall framing, and metal bar joist and steel frame upper level floor structure with concrete slab, and metal bar joist with steel frame and metal deck roof structure with membrane roof system. The work shall also include all of the related site
work for excavation, building layout, temporary construction fencing & construction trailer; NOI, soil erosion control, excavation & fill; trench excavation, underground storm water drainage system, parking
lot revision and replacement including asphalt and concrete paving & striping of lot, concrete curb and gutter, concrete walks, site lighting and sod landscaping. This work and other related work necessary to complete all work as shown on the Contract Documents prepared by Pearson & Peters Architects PLC;
Poage Engineers & Associates, and N3D Consulting Engineers
PROJECT DESCRIPTION:
This package involves the installation work for Bid Package # 01 – Grehan Journalism
Building Project. The work will be performed under contract with the Construction
Manger, Turner Construction Company.
TC-001 – ABATEMENT WORK
TC-002 – DEMOLITION WORK
TC-003 – SITE EXCAVATION WORK
CCK-2340-19 Ag North Curtain Walls Repair & Caulk 2018, Floors 1,2, & 3
CCK-2340-19 Ag North Curtain Walls Repair & Caulk 2018, Floors 1,2, & 3
PROJECT DESCRIPTION:
The objective of this project is to prepare for and re-caulk specified glazing and spandrel panels
of the curtain wall system on first, second, and third floors of Ag North (Ground floor windows
and curtain walls are excluded). Specified glass panes and spandrel panel perimeter gasketing
and perimeter caulking are included in the project. The work includes, but is not necessarily
limited to
1. Removing all existing superficial/overlaid caulking on the specified curtain walls and
panels
2. Preparing gasketing of all specified glass and spandrel units for caulking/glazing
material,
3. Caulking prepared glass panes and spandrels panels,
4. Replacing all existing cracked and/or damaged glass (replacement glass shall have
reflective film installed matching the existing film),
5. Final exterior window cleaning and application of Wonder-Glass (Ground Floor is
included),
6. Site cleanup and restoration.
PROJECT DESCRIPTION:
The Project consists of relocating
600 LF of 8” DI Water Line and 345 LF of 3” HDPE Sewer Force Main in advance of a KYTC highway project.
Architectural work includes the exterior cleaning and sealing/repainting of veneer materials on multiple buildings, repair and/or replacement of public stairs, replacement of all exterior windows in three buildings, and the renovation of the rear dock on Building M. Also included is the re-placement of exterior storefront and overhead sectional doors in multiple locations and the re-placement of several aluminum canopies at exterior door locations.
Interior work included consists of the minor renovation of classrooms in Building A, minor reno-vation of a set of restrooms in Building M and the installation of plastic laminate casework in the Radiography Lab in Building M.
Mechanical work includes the replacement of two chillers with a new single chiller and the re-placement of two existing boilers with new high efficiency equipment.
Electrical work includes upgrades to the existing campus JACE DDC controllers as well as other IT infrastructure upgrades.
Existing equipment shall not be taken offline until such time as new equipment is capable of being put into service.
Georgetown Municipal Water and Sewer Service – Bluegrass RV Gravity Sanitary Sewer Line
Georgetown Municipal Water and Sewer Service – Bluegrass RV Gravity Sanitary Sewer Line
PROJECT DESCRIPTION:
The project scope includes 2,045 linear feet of 10” PVC gravity sewer pipe, 120 linear feet of boring 18”
encasement pipe and appurtenances.
PROJECT DESCRIPTION:
Demolition of a portion of the existing concrete deck, minor
sub grade preparation, installation of a new concrete deck, the installation of a new steel shelter,
finish grading, seed and straw, and construction fencing and construction signage.
Louisville Metro Government uses Bonfire portal for accepting and evaluating proposals digitally (https://louisvilleky.bonfirehub.com/portal)
. Bidders must submit all pages of bid document through Bonfire. Sealed Proposals must be uploaded,
submitted, and finalized prior to the closing at 07/11/18 3:00pm. The bid document and drawings
are available on Bonfire and Lynn Imaging, all other forms, documents and attachments are available
on (https://louisvilleky.bonfirehub.com/portal).
PROJECT DESCRIPTION:
Construction of a spray ground, playground and
building extension at Victory Park, 1051 S 23rd St. Louisville, KY 40210. This project includes but is not
limited to: demolition of existing playground, swings, and spray ground. Construction of a new 24
feature spray ground, playground, and swings as shown on the plans. All associated grading, drainage,
utility work and seed/straw as shown on the plans.
Louisville Metro Government uses Bonfire portal for accepting and evaluating proposals digitally (https://louisvilleky.bonfirehub.com/portal)
. Bidders must submit all pages of bid document through Bonfire. Sealed Proposals must be uploaded,
submitted, and finalized prior to the closing at 07/12/18 3:00pm. The bid document and drawings
are available on Bonfire and Lynn Imaging, all other forms, documents and attachments are available
on (https://louisvilleky.bonfirehub.com/portal).
Hopkinsville Water Environment Authority – US41A 8” Natural Gas Main Extension-Phase II – Task E
Hopkinsville Water Environment Authority – US41A 8” Natural Gas Main Extension-Phase II – Task E
Please note: Addendum 01 has changed the Bid Date!
PROJECT DESCRIPTION:
HWEA CONTRACT # 126-2015-01-A
Construction of approximately 24,180 linear feet of 8” steel gas main, auxiliary components, and appurtenances, including a regulator station, and associated equipment,
Hopkinsville Water Environment Authority – Eagle Way Bypass / US41A 8” Natural Gas Main Extension-Phase II – Task F/G
Hopkinsville Water Environment Authority – Eagle Way Bypass / US41A 8” Natural Gas Main Extension-Phase II – Task F/G
Please note: Addendum 01 has changed the Bid Date!
PROJECT DESCRIPTION:
HWEA CONTRACT # 126-2015-01-B
Construction of approximately 19,611 linear feet of 8” steel gas main auxiliary components, and appurtenances, including a meter station, and associated equipment
City of New Haven – Sanitary Sewer System Replacement and Repairs Phase II
City of New Haven – Sanitary Sewer System Replacement and Repairs Phase II
PROJECT DESCRIPTION:
The work to be bid is generally described as follows:
1,220 LF 8″ Gravity Sewer Replacement
2 Furnish and Install Precast Concrete Manholes
4 Remove and Reset Existing Manholes
60 SY Asphalt Replacement
60 SY Driveway & Sidewalk Replacement
This project consists of the renovation of the lower level of the 3-story Gray Building and will create offices for business, financial aid, veterans’ affairs, security, student organization in addition to improvements to the central student center space and large multi-purpose space. Demolition will include the removal of interior walls, stair and exterior façade at a limited location facing the plaza. New interior construction will consists of primarily gypsum board walls, upgrade to finishes and new ceilings. HVAC will be replaced throughout the lower level and will include new VAV boxes and branch ductwork. Electrical and communications modifications will be completed in support of renovated spaces. A new patio and canopy will be constructed immediately off of the Student Center space and will connect to the exterior plaza.
City of Gamaliel – Gamaliel City Hall CDBG ADA Project
City of Gamaliel – Gamaliel City Hall CDBG ADA Project
PROJECT DESCRIPTION:
The work to be bid consists of
Interior building improvements of restroom facilities and exterior site improvements including, but not limited to, a new ADA handicap access ramp, sidewalks, and minor demolition.
Description and location of Project: This unit base construction order is for the installation of a modular wall, and 12- inch pipe along the rear yard of 3930 E Pages Lane in Metro Council District 25.
Description and location of Project: This unit based construction order is for the 12-inch pipe, and valley gutter installation along the Cardinal & Oriole Drive, in Metro Council District 10.
Phase 4 – Capitol Campus Parking Garage is comprised of the following work on Levels 2 – 6 of the garage.
1. Concrete slab repairs.
2. Concrete beam and column repairs.
3. Sealant installations.
4. Waterproofing vehicular traffic membrane installation.
5. Isolated painting repairs.
6. Isolated drain riser replacement.
7. Replacement of fire suppression standpipes.
8. Pavement markings.
9. Construction barriers and dust protection.
City of Hartford – Hartford Downtown Sidewalk Improvements
City of Hartford – Hartford Downtown Sidewalk Improvements
PROJECT DESCRIPTION:
The work to be bid is described as follows
CONTRACT 141-16-02
Construction of approximately 8,700 L.F. of concrete sidewalk, 2,560 L.F. of curb and gutter, concrete entrances, earthwork, storm drains, headwalls, and drop box inlets, as depicted in the Drawings.