The project is the consists of exterior repairs for Henry Ward Lodge and nine guestroom buildings. Repair work involves the following:
1. Painting of guardrails and handrails, including supporting steel channel and angle brackets.
2. Repair of exterior insulation and finish system, and application of weatherproof coating.
3. Repairing and painting of cement plaster soffits.
4. Masonry repair.
5. Repairing and painting of miscellaneous wood trim.
6. Painting of underside of concrete decks.
7. Painting of upper deck ceilings.
8. Repairing and painting of upper deck privacy walls.
9. Construction of new lower patio privacy walls.
Lexington-Fayette Urban County Airport Board – TSEP Phase IV-Construct New ARFF Facility
Lexington-Fayette Urban County Airport Board – TSEP Phase IV-Construct New ARFF Facility
The Project consists of the Construction of a New ARFF Facility; Lowering
the Terminal Concourse Roof; Constructing Associated Roadway Pavements and a Portion of Taxiway A. Significant items of work include:
P-152 EXCAVATION 12500 CY
P-156 EROSION CONTROL BLANKET 2800 SY
P-209 AGGREGATE BASE COURSE 17500 SY
P-304 CEMENT TREATED BASE 1800 SY
P-501 PORTLAND CEMENT CONCRETE 8350 SY
D-754 GUTTER AND PAVED DITCH 1300 LF
L-108 UTILITY AND CONTROL CABLE 3000 LF
L-110 DUCTS AND CONDUIT 5700 LF
T-901 TURFING 5.4 AC
SP. NO. 1 ARFF BUILDING 1 LS
SP. NO. 1 TERMINAL CONCOURSE MODIFICATIONS 1 LS
SP. NO. 3 RETAINING WALL 156 LF
SP. NO. 5 FIBER OPTIC 30400 LF
SP. NO. 11 PERMEABLE INTERLOCKING CONCRETE 2725 SY
SP. NO. 12 TRACKLESS
BI-FOLDING GATE 1 EA
In addition to these major Items of work, minor items of work that may require specialty materials or
construction methods would include but not be limited to:
Pavement Removal
Erosion Control
Bituminous Paving
Pavement Marking and Pavement Marking
Underdrain
Precast structures
Fencing
Utilities – Electric, Water, Telephone, Gas & Sanitary
Bell County Detention Center – Smoke Evacuation System Upgrade
Bell County Detention Center – Smoke Evacuation System Upgrade
PROJECT DESCRIPTION: Furnish all labor and materials to complete the Bell County Detention Center Smoke Evacuation System Upgrade at the Bell County Detention Center
The construction contract
shall be a single (all trades) contract.
Description and location of Project: This unit based construction order is for 15-inch, 12-inch, 10-inch, and paved “v” ditch installation along Parkwood Road in Metro Council District 12.
CCK-2229-17 Research Lab #3 – Elevator Modernization
CCK-2229-17 Research Lab #3 – Elevator Modernization
PROJECT DESCRIPTION:
This project is for the modernizing and upgrading of the elevator currently in service in the Research lab #3
located at 700 S. Limestone on the University of Kentucky Central Campus
Bid Date Change!! Addendum#3 changes bid date to 6/6/17
PROJECT DESCRIPTION:
The Morgan County Board of Education will receive bids to furnish all labor and materials to complete the:
The Morgan County High School
150 Road to Success
West Liberty, Kentucky 41472
The Project has 3 Phases each with Separate Final Completion dates as noted below.
Phase 1 – New Road and 103,000 sf. School – beginning July 1, 2017 thru December 1, 2018
Phase 2 – Renovation and Additions to the Existing Gymnasium. 21,000 total sf. – beginning March 1, 2018 thru November 1, 2018.
Phase 3 – Demolition of Existing School and Site Work – beginning January 1, 2019 thru June 1, 2019.
Mt. Sterling Water and Sewer – East & West High Street Sewer Line Replacement
Mt. Sterling Water and Sewer – East & West High Street Sewer Line Replacement
PROJECT DESCRIPTION:
These projects consist of
approximately 1,500 feet of 8″ SDR 35 gravity sewer, related fittings and accessories as well as reconnection of existing service laterals.
The Bid will consist of the following work: Install 693 L.F. of various sizes (12″ to 54″) RCP, and 49 L.F. various size (8″ to 18″) D.I.P for storm water improvements. Install 27 L.F. of
6’x5′. and 8 L.F. of 4’x3′ Box Culverts. 181 L.F. of Trench Drains, 48 L.F. of earth ditches, 187 L.F. of Paved Ditch and 221 LF. of Earth embankment, and 385 L.F. of Bank Stabilization. Additional work will include 12 water and sewer laterals relocations, 40 L.F. of 6″ Water Main Relocation. Work will include manholes, junction boxes, and Headwalls, Fences Replacements, asphalt and concrete replacement and other related appurtenances.
Lexington-Fayette Urban County Airport Board – Blue Grass Airport Rental Car Facilities
Lexington-Fayette Urban County Airport Board – Blue Grass Airport Rental Car Facilities
Please Note: Addendum 04 has changed the Bid Date
PROJECT DESCRIPTION:
The project consists of Construction of new rental car vehicle storage lots,
buildings and fuel stations. Demolition of existing rental car facilities. All associated
site work such as grading, utilities, parking lots and roadway improvements.
CALL 121 CONTRACT ID 171020 JEFFERSON COUNTY TGR 0311 (037) : DIXIE HIGHWAY(US-31W) FEDERAL TIGER GRANT COMMITMENT (MP 14.488) PEDESTRIAN ACCESS/SAFETY IMPROVEMENT AND ACCESS CONTROL ON US-31W (DIXIE HIGHWAY) FROM HEATON ROAD MP 14.488 NORTHWARD TO HERBERT AVENUE MP 14.969. (THIS PROJECT IS PART OF THE KYTC FUNDING COMMITMENT TO LOUISVILLE METRO FEDERAL TIGER GRANT PROJECT). (MP 14.969) GRADE & DRAIN WITH PCC PAVEMENT. SYP NO. 05-00478.01.
CALL 109 CONTRACT ID 171217 JACKSON COUNTY STP BRO 4211 (047) : MANCHESTER TO MCKEE ROAD (US 421) (MP 13.919) REPLACE BRIDGE ON US 421 OVER PIDGEON ROOST CREEK AT INTERSECTION WITH WATER STREET E (CS 1006) (MP 13.959), A DISTANCE OF 0.11 MILES. BRIDGE WITH GRADE, DRAIN & SURFACE. SYP NO. 11-01090.00.
CALL 108 CONTRACT ID 171211 OHIO COUNTY STP BRZ 0203 (337) : CLAY LEACH LANE (CR 1194) (MP 0.029) REPLACE BRIDGE ON CR 1194 OVER THREELICK CREEK; 0.15 MI WEST OF JCT CR 5172 (MP 0.129), A DISTANCE OF 0.10 MILES. BRIDGE WITH GRADE, DRAIN & SURFACE. SYP NO. 02-0177.00.
Project Location: Ohio County, Kentucky
171018 Perry Call 107
Kentucky Transportation Cabinet
CALL 107 CONTRACT ID 171018 PERRY COUNTY STP BRO 5375 (045) : BULAN-HINER ROAD (KY-1146) (MP 2.679) REPLACE BRIDGE ON BULAN-HINER ROAD(KY-1146) OVER TRACE FORK AT JCT WITH KY-476. (MP 2.712), A DISTANCE OF 0.05 MILES. BRIDGE REPLACEMENT. SYP NO. 10-01102.00.
CALL 106 CONTRACT ID 171215 LEE COUNTY STP 5262 (060) : WEST MAIN STREET (KY 52) (MP 11.780) CONSTRUCT SIDEWALKS, CURB AND GUTER ON KY 52 FROM DOWNTOWN BEATTYVILLE TOWARD IRVINE (MP 12.260), A DISTANCE OF 0.47 MILES. ASPHALT SURFACE WITH GRADE & DRAIN. SYP NO. 10-08852.00.
CALL 100 CONTRACT ID 171019 PIKE COUNTY NHPP 0806(044) : POND CREEK BRIDGE(US-460) POND CREEK BRIDGE, US-460/KY-80 FROM KY-195 TO EAST OF POND CREEK, SECTION 6A-2., A DISTANCE OF 2.18 MILES. BRIDGE WITH GRADE & DRAIN. SYP NO. 12-00263.63.
The new 2-story, Educational Alliance Center will be constructed on the north side of the Middlesboro Campus for Southeast KCTC. The base bid building is approximately 27,000sf. LEED certification will be pursued for this project.
The building will include: A Nursing department, an Aviation lab, Assembly areas, Internet café, general and computer classrooms, faculty offices, administrative and supports spaces. The project will also include a 2-stop hydraulic elevator.
The foundation will include a 10-inch thick concrete slab, concrete grade beams supported by auger-cast piles, all steel reinforced. The second floor will be framed with precast concrete planks supported by reinforced masonry walls. The equipment platform will be a composite concrete/metal deck. The roofs steel-framed.
For HVAC, chilled water will be provided by air cooled chillers, HVAC hot water will be provided by gas fire boilers. Classroom and multipurpose areas will be served using fan coil units. Offices and other small areas will be served by a central VAV air handling unit and single duct terminal units with reheat coils. Outside air will be fed to the system using a central dedicated outside air unit.
Existing site infrastructure will be utilized to extend utilities to the new building. The service into the building will be 277/480V/three-phase. The internal distribution system will provide 277/480V/three-phase power to equipment loads, 277V power to lighting loads, and 120V power to receptacle loads. The project will include a fire alarm system, telecommunications systems, and rough-in for Owner-provided AV and security systems.
CCK-2226-17 Parking Structure #2 Entrance Plaza – 2470.0
CCK-2226-17 Parking Structure #2 Entrance Plaza – 2470.0
PROJECT DESCRIPTION:
The project includes the removal of pavement, sidewalks and salvage of brick pavers in order to construct a
traffic table across Hilltop Avenue at the entrance to Parking Structure #2. The traffic table will be
constructed of asphalt block pavers set in a bituminous setting bed on top of a new concrete slab. The
sidewalks on both sides of the road will be replaced, including some exposed aggregate concrete, standard
concrete and brick paver bands salvaged from demolition. The traffic table will include heavy duty concrete
ramps on both ends for vehicles and trench drains to capture storm water and pipe it to adjacent existing
storm structures. Two existing catch basins located along each curb line within the limits of the traffic table
will be modified to replace the castings with new flush castings. Stainless steel bollards will be installed
along both sides of the traffic table to designate vehicular lanes from pedestrian only walks. Sod shall be installed on any disturbed surrounding lawns.
Travel to GRCC to remove existing Kohler 300ROZD71 from building K and day tank from building K at Green River Correctional Complex capping off the fuel lines and leaving the building louvers in place. Deliver generator to Tank/Housing Manufacturer. Please see Summary of Work for complete Description of Work.
Base bid: Installation of new heat trace on portions of the existing fire protection system. Work includes a new heat trace system and associated electrical work, pipe insulation and fire alarm modifications. Demolition and re-installation of ceiling will be required to accommodate the installation of the new heat trace system.
Alternate: The addition of a new clean agent system and associated fire protection modifications, new HVAC work, new associate fire alarm work and associated new electrical work for storage room 111.
Description and location of Project: This unit based construction order is for 18-inch and 12-inch pipe installation from 10702 – 10706 Ward Ave in Metro Council District 19.
City of New Albany – 2017 Annual Street Paving & Repairs Project
City of New Albany – 2017 Annual Street Paving & Repairs Project
PROJECT DESCRIPTION:
The project consists of milling, pavement patching, pavement placement, curb ramp replacement, curb, sidewalk and driveway replacement, pavement striping and
other appurtenant work associated with pavement improvements to various streets throughout the City.
Estimate:
$201,691.00 Estimated Length of Project:
(Substantial Completion) + 120 Calendar Days (Final Completion)
The site is located off Hwy 3 at Big Lick Branch Road in Martin County (Lat: 37°, 54’, 57.5”, Long: 82°, 32’, 39.0”). To reach the site from Prestonsburg, travel north on US 23 for approximately 5.1 miles to a right onto Bays Branch Road to KY 3/KY 321. Continue straight for 1.6 miles and turn right onto KY 3 North. Continue on KY 3 for 16 miles and take the ramp onto KY 3 N/KY 645 W. Follow KY 645 W for 4.2 miles to Fitch Branch and turn right onto Fitch Branch. Travel 0.5 miles to KY 3 and turn left ontoKY 3 North. Travel 2.1 miles to a right onto Big Lick Branch Road and travel 0.4 miles to Webb Stepp Road. Continue up the hill and take the first driveway on the left.
Drainage issues and a slide have developed on the Stepp/Webb property from mining on the property. OSM constructed a project at the site 20 years ago. Material is sliding through the OSM pilings in front of the Stepp trailer and the subdrain behind the trailer is no longer functioning. Also, the Webb house adjacent to the trailer has similar issues.
The subdrain behind the trailer will be replaced with a new combination rock ditch/drain and an additional combination ditch will be constructed behind the Webb house. The slide/slump in front the trailer near the pilings will be corrected by building a 10 ft deep trench in front of the pilings and filling it with stone and a perforated pipe that will be connected to ditches to drain water away from the area.
The area in front of the Webb house will be stabilized by building a pile and lagging wall between the house and the driveway.
Ditches will be constructed to drain water away from the subdrains as well as the surface.
A Portal will be closed behind the trailer.
Excess excavated material from the construction activities will be taken to a waste area approximately 0.5 miles away near Johnson Bottom Road (Lat: 37°, 55’, 25.1”, Long: 82°, 32’, 58.1”). It is anticipated that only a relatively small portion of the waste area will be used for placement of material. Lengths of ECB ditch and of concrete block tied-mat ditch are included to minimize erosion that is currently occurring in a part of the waste area. This waste area is also being used for the Willie Johnson project.
Site Preparation includes clearing and grubbing of vegetation. The construction area at the site and at the waste area will be revegetated in accordance with regional, regulatory, and project standards, using agricultural limestone, fertilizer, seed and mulch. A standard seed mix is to be used. Hay bales and silt fences shall be installed for silt and erosion control. A hoe ram bid item is included for excavation work needed for the ditches, subdrains and retaining walls.
A landscape allowance is included to replace “in kind” landscape disturbed as needed as part of normal construction efforts