This project involves removing Grow Hall, the primary food service facility on the campus, from the central steam heating system and replacing steam service with an independent heat source. The heating in the building is currently provided from two steam convertors and a steam duct coil, which shall be demolished, along with two hydronic heating pumps and a condensate return unit. They will be replaced by one new high-efficiency, condensing, natural gas, hot water boiler, with onboard controls, one new hot water heating coil and three new pumps, with all required accessories. Existing gas line will be demolished, and a new, larger gas line will be run from an existing regulator on the outside wall to the new boiler with existing branches re-welded to the new main. Condensing boiler exhaust vent and combustion air lines will be run to an outside wall.
Please note: Per Addendum 01, a pre-bid meeting will be held on 6/26/2019 at 2PM ET. If interested in attending contact Ryan Gentry (606)383-3111
rgentry@wehrconstructors.com or Warren Thomas (502) 471-7181
wthomas@wehrconstructors.com.
Renovate the 1st and 2nd floors of Whitney Hendrickson Bldg. (Pavilion WH, Bldg #0098) for
use as an Infusion Clinic. Renovate a suite on the 2nd floor of Chandler Medical Center
(Pavilion H, Bldg #0293) for use as an Infusion Clinic. Renovate the 2nd floor of Ben Roach
Bldg. (Pavilion CC, Bldg #0093) for use as a medical clinic.
Trade PackageDescription
TP – 09 Electrical & Data LV Systems
Community Action Council of Lexington-Fayette, Bourbon, Harrison, & Nicholas Counties – The Prep Academy at Winburn
Community Action Council of Lexington-Fayette, Bourbon, Harrison, & Nicholas Counties – The Prep Academy at Winburn
The scope of work includes fitting up approximately 4,300 square feet of unfinished shell space,
within the existing Community Action Council building at 1169 Winburn Drive, Lexington,
Kentucky. In general the project includes removal of the existing windows and hollow metal doors,
cutting and patching existing concrete floor slab to accommodate new plumbing, patching of
existing separation walls and reinstallation of existing wall and roof insulation where sagging or
removed. New construction includes the complete construction of 3-classrooms, student toilet
rooms, office, public restroom, lactation room and storage. Construction generally consist of
installation of gypsum board and metal stud partitions, installation of new doors, frames and
hardware, new fixed view windows, installation of new acoustic tile, floor tile and LVT flooring. All
spaces will be served by new mechanical, electrical and plumbing fixtures. Refer to Contract
Documents for complete scope of project work.
Provide labor, equipment, materials, supplies and components, and perform all operations necessary for installation of electrical system. Scope of the electrical work are described, but not limited to the following: Complete demolition and replacement of Federal Pacific pad mounted switchgear. Removal of temporary 15KV tray cable feeder. Refusing adjacent switchgear (that provided the temporary power feed).
Project includes renovation of an approximately 21,000 SF area of a two story office building that houses the emergency management offices, and other programs related to the Emergency Operations Center at Boone Center, KY. HVAC renovations include HVAC controls replacement, repairs to existing air handlers, and replacement of all VAV boxes, reheat piping, and ductwork in the office areas. Architectural upgrades include but are not limited to complete new ceilings in the offices areas, new wall and floor finish replacements. This is a phased project where the upper floor will get renovated first then the occupants of the lower floor will occupy the upper floor when the lower floor is renovated.
Monroe County Board of Education – Tompkinsville Elementary School Roof Renovation
Monroe County Board of Education – Tompkinsville Elementary School Roof Renovation
The project scope includes new fluid-applied polyurethane coating to
approximately 65,000 square feet of existing EPDM roofing system, including replacement of
approximately 470 square feet of existing damaged insulation and cover board. New fluid-applied
polyurethane coating is from State Price Contract.
Monroe County Board of Education – Monroe County Central Office Roof Replacement
Monroe County Board of Education – Monroe County Central Office Roof Replacement
Please note: Addendum 01 has changed the bid time.
This project consists of the removal of the existing roof system down to deck and replacement with new roof system including required insulation, gutters, downspouts, etc. New
roofing system to be SBS from State Price Contract.
The project consist of replacement of existing smooth surface 2-ply modified bitumen roof and ½” cover board with a new 1″ poly-iso cover board and a new single ply SBS modified bitumen roof with a type M (mineral-granule-surfaced cap sheet).
REQUEST FOR QUALIFICATIONS (RFQ) – Sanitary, Drainage, and Flood Protection Maintenance Design Support
REQUEST FOR QUALIFICATIONS (RFQ) – Sanitary, Drainage, and Flood Protection Maintenance Design Support
INVITATION TO SUBMIT STATEMENT OF QUALIFICATIONS
The Louisville and Jefferson County Metropolitan Sewer District (MSD) invites submittal of responses to a Request for Qualifications (RFQ) from qualified and experienced engineering firms, or teams, for the analysis, design, plan production, project management, and support during construction for small- to medium-sized projects related
to the operation and maintenance of MSD’s sanitary, drainage, and flood protection systems. MSD intends to contract with one or more Respondent(s) to this RFQ.
The Department of Criminal Justice Training Mat Room Renovation. Scope shall include the installation of seamless Athletic floor mats, wall impact pads and column protection. Relocation of existing lay-in light troffer fixtures and ACT grid modification to accommodate installation of heavy punching bag hanging rail system.
Montgomery County Schools – High School Girls Softball Improvements
Montgomery County Schools – High School Girls Softball Improvements
Project consists of an addition to an existing locker room dugout facility to
include new equipment lockers. Also, includes removing the roof of the existing concessions
stand building and adding a second floor for the press box office.
Monroe County Board of Education – Falcon Academy Adult Education Center & Auxiliary Athletic Training Center Roof Replacement
Monroe County Board of Education – Falcon Academy Adult Education Center & Auxiliary Athletic Training Center Roof Replacement
Please note: Addendum 01 has changed the bid time.
This project is at three buildings (Falcon Academy, Adult Education Center, and
Auxiliary Athletic Training Center) and consists of the removal of the existing roof system down to
deck and replacement with new roof system including required insulation, gutters, downspouts, etc.
New roofing system to be SBS from State Price Contract.
City of Hindman – Wastewater Treatment Plant Rehabilitation
City of Hindman – Wastewater Treatment Plant Rehabilitation
The project Includes sandblasting and recoating existing steel surfaces (including tanks, struts, beams,
handrails and steps) and replacement of equipment (including comminutor, surge tank pumps, blowers, UV
system, flow measurement, air diffusers), piping replacements and blower building demolition.
DRGWQTC Secondary Clarifier Grout Repair and Gate and Actuator Replacement
DRGWQTC Secondary Clarifier Grout Repair and Gate and Actuator Replacement
Please note: Addendum 04 has changed the Bid Date! Sealed Bids addressed to the Louisville and Jefferson County Metropolitan Sewer District, 700 West Liberty Street, Louisville, Kentucky 40203 for the construction of DRGWQTC Secondary Clarifier Grout Repair and Gate and Actuator Replacement Contract No. 16,083, Budget ID No. D18292, Drawing Record No. 16083, Sheet No. 1-18, will be received at the office of MSD until Thursday July 25, 2019, Local Time, 10:00 a.m., and will be publicly opened and read at that place and time.
Description and location of Project: Repair of grout in Secondary Clarifier Nos. 7-12, replacement of influent and RAS gates and actuators for Secondary Clarifier Nos. 1-6, and installation of isolation gates to Secondary Clarifier Nos. 1-6 at the Derek R Guthrie Water Quality Treatment Center (DRGWQTC) located at 11601 Lower River Road, Louisville, KY 40272.
All work shall be done in accordance to MSD’s Standard Specifications.
There will be a non-mandatory pre-bid meeting held for this project. The meeting will be held at the DRG
WQTC located at 11601 Lower River Road on Thursday June 27, 2019 at 10:00 a.m. local time with site visit to
follow. Anyone wishing to view the site will be required to provide their own PPE.
The Engineer’s Construction Cost Estimate for this project is between $1,500,000.00 to $2,500,000.00.
The bid documents will be available on, Monday June 17, 2019, online at www.msdbids.com The charge for each set of bid documents is outlined on the above-referenced web site.
Persons wishing to view the bid documents may do so online at www.msdbids.com or at the following locations: Builders Exchange of Louisville, Inc., 2300 Meadow Drive; Associated Builders & Contractors of Kentuckiana, 1810 Taylor Avenue; and F. W. Dodge, 1812 Taylor Avenue; all located in Louisville, Kentucky; and the Associated General Contractors of Kentucky, 2321 Fortune Drive, Suite 112, Lexington, Kentucky.
The Project Manager for this Invitation to Bid is Steven Leong. All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s Project Manager, Steven Leong E-mail: steven.leong@louisvillemsd.org. Questions received less than ten days prior to the date for opening of bids may not be answered. Only answers by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. All inquiries and questions between the bid opening and the contract awarding shall be directed, in writing, to MSD’s Chief Engineer, Angela Akridge, P.E.
IF THE ENGINEER’S CONSTRUCTION COST ESTIMATE IS $50,000 OR MORE, the Minority Business Enterprise and Woman Business Enterprise (MBE/WBE) participation goals shall be applicable to all contracts and comply with MSD’s Interim Supplier Diversity Policy and Guidelines (Interim Policy). The Interim Policy is considered as one of the elements of responsiveness in a bid. Bidders must subcontract at least 15.0% of the total amount of the Contract Bid price to a certified MBE and 6.0% to a certified WBE, or if the Contractor is unable to meet the goals, must demonstrate adequate “GOOD FAITH EFFORTS” in accordance with the Interim Policy. – (see MSD Construction Related MBE/WBE Documents and Forms at http://www.msdlouky.org/insidemsd/diverse ). Each bidder is responsible for careful review of the Interim Policy requirements contained in the bid documents. Failure to comply with the Interim Policy may be grounds for rejection of the bid as non-responsive.
All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s Project Manager.
MSD Interim Supplier Diversity Policy and Guidelines for this project is as follows:
15% MBE and 6% WBE participation is required for this project.
LOCAL LABOR PREFERENCE: No
The contract will be awarded on the basis of the lowest, responsive, responsible bid, subject to the approval of the MSD Board. MSD reserves the right to reject any or all bids or waive any informality in any bid.
Project includes the e upgrade/replacement of all HVAC Controls for Thompson Hood Veteran’s Center. Existing controllers are BACnet and points shall be pulled into new JACES. All new graphics, trends, and Sequences of Operation shall be provided.
This Work includes a 1,444 square foot addition to an existing unheated storage building located at the Kentucky Nation Guard Armory in Tompkinsville, Kentucky. The addition will be constructed on new concrete slab with turn-down footing and similar in construction to existing pre-engineered metal building. Minor electrical renovation is included in the scope, including all new interior and exterior lighting. Existing ventilation louvers on the front elevation will be re-used on the new front elevation on the addition. The front elevation of the addition will also include a new concrete approach apron, hollow metal person door and coiling overhead door. New interior security caging will also be included in the scope.
Estimate:
$ 78,423.00
Estimated Length of Project:
(Substantial Completion) + December 31, 2019 (Final Completion)
The Division of Abandoned Mine Lands wishes to receive bids to perform reclamation work on approximately 9.31 acres of mine land in Magoffin County, Kentucky. The work will consist of earthwork, gradework, waste removal and revegetation of 1 bond forfeiture permit(s).
Renovation of (6) existing kitchen In Hazelwood Center
1. Appliances to remain – stand alone stove/oven, refrigerator.
a. Dishwasher – replace old with Hobart – hot water only.
2. Cabinets – minimum of (2) open space under the counter: 1. Under the sink, 2. 30″ work spaces
a. Remove and replace with severe use base & wall cabinet per budget with pull.
b. Wall cabinets: 1 will be lockable
c. Base cabinets – 1 will be the bank of drawers and the others with slide out trays.
d. All counter will be 34″ height to meet ADA.
e. Additional heights requested by the UA of 32″ & 30″ will be accommodated with an adjustable height dining table (NIC) in the center of the rooms that could be accommodated in place of proposed stainless steel table with lockable wheels.
f. Provide slide trays or racks in the base cabinets for accessibility.
g. Pantry type cabinet with fixed shelves on tops & pull out shelves at bottoms.
h. (5) knuckle hinges will require cabinet door closer to keep cabinet doors closed.
3. Countertop & backsplash: Solid surface.
4. Replace existing kitchen sink with (2) compartments sink with goose neck with separate sprayer fixture to meet ADA.
5. Provide small wall-hung hand washing lavatory in the space and meet ADA.
6. Remove from old cabinet and re-install in the new cabiner, existing exhaust fan & suppression system.
7. Provide corner guards on outside corner where indicated
8. Paint – kitchen walls & gypboard ceiling to match existing surrounding area.
9. Remove wall tiles above the back splash, prep and paint.
10. Floor – remove existing VCT, prep and install new VCT in (4) kitchen, prep and install new VCT in the (2) kitchen where its been abated.