The project provides for all labor, materials, and equipment necessary for the installation of approximately 2358 linear feet of storm sewer, 906 linear feet of under drains, 155 tons of pavement leveling & wedging with overlay, 11 storm sewer manholes, 12 inlet structures, 540 square yards of conventional concrete sidewalk, 444 square yards of pervious concrete sidewalk, 827 linear feet of pervious concrete header curb, 790 linear feet of conventional concrete curb & gutter and related appurtenances of construction.
This project consists of removal (by others) of the existing floor finishes in their entirety and disposal of them off campus, prepare floor to receive new finishes. New finishes are to be provided and installed as per the attached specs and drawings. Wax shall also be included as per specs. Trades need for this job will be floor prep, installation, cleaning and waxing. Contractor shall be responsible for all field measurements and materials amounts. Contractor will bid based on the take-offs provided. Any differencses on take-off will be adjusted accordingly by the corresponding unit price, credit, or additional change order. Asbestos abatement and existing floor covering removal by WKU Contractor (ROMAC) during the week of July 7-13, 2012.
RFB-222-12 Highway Engineer Section Office Jefferson County
RFB-222-12
This Work includes the construction of a 2,000 sf office building at 8310 Westport RD., Louisville, KY 40222. The building is slab-on-grade with wood framed walls, moveable partition, vinyl clad double hung wood windows, R-19 batt insulation, shop-fabricated wood trusses, asphalt shingle roofing, and fiber cement siding. Typical floor finish to be vinyl composition tile, typical wall finish to be painted gypsum board, typical ceiling to be suspended acoustical tiles. Typical ceiling height to be 8’-0″, typical bearing wall to be 10’-1″. The HVAC system is an electric heat pump. The building will accommodate an occupancy of 21 and house the following rooms and functions: a large workroom with kitchenette, four private offices, a small conference room, men’s and women’s restrooms, mechanical room, custodial room, communications room, and reception room. The Work also includes a small blacktop parking area (1 space, accessible).
Retina Assoc of Kentucky Renovation – Burchfield and Thomas
Retina Assoc of Kentucky Renovation – Burchfield and Thomas
The project consists of a complete phased renovation of an existing office suite (9,200 SQ FT). The work specifically includes interior framing and drywall, finishes, casework, electric, HVAC, plumbing and speinkler modifications.
Knox Co Utility Commission Water System SCADA, Radio Telemetry Monitor and Control System
Knox Co Utility Commission Water System SCADA, Radio Telemetry Monitor and Control System
This contract consists of a system control computer with appropriate peripherals, base radio modem and remote site terminal units for four booster pump stations, one high service pump, one solenoid valve station, sex water storage tanks and one master meter.
Black Mountain Utility District Water System SCADA, Radio Telemetry Monitor and Control System
Black Mountain Utility District Water System SCADA, Radio Telemetry Monitor and Control System
This contract consists of a system control computer with appropriate peripherals, base radio modem and remote site terminal units for four booster pump stations, one high service pump, one solenoid valve station, six water storage tanks and one master meter.
DB Services for LMPD Firearms Training Center Phase II Renovation/Adaptive Reuse
DB Services for LMPD Firearms Training Center Phase II Renovation/Adaptive Reuse
A Request for Proposals to furnish all labor, material and necessary equipment for Design Build Services for the LMPD Firearms Traing Center, Phase II Renovation/Adaptive Reuse
RFB-224-12 Chiller Replacement Transportation – Central Utilities Plant
RFB-224-12
Chiller Replacement for Central Utility Plant at the Transportation Cabinet Central Utility Plant Building in Frankfort, KY. The project includes the demolition of two existing 500 Ton chillers (CH-3 and CH-4), the associated pumps, piping, and starters; installation of new Owner Furnished/Contractor Installed equipment (1200 Ton Centrifugal Chiller, starter, associated pump, and variable speed drive). Controls for the replacement chiller and associated equipment are to be Owner furnished including controllers, control devices, and sensors as well as wiring, programming, and start-up
RFB-225-12
The Base Bid consists of removing the existing housing unit security control system, intercom and lighting control system and installing a new security control system, intercom, and lighting control system for housing unit number two (consisting of dorms three and four).
New Traffic Signal at Spring Street & Fairview Drive
New Traffic Signal at Spring Street & Fairview Drive
The scope of work includes the addition of a new traffic signal at the intersection of Spring Street, Fairview Drive and the new drive entrance to the Kruchers facility.
RFB-215-12 Upgrade Welding Shop Exhaust System – Rowan Campus
RFB-215-12
The project consists of welding shop exhaust and ventilation system replacement and
upgrade. The HVAC scope includes equipment and ductwork demolition, new welding
exhaust ductwork and hoods, utility set exhaust fans and new gas fired make up air
unit. Electrical includes re-feed of MCC and power distribution to new HVAC
equipment. Additional work includes structural steel modifications for rooftop
equipment support and metal building roof and wall penetrations.
2335.0 Electronic Health Records Infrastructure Upgrade
2335.0 Electronic Health Records Infrastructure Upgrade
The project includes electrical and telecommunication infrastructure for the Ambulatory Electronic Health Records implementation in three clinics in the KY Clinic, the Pain Clinic at Good Samaritan Hospital, and the OB-GYN Clinic at the Good Samaritan Medical Office Building. The scope also includes a closed loop chilled water HVAC system for the communication rooms in the KY Clinic and Warren Wright buildings.
The furnishing of all labor, materials, supplies, tools, equipment, services, etc., necessary for the construction of Marion County High School Renovations as set forth in the specifications and as shown on the drawings prepared by Ross Tarrant Architects, Inc.
Whitley Co Water District SCADA, Radio Telemetry Monitor and Control System
Whitley Co Water District SCADA, Radio Telemetry Monitor and Control System
This contract consists of a system control computer with appropriate peripherals, base radio modem and remote site terminal units for two booster pump stations and two water storage tanks.
Cawood Water District Water System SCADA, Radio Telemtry Monitor and Control System
Cawood Water District Water System SCADA, Radio Telemtry Monitor and Control System
This contract consists of a system control computer with appropriate peripherals, base radio modem and remote site terminal units for four booster pump stations, one high service pump, one solendoi valve station, six water storage tanks and one master meter.