In conjunction with the construction of a 52,050 square foot, two story classroom building being constructed under a separate contract, supply and install the machine room-less hydraulic elevator is being performed under a separate contract.
PROJECT DESCRIPTION:
Furnish all labor, materials, equipment and services
required to complete all work for Lexington Fayette Urban County Housing Authority – Glen Arvin 10 Townhomes 366-370 Glen Arvin Avenue
Lexington, Kentucky
Estimate:
$277,945.00 Estimated Length of Project:
(Substantial Completion) + 90 Calendar Days (Final Completion)
The site is located on Hwy 550 in Floyd County (Lat: 37°, 30’, 48.55”, Long: 82°, 49’, 2.36”).
Drainage issues and a slide have developed on the Osborne property from mining on the property. The problems will be corrected by constructing steel piles in front of the house and a rock toe buttress in the yard as well as ditches to direct the runoff away from the property.
Excess excavated material from the construction activities will be taken to a waste area approximately 2.5 miles away near Hwy 80 (Lat: 37°, 29’, 4.4”, Long: 82°, 49’, 34.1”). The waste area is also being used for the Wayland Stream Stabilization project.
Site Preparation includes clearing and grubbing of vegetation. The construction area at the site and at the waste area will be revegetated using residential seeding. Hay bales and silt fences shall be installed for silt and erosion control. A hoe ram bid item is included for excavation work needed for the ditches, subdrains and retaining walls.
A landscape allowance is included to replace “in kind” landscape disturbed as needed as part of normal construction efforts
The Fire Alarm System will be removed and upgraded per the 2015 Kentucky Building Code with Current Revisions and the 2013 National Fire Alarm and Signaling Code at the Argo McClure Building, located on the Kentucky School for the Deaf Campus, 202 South Second Street, Danville, Kentucky. An intelligent, addressable fire alarm system shall be provided in accordance with National Fire Alarm and Signaling Code requirements as well as the requirements of the State Fire Marshall’s Office. The system will comply with all manufacturers’ requirements and shall report compatible alarm signals to the remote central system via an externally mounted dialer. The fire alarm system will monitor any and all sprinkler system flow switches, tamper switches, and duct mounted smoke detectors as well as heat detectors and smoke detectors. A remote annunciator panel will be provided at the Main Entrance Lobby.
The Lighting Systems will be replaced in the majority of the building including new LED lay-in style with energy controls as well as emergency exit signage and emergency lighting units. The majority of the exterior Lighting Systems will also be replaced and controlled with new lighting control relay panels. The Transformer to the Building will be replaced, the electrical services will be upgraded and a Main Distribution Panelboard installed. Several shops and classrooms will receive new power panel replacements, raceway, emergency stop contactors, and new grounding.
The work to be performed shall be commenced at the time stipulated in the Notice of Intent to Award (work order) to the contractor by the Division of Contracting. Substantial Completion shall be within ninety (90) consecutive calendar days thereafter. Final completion shall be fifteen (15) consecutive calendar days after Substantial Completion.
The project consists of complete tear-off of existing gravel-surfaced coal tar pitch roof and installation of new SBS Modified Bituminous Membrane Roof System.
Project includes mechanical systems upgrades to Scoggan and McDaniel Buildings at the Kentucky School for the Blind. Select existing unit ventilators and fan coil units will be replaced. Air handling units in Scoggan will be replaced with new units. Existing fin tube radiant heaters will be replaced to allow for system to function.
New Fan Coil units will be installed at the corridors in the Scoggan building and in the third level of the connector to provide cooling to the spaces.
Piping will be replaced in select areas and new electrical connections provided for new equipment. Cooling is being added to the bridge between the two buildings and to the corridors in Scoggan Hall.
The Scoggan Classroom Building was originally constructed in 1963 and is a 40,669- square-foot facility. The McDaniel Classroom Building was originally constructed in 1985 and is a 23,774- square-foot facility.
Big Sandy Health Care, Inc. – Shelby Valley Clinic Addition
Big Sandy Health Care, Inc. – Shelby Valley Clinic Addition
PROJECT DESCRIPTION:
The project consists of a 3,986 SF addition to the existing clinic building, and
includes a waiting room, treatment rooms, lab, offices, break room, and storage
rooms.
725 East Market Street Storm PSC Installation – Rebid
725 East Market Street Storm PSC Installation – Rebid
Description and location of Project: Install approximately 17 LF of 12″ PVC to Property Line, 5’ Deep; Install Dog House Manhole over single ring brick sewer; Pour 8″ base pad with #5 rebar, 8″ side walls with #5 rebar, 12″ O.C., each way; Dig out 24″ brick down to haunches of pipe; May have to hand dig from 12″ above pipe to haunches; Set flat top on Dog House and core 12″ through concrete wall with boot; Trench cut 10’x10′ and 11’x4′ with 1′ set back, concrete cap trench cut repair flush with existing asphalt surface; All traffic control and permits the responsibility of the contractor; May have to close the road.
725 East Market Street Sanitary PSC Installation – Rebid
725 East Market Street Sanitary PSC Installation – Rebid
Description and location of Project: Install approximately 31 LF of 12″ PVC to Property Line, 7’ Deep; Install Dog House Manhole over single ring brick sewer; Pour 8″ base pad with #5 rebar, 8″ side walls with #5 rebar, 12″ O.C., each way; Dig out 24″ brick down to haunches of pipe; May have to hand dig from 12″ above pipe to haunches; Set flat top on Dog House and core 12″ through concrete wall with boot; Trench cut 10’x10′ and 11’x4′ with 1′ set back, concrete cap trench cut repair flush with existing asphalt surface; All traffic control and permits the responsibility of the contractor; May have to close the road.
WKU-PDC-2018-001 Cleaning / Sanitizing HVAC Systems South Campus
WKU-PDC-2018-001 Cleaning / Sanitizing HVAC Systems South Campus
PROJECT DESCRIPTION:
The project scope:
This project is for the cleaning, sanitizing and encapsulation of commercial heating, ventilating and air conditioning systems located within the WKU South Campus.
Estimate:
$ 59,640.00 Estimated Length of Project:
(Substantial Completion) + 60 Calendar Days (Final Completion)
The proposed project (approximately 2.0 acres total) consists of drainage controls in Perry County. The project area is located on the United States Geological Survey (USGS) 7.5’ Hazard North quadrangle (see the attached project and site maps).
The James Cheek Site consists of installing a subdrain, a concrete block-tied mat, and pipes around the Angie Back residence. The site is located at 28 Tyler Lane, near the community of Bulan, KY. The project area is centrally located at N 37° 19’ 19.20”, W 83° 9’ 6.80”. To reach the site from the junction of Hwy 80 and Hwy 1146 east of Hazard, turn right onto Hwy 1146. Travel approximately 1.2 miles to Hwy 476. Turn left onto Hwy 476. Travel approximately 1.6 miles to Tyler Lane. Turn left onto Tyler Lane. The first house on the left is the Angie Back residence.
Reclamation work consists of installing 285 L.F. of subdrain and finger drains behind the residence, installing 160 L.F. of concrete block-tied mat along the bottom of the hillside, and replacing an existing pipe across the yard with a new 18” HDPE pipe outletting into the existing drain. Class II rock will be placed at the pipe outlet to reinforce the side slopes. Also, a new 18” pipe culvert will be replaced across Tyler Lane road. The existing driveway will serve as the access road and it will be replaced with roadway stone after the construction work is completed. The waste material generated during project work will be used on site as indicated on the site map within the project boundaries.
During the process of these construction activities, trees over 5 inches in diameter at breast height will not have to be removed in the AML problem area and to install drainage controls. A sediment and erosion control program, consisting of such measures as constructing hay bales/silt fence to be maintained throughout the life of the project and prompt re-vegetation using agricultural limestone, fertilizer, seed, and mulch will be implemented on all areas disturbed by this project.
Entry to the work areas will be accessed by the county road, residential driveways, and residentially maintained yards. The entire project work area slated for any excavation has been previously disturbed by any or all of the following: coal mining operations, including mine drainage, timber operations, gas/oil well development, residential development, road construction, and/or high velocity water flows associated with heavy rain events and flooding. These disturbances consist of significant upheaval, mixing, and removal of earthen material from deep excavation, grading, sub-surface drilling, fill material placement, and erosion. There should be no undisturbed earthen material to a depth of several feet at the areas slated for significant project-related construction activities.
This project will include pre- and/or post- project maintenance and repair of existing previously constructed public county roads utilized during the construction of this project, which are administered by the county or local road authority. This construction activity will be conducted under the authority and supervision of the local public road authority and will consist of standard road construction practices appropriate to mitigate impacts to the local community from potential degraded road conditions in order to maintain public traffic safety.
Description and location of Project: This unit based construction order is for a 12-inch trench drain, pipe and drain, and driveway replacement along Shadwell Lane in Metro Council District 16.
New Albany Flood Control District – New Albany Concrete Floodwall Repairs
New Albany Flood Control District – New Albany Concrete Floodwall Repairs
PROJECT DESCRIPTION: The work involved is described below:
•Coordinate with property owners
•Refurbish gate well hatches, metal steps, railing, and grates
•Refurbish 2 flood wall service openings
•Replace flood levels
•Repair damaged water stop at service opening
•Repair spalls and cracks in the concrete surfaces
•Label each floodwall monolith and gate well with structure number according to plans
•Removal of asbestos within monolith joints
•Replace the joint filler and silicone water seal between each flood wall monolith
•Remove graffiti and repaint
•Seal every monolith and gate well with anti-graffiti sealent
•Remove vegetation along flood wall and any overhanging trees
Beech Spring Farm Sections 1-7 Infrastructure Completion Project
Beech Spring Farm Sections 1-7 Infrastructure Completion Project
Description and location of Project: This unit based construction order is for the Infrastructure Completion Project in Beech Spring Farms in Metro Council District 16.
The project involves the complete removal of the existing DX HVAC system. This will include removal of the existing hot water boiler system, expansion tanks, housekeep pads, circ. Pumps, air separator and controls.
This project will include the installation of a new VRF systems, mechanical ventilation system which includes an energy recovery unit, ventilation air ductwork and the installation of the refg. piping. This contractor will need to make all of the interlocks between equipment.
If Add Alternate #1 is accepted will paint the Drill Walls, windows, doors and frames.
If Add Alternate #2 is accepted install new Epoxy floor finish in the Drill Hall.
Also, this project has a $39,000.00 allowance to expand the existing DDC controls to except the new HVAC equipment.
Hopkinsville Community College – Agricultural, Health & Career Center
Hopkinsville Community College – Agricultural, Health & Career Center
Post Bid Addendum 01 has rebid Bid Package 010 – Grading and Storm Drainage.
PROJECT DESCRIPTION:
Furnish all labor and materials to complete each Bid Package listed for the KCTCS – Hopkinsville Community College
Emerging Technologies Building.
Lewis County Schools – New Lewis County Central Elementary School
Lewis County Schools – New Lewis County Central Elementary School
PROJECT DESCRIPTION:
The Lewis County New Central Elementary School project will be bid and constructed utilizing the
Construction Management Agency form of construction contract delivery. Trace Creek Construction will
be the Construction Manager for the project under direct contract with the Lewis County Board of Education. The New Elementary School project is generally described as the construction of a new 2-story facility, including site improvements and demolition of existing buildings.
Laurel County Schools – Camp Ground Elementary School – Renovation & Addition
Laurel County Schools – Camp Ground Elementary School – Renovation & Addition
Please Note: Addendum 03 has changed the Bid Date
PROJECT DESCRIPTION:
Camp Ground Elementary School located in London, Kentucky for the Laurel County Board of Education is being renovated to provide new finishes throughout the building interior including new floor finishes, new ceilings, new lighting, new fire sprinkler
system and upgraded HVAC system throughout to become a 300-student elementary school.
Renovations include demolition of existing toilet rooms to become classrooms and the existing Media Center to become a new Music Room, new Art Room, and Resource Rooms to meet Kentucky Department of Education standard guidelines for a 300-student capacity facility.
There will be two new additions and an infill of an existing exterior breezeway to become a new
enclosed corridor. The addition at the front entrance to the building will include a new secure vestibule and reception area, with a new Family Resource Center and new Media Center. The second addition at the rear of the building will include a new vestibule and entry lobby into the existing Gymnasium complete with new toilet rooms for students and staff. The new lobby will provide second direct access to the existing gym from the interior of the building that was
previously accessed via a single interior entry point within the existing building. The project will include improvement, upgrades and reconfiguration for the vehicular access for both student drop off by parents, a new bus loop and staff parking. There are several new exterior covered areas to provide additional staging locations for student pick-up and drop-off There will be an
alternate amongst others included in the project for a complete re-roof of the existing building as well.
Construction Contract: Sealed Bids will be received for the following Work:
Multiple Contract Project consisting of the following prime contracts:
a. 0300 – General Trades
b. 0400 – Masonry
c. 0500 – Structural Steel
d. 0700 – Roofing & Sheet Metal
e. 0820 – Hollow Metal, Wood Doors, & Hardware
f. 0840 – Aluminum Framed Entrances, Storefronts, Glass
g. 0920 – Gypsum Board Assemblies
h. 0930 – Tile
i. 0950 – Acoustical Ceilings
j. 0960 – Resilient Flooring
k. 0990 – Painting
l. 1000 – Specialties
m. 1230 – Manufactured Laminate Casework
n. 2100 – Fire Protection
o. 2223 – Plumbing & HVAC
p. 2600 – Electrical
q. 3100 – Site Excavation
r. 3200 – Asphalt Paving
Louisville Zoo-Outpost on the Edge-African Primates & Snow Leopard Leap – IFB# 170115
Louisville Zoo-Outpost on the Edge-African Primates & Snow Leopard Leap – IFB# 170115
PROJECT DESCRIPTION Louisville Metro Government is currently accepting bids for Outpost on the Edge-African
Primates and Snow leopard Leap per the attached specifications. The selected firm will be
responsible for renovations and expansions to the Outpost Cafe along with an African Primate
exhibit and a separate Snow Leopard LEAP exhibit
Louisville Metro Government uses Bonfire portal for accepting and evaluating proposals digitally (https://louisvilleky.bonfirehub.com/portal)
. Bidders must submit all pages of bid document through Bonfire.
CALL 107 CONTRACT ID 171022 LETCHER COUNTY NHPP 1191 (052) : HARLAN-WHITESBURG ROAD(US-119) PARTRIDGE TO OVEN FORK;SURFACING ON US-119 FROM 1000 FT WEST OF JCT. KY-3404 TO 0.15 MILE WEST OF KY-806 AT OVEN FORK INCLUDING APPROACH TO EXISTING US-119. ASPHALT SURFACING NEW CONSTRUCTION. SYP NO. 12-00311.79.
CALL 100 CONTRACT ID 171218 GARRARD COUNTY STP BRZ 0703 (338) : FALL LICK ROAD (KY 1972) (MP 0.613) REPLACE BRIDGE ON KY 1972 OVER BRANCH OF TURKEY CREEK; 0.50 MILES EAST OF JCT KY 39 (MP 0.713), A DISTANCE OF 0.10 MILES. BRIDGE WITH GRADE, DRAIN & SURFACE. SYP NO. 07-01120.00.
The Work consists of replacing two (2) existing 10’x10’ sliding motorized gates, operators, 2 personnel swing gates, and modification of existing fencing. Two existing gate controllers shall be reused and modified as required for the new gate operators. Replacement gates will be motorized sliding 14’x14’ each, swing gates will be 7’x3’ and new fencing to match existing. Replacement of a significant area of concrete in the gate area is included along with all concrete and metal supports, bollards as indicated on the drawings.
Electrical circuit and replacement of electrical circuits during construction is required.
Perimeter fence detection system removal and reinstallation will be performed by LLCC.
The project shall be constructed in two phases so that one secure gate remains in operation at all times.
All requirements of Section 010500 – Special Conditions required at LLCC will be applicable.