The scope of this project is to replace the two existing air-cooled chillers. The HVAC control valves and actuators also are being replaced and a new direct digital control system will be installed.
City of New Albany – Grant Line Road Sight Distance Corrections
City of New Albany – Grant Line Road Sight Distance Corrections
The project consists of vertical sight distance improvements on Grant
Line Road from 355 ft. south of Mure de Ronce Drive to 445 ft. north of Mure de Ronce Drive, near
the Blackberry Ridge neighborhood. Improvements include pavement replacement, new curb and
gutter, minor drainage modifications, new driveway approaches, new pavement markings, updated
signage, and all other appurtenant work.
Clinton County Board of Education – Albany Elementary School – Partial Roof Replacement
Clinton County Board of Education – Albany Elementary School – Partial Roof Replacement
Partial roof replacement including removal of existing ballasted EPDM membrane
roofing system and installation of new mechanically fastened TPO membrane system.
Description and location of Project: The principal features of the work to be performed under this contract include, but are not limited to the following:
The intent of this project is to add redundancy to the utility power source for the RAS Pump Station. The Contractor shall furnish all labor, equipment, and materials required for re-routing substation feeder 1A through a new 15kV switch to provide a redundant 15kV feed to Substation U-8 and disconnecting existing 480V feeders at the Process Water Building and at 9MCC-1 & 2 in the RAS Pump Station. Work shall include new conduit in concrete ductbank for the redundant electrical feed from MH-1 near the Process Water Building to a new 15-kV switch at the RAS Pump Station. The existing 15kV substation feeder 1A from MH-1 to TU-1 is to be removed and re-used as one of the feeders from MH-1 to the new 15kV switch at Substation U-8. The feeder is to be pulled into the new underground ductbank. The conductors in existing conduits will remain and be disconnected at each end. Fuses shall be furnished and installed within Unit Substation U8 in a new parallel 15kV primary switch. Testing and coordination with Louisville MSD and their plant operations shall be facilitated by the Contractor for completion of this Work. Once electrical work is complete, the Contractor is required to restore all surfaces including pavement and grass, natural areas that were disturbed during construction. Contractor will be paid on a lump sum basis for the materials and labor required to complete the work.
For additional information go to https://eprocurement.ky.gov
Estimated Length of Project:
365 (Substantial Completion) + 30 (Final Completion)
This project is the partial renovation of the Jefferson Community and Technical College downtown campus’ Tech B building currently housing a number of the College’s vocational programs. The work includes renovation for the new Carpentry, General Automotive, and Mercedes Automotive labs.
The scope of work includes, but is not limited to selective demolition of interior CMU walls, mezzanine concrete slabs, and MEP systems. New upgrades include mechanical/electrical/plumbing systems to accommodate the needs of each lab’s teaching requirements, new overhead coiling doors, and reconfiguration of CMU walls for the inclusion of new classroom spaces. Exterior work includes installation of new roof curbs for added mechanical system roof penetrations, and a new exterior concrete curb cut and ramp.
Eastern Kentucky University (EKU) hereby requests sealed bids for the materials, supplies,
equipment or services set forth herein, subject to all conditions outlined in this Bid Package
City of Jeffersontown – Public Works Office – Bid Package 2
City of Jeffersontown – Public Works Office – Bid Package 2
The City of Jeffersontown is accepting sealed bids on the construction of the building frame and roofing,
to include flooring, walls, roof structure, and interior walls/windows walls to support the construction of a
new Jeffersontown Public Works Administrative/Training building.
CCK-2487-20 Modernization of Facilities (Rose Street Enabling)
CCK-2487-20 Modernization of Facilities (Rose Street Enabling)
Install a new underground ductbank and manhole system for future telecommunications and
electric cabling along Rose Street. In support of these systems, new electrical circuits
originating from Parking Structure #2 are to be installed within these pathways.
City of Coal Run Village – US 23 North Sanitary Sewer Project
City of Coal Run Village – US 23 North Sanitary Sewer Project
The Project consists of construction services for
sanitary sewer force mains, laterals, and grinder units that will facilitate and replace the Blairtown,
Kinnikinnick, and Coal Run Village areas of failing and outdated septic systems.
Pikeville Medical Center – Pediatric Suite Renovation
Pikeville Medical Center – Pediatric Suite Renovation
Project consists of the renovation of 13,420 square feet on the second floor of the May Tower, for the Pediatric
Suite, consisting of 10 private patient rooms and 13 exam rooms with support space for both.
20-16 / Distribution System Repairs & Capital Improvements
20-16 / Distribution System Repairs & Capital Improvements
Louisville Water Company is requesting Bids for unit prices to furnish all necessary equipment, tools, and labor in time of need to undertake improvements, repairs, maintenance and necessary construction to LWC distribution facilities. Distribution facilities shall include but not be limited to distribution mains, domestic services, fire services and fire hydrants. This unit price Master Agreement will be for two (2) years.
Replace damaged and dilapidated shelters supporting the Kentucky Emergency Warning System. Upgrade and expand site to accommodate new larger shelters as needed. Upgrade electrical and grounding.
Estimate:
$221,892.25
Estimated Length of Project:
120 Calendar Days (Final Completion)
The Jack Pelphrey Drainage AML Reclamation Project consists of constructing a gabion ditch upstream from the Pelphrey residence that transitions into a concrete block tie mat ditch. The project site is located in Patterson Creek near the community of Flat Gap, within the Redbush Quadrangle, at 37° 55’ 56″ N, 82° 55’ 04″ W. The Pelphrey residence is located on the left side of Patterson Creek. The site acreage is approximately 2.62 acres. The waste area is located on a bond forfeiture permit and consists of 17.16 acres exclusive of the access road for a total project area of 19.78 acres exclusive of the access road.
The project will consist of constructing a gabion ditch within the drain upstream of the Pelphrey home that transitions into a block tie mat ditch within the Pelphrey yard. A class II ditch will be constructed in the area of an old pre-law pond that has washed out. An existing culvert within the Pelphrey driveway will be replaced as part of access to the site. The waste material from the project will be used to cover bare areas on the J& M Construction and Equipment Co, In. Permit No. 858-0168 bond forfeiture.
The project site and waste area has been previously disturbed by coal mining operations, house seat development, road construction, landowner disturbances, and/or utility installation. These disturbances consist of significant upheaval, mixing, and removal of earthen material from excavation, grading, subsurface drilling, fill material placement and erosion. Trees 3″ in diameter or more at breast height will require removal as part of the project. Trees will be removed during the period from October 16 through March 31.
Construction disturbances will be kept to a minimum with a stringently formulated sediment and erosion control program that includes a temporary type A sediment trap and straw bales and/ or silt fence. Prior to beginning any major earth disturbance, all silt control measures will be installed. All areas disturbed by construction activities are to be revegetated in accordance with regional, regulatory, and project standards, using agricultural limestone, fertilizer, seed and mulch, as needed. Prompt re-vegetation will be implemented by using agricultural limestone, fertilizer, seed, netting and/or mulch, as needed, for the areas disturbed by the project, in accordance with standard AML design specifications. Access to the site is via county roads, residentially maintained driveways and yards, and an existing road permitted as part of the permit that has be forfeited. This project will include pre- and/or post- project maintenance and repair of existing previously constructed public county roads utilized during the construction of this project, which are administered by the county or local road authority. This construction activity will be conducted under the authority and supervision of the local public road authority and will consist of standard road construction practices appropriate to mitigate impacts to the local community from potential degraded road conditions in order to maintain public traffic safety.
A. Bluegrass-Oakwood is an Intermediate Care Facility supporting individuals with intellectual and developmental disabilities. Construction at this site must be performed in a manner that protects the existing staff and clients from risks that are inherent to construction operations.
B. Work of the Project includes:
1. Full tear off and legal disposal of existing asphalt shingles, plywood and insulation at Cottages 110, 112, 114, and 117.
2. Installation of new nailable base, vented roof insulation panels, asphalt shingles and associated sheet metal flashing and trim.
3. The work also includes raising the height of existing plumbing stacks to conform to the Kentucky Plumbing Code.
Warren County Board of Education – South Warren High/Middle School Geothermal Well Field Valving Project
Warren County Board of Education – South Warren High/Middle School Geothermal Well Field Valving Project
Project consists of installing new geothermal circuit pipe and main pipe
valves, and repairing a leak in one well field at South Warren High/Middle School.
Major Work items in this Contract include:
Installing pump stations, valve vault, and force main.
Installing gravity sewer piping, manholes, and accessories.
Contractor shall coordinate with local utility company for installation of electrical service drops. Contractor shall be responsible for providing all electrical connections from the utility company service drop as specified and as shown on the Drawings. The Contractor shall be responsible for all fees and inspections related to the electrical portion of this project.
Contractor shall coordinate with local utility company for tie-in and meter installation for meter service. Contractor shall be responsible for meeting all utility company requirements for connection and providing all equipment or other apparatus necessary for connections. The Contractor shall be responsible for all fees and inspections related to this portion of the project.
Project Field Office: The Contractor shall provide accommodations in the Contractor’s field office trailer for use by the Owner and Engineer throughout the duration of the project.
Franklin County Board of Education – Turf Field Installations at WHHS & FCHS
Franklin County Board of Education – Turf Field Installations at WHHS & FCHS
The work includes the construction of two (2) new artificial turf fields within the existing running tracks at
both High Schools. This scope of work for the construction project includes, but not limited to, the
underground improvements for the new turf fields, excavation of existing soils, grading, underground
drainage systems, fill materials, regrading of spoils on-site, relocation of a scoreboard, new flagpole and
installing empty electrical conduit. The Artificial turf field system and its installation will be purchased off
the State Term Contract by the District from The Motz Group. The contractor shall be required to
coordinate the contract work with the Turf Field System supplier/installer and any daily school activities.
Eastern Kentucky University (EKU) hereby requests sealed bids for the materials, supplies,
equipment or services set forth herein, subject to all conditions outlined in this Bid Package
Warren County Board of Education – Greenwood High School Reroof
Warren County Board of Education – Greenwood High School Reroof
Project consists of the installation of a retrofit roof system over the
existing metal roof system on perlins and steel framing. Scope to include demolition and
replacement of any existing low slope membrane roofing, down to existing metal deck
and installation of new insulation and a TPO roof system. Select locations of metal panel
removal and replacement is also included.
Warren County Board of Education – Drakes Creek Middle School Reroof
Warren County Board of Education – Drakes Creek Middle School Reroof
Project consists of the installation of a retrofit roof system over the
existing metal roof system on perlins and steel framing. Scope to include demolition and
replacement of any existing low slope membrane roofing, down to existing metal deck
and installation of new insulation and a TPO roof system. Select locations of metal panel
removal and replacement is also included.