RFB-61-19 DMA – London Readiness Center Renovation

RFB-61-19 DMA – London Readiness Center Renovation

Project Manager Name: Joseph Sandman
Phone: (502) 782-0329
Email:Joseph.Sandman@ky.gov


Estimate:
$860,935.00
Estimated Length of Project:
300 (Substantial Completion) + 30 (Final Completion)

Replace aging Mechanical Systems of the London Readiness Center in London, Kentucky, along with a full lighting, ceiling grid and pad replacement, a renovation of the restroom facilities, and a renovation to include a Nursing Room to comply with UFC 4-171-05. Demo existing restroom facilities and associated MEP systems, and replace with new fixtures and systems as indicated in the contract documents.

Project Location: London

More Details

RFB-60-19 DMA – USPFO Warehouse Floor Resurfacing

RFB-60-19 DMA – USPFO Warehouse Floor Resurfacing

Project Manager Name: Bernard Engelman
Phone: (502) 782-0319
Email:
Bernard.Engelman@ky.gov


Estimate:
$523,589.00
Estimated Length of Project:
45 (Substantial Completion) + 15 (Final Completion)

The goal of this project is to provide a resinous floor in the warehouse areas of the USPFO Building at the Boone National Guard Center. Additional scope of work includes the removal of empty shelving prior to prep and installation of the floor. After installation of the floor new shelving will be reinstalled by the contractor. Walls in the open area of the warehouse shall receive wall paint and dryfall ceiling paint.

Project Location: Frankfort

More Details

RFB-57-19 KCTCS – OCTC Manufacturing Labs Renovation and Equipment

RFB-57-19 KCTCS – OCTC Manufacturing Labs Renovation and Equipment

Project Manager Name: Dwayne Brown
Phone: (502) 782-0315
Email:
Dwayne.Brown@ky.gov


Estimate:
$316,675.00
Estimated Length of Project:
80 (Substantial Completion) + 14 (Final Completion)

The project consists of interior renovations to multiple rooms, with a total of 10,050 sf. The renovations are for improvements to install new equipment for student training. Work includes new lay-in ceilings, carpet, painting, rework of electrical for new equipment, conduit pathways for network cable, replacement of compressed air system, and HVAC improvements.

Project Location: Owensboro

More Details

RFB-55-19 FSS – HVAC Replacement CHR Building

RFB-55-19 FSS – HVAC Replacement CHR Building

Project Manager Name: David Marshall
Phone: (502) 782-0332
Email:
David.Marshall@ky.gov


Estimate:
$3,167,600.00
Estimated Length of Project:
330 (Substantial Completion) + 30 (Final Completion)

The scope of this project is to repair, upgrade and modernize the heating, cooling and ventilation systems at the Cabinet for Human Resources building in Frankfort. The overall system design shall remain intact with sub-assembly replacements such as coils, valves, piping, fans and drives. All air terminal units throughout the building shall be replaced. This project will include various mechanical replacements, electrical upgrades as well as associated controls upgrades and programming. The controls system shall be totally renovated and move to a system that is entirely electronic without the need of any type of pneumatic or electric to pneumatic conversion.

Project Location: Frankfort

More Details

Mount Sterling – Montgomery County – New Swimming Pool Complex

Mount Sterling – Montgomery County – New Swimming Pool Complex

Please Note: Addendum 01 has changed the Bid Date and Location

PROJECT DESCRIPTION:
Packs + Walker, The Construction Management Company, will be soliciting bids for numerous
different trades for the construction work associated with the new pool project.

Project Location: Mt Sterling, Kentucky

More Details

RFB-62-19 DMA – EOC Pond Aquatic Awareness Project

RFB-62-19 DMA – EOC Pond Aquatic Awareness Project

Project Manager Name: Josh Morgan
Phone: (502) 564-3155
Email: josh.morgan@ky.gov


Estimate: $380,853.00
Estimated Length of Project: 90 (Substantial Completion) + 15 (Final Completion)

The project is for improvements around an existing pond. Project scope includes some
limited demolition, tree protection, as well as clearing of existing landscape material.
New construction includes crushed stone trails, boardwalk / deck overlook, limited site
signage, installation of new pond fountain, new native stone edging around the
perimeter of the pond, installation of new landscape plantings including trees, shrubs,
perennials and plugs to naturalize the pond perimeter.

Project Location: Frankfort

More Details

8004 Sandness Court Drainage Improvement Project

8004 Sandness Court Drainage Improvement Project

Description and location of Project: This unit base construction order is for the pipe, and paved ditch along the open space behind Sandness Court, in Metro Council District 19.

Project Location: Louisville, Kentucky

More Details

RFB-46-19 DMA – WHFRTC Range Operations Center

RFB-46-19 DMA – WHFRTC Range Operations Center

Project Manager Name: Dwayne Brown
Phone: (502) 782-0315
Email:
Dwayne.Brown@ky.gov


Estimate:
$1,173,800.00
Estimated Length of Project:
200 (Substantial Completion) + 30 (Final Completion)

The project is an addition to the existing Range Operations Center at the Wendell H. Ford Regional Training Center in Greenville, KY. The addition is 3,950 square feet in size. The structural system consists of poured in place concrete shallow foundations and stem walls and concrete slab on grade. Exterior walls are insulated concrete forms with cast in place concrete. Exterior wall finishes are a combination of pre-finished metal panels and anchored stone veneer. Roof structure is cold formed metal framing and trusses with steel deck, roof will be pre-finished metal roof panels over rigid insulation board with a nailable surface. Interior layout consists of a reception/customer service area, offices, meeting room, break room, storage, mechanical and toilets. Interior partitions will be light gauge steel framing with gypsum board surfaces and sound batt insulation. Floor finish will be sealed, colored concrete. Doors and frames will be hollow metal, windows are aluminum and ceilings are suspended acoustic panels. There will be minor demolition and patching of the existing facility walls to provide connections to the addition. Site work consists of grading, storm water structures and pipe, sidewalks and a flagpole. Water service shall connect to existing main at street, sanitary will gravity flow to existing sanitary main adjacent to building, and natural gas piping will be extended from existing natural gas utility meter. The building will utilize natural gas for heat. HVAC will consist of furnaces and condensing units, and ceiling cassettes with outdoor condensing unit. Electrical work includes modifications to existing 208V/3 phase service and a new 208V/120V panel for the power distribution system. Interior and exterior lighting will be LED. Communications systems will include telephone and data wiring and devices. A natural gas emergency generator will be installed.

Project Location: Greenville

More Details

RFB-53-19 KCTCS – ECTC Campus Signage Improvements

RFB-53-19 KCTCS – ECTC Campus Signage Improvements

Project Manager Name: Josh Morgan
Phone: (502) 564-3155
Email: josh.morgan@ky.gov


Estimate:
$255,000.00
Estimated Length of Project:
120 (Substantial Completion) + 15 (Final Completion)

The Elizabethtown Community & Technical College seeks improvements to their existing campus signage and wayfinding. Replacement of existing entrance signage and installation of new/additional signage with updated college logos will appropriately designate each entrance on to campus. New directional signage will be installed to help with vehicular navigations around the campus. New building identification signage will also be added to clearly delineate each building on campus. Additionally, new pedestrian way finding kiosks with campus maps will be strategically located around the site to help new and potential students and visitors navigate the campus.

Project Location: Elizabethtown

More Details

8700 Hudson Lane Drainage Improvement Project

8700 Hudson Lane Drainage Improvement Project

Description and location of Project: This unit base construction order is for the 48-inch pipe and drain system along the front of 8700 Hudson Lane, in Metro Council District 22.

Project Location: Louisville, Kentucky

More Details

Laurel Ridge Road Drainage Improvement Project

Laurel Ridge Road Drainage Improvement Project

Description and location of Project: This unit base construction order is for the drainage improvement project along Laurel Ridge Road which includes 10-inch driveway pipe, and 1′ paved ditch installation, in Metro Council Distract 24.

Project Location: Louisville, Kentucky

More Details

Blue Horse Ave. Drainage Improvement Project

Blue Horse Ave. Drainage Improvement Project

Description and location of Project: This unit based construction order is for the pipe and drain installation along Blue Horse Ave in Metro Council District 9.

Project Location: Louisville, Kentucky

More Details

RFB-50-19 KCTCS – JCTC Advanced Manufacturing Center Phase2

RFB-50-19 KCTCS – JCTC Advanced Manufacturing Center Phase2

Project Manager Name: Anne Saint-Aignan
Phone: (502) 782-0337
Email:anne.saintaignan@ky.gov


Estimate:
$13,787,500.00
Estimated Length of Project:
510 (Substantial Completion) + 30 (Final Completion)

A. The Work of the Project is defined by the Contract Documents and consists of, but not limited to, the following Phase 2 AMIT site clearing and new construction work:
1. Demolition of existing 746 South First Street, JCTC office/storage building concrete first floor slab, loading dock, partial basement, foundations and footings.
2. Demolition of existing billboard foundations adjacent to the 746 South First Street structure complete.
3. Site clearing including but not limited to asphalt parking lots and drives, concrete parking lots and drives, public sidewalks and curbs, existing foundations, overhead utilities and other Work indicated in the Contract Documents.
4. Construction of new JCTC, AMIT facility.
5. A Property Management Plan by Linebach Funkhouser have been included in the specifications. Based on the depth of excavation and demolition it is not anticipated that any contaminated soils will be encountered but provisions are attached in the event contaminated soils are exposed during demolition of structures and/or excavation of test trenches.
6. Phase 2 AMIT General Contractor to assume possession and responsibility for upkeep of construction fencing that was originally installed by the Phase 1 Demolition Contractor. Traffic control devices currently installed are the responsibility of the Phase 1.5 Traffic Control Contractor for the duration of the Phase 2 AMIT construction.

Project Location: Louisville

More Details

CCK-2354-19 BP6 Pav HA Emergency Power – 2402.3

CCK-2354-19 BP6 Pav HA Emergency Power – 2402.3

Please Note: Addendum 03 has changed the Bid Date

PROJECT DESCRIPTION:
Contractor to furnish and install a complete electrical system that will provide 300 emergency
power panel in room HA619 on the 6th Floor of Pavilion HA in Chandler Medical Center. The
panel will be fed from the first floor room HA0199.

Project Location: Lexington, Kentucky

More Details

Mason County Board of Education – Straub Elementary School and Athletic Building Roof Replacement

Mason County Board of Education – Straub Elementary School and Athletic Building Roof Replacement

PROJECT DESCRIPTION:
Straub Elementary School and
Athletic Building Roof Replacement

Project Location: Maysville, Kentucky

More Details

CCK-2353-19 HSRB Cold Room Chiller

CCK-2353-19 HSRB Cold Room Chiller

Please Note: Addendum 01 has changed the Bid Date

PROJECT DESCRIPTION:
This project is for HSRB COLD ROOM CHILLER

Project Location: Lexington, Kentucky

More Details

Woodford County Public Schools – Southside Elementary School Cafeteria / Kitchen Addition

Woodford County Public Schools – Southside Elementary School Cafeteria / Kitchen Addition

PROJECT DESCRIPTION:
Southside Elementary School Cafeteria / Kitchen Addition located at 1300 Troy Pike, Versailles,
Kentucky

Project Location: Versailles, Kentucky

More Details

RFB-52-19 KYTC – Woodford County Rest Area Pump Station

RFB-52-19 KYTC – Woodford County Rest Area Pump Station

Project Manager Name: Mark Strevels
Phone: (502) 782-0334
Email:
mark.strevels@ky.gov


Estimate:
$ 79,000.00
Estimated Length of Project:
120 (Substantial Completion) + 30 (Final Completion)

This project will replace a poorly functioning lift station and appurtenances at/near the I-64 Rest Area in Woodford County, Kentucky.
The project will construct a short length (less than 30’) of 8″ gravity sewer for the new inlet to the lift station. As shown on the plans, discovery of where this existing 8″ line bends is the Contractors responsibility. The Contractor shall provide underground power to the station as indicated from an existing disconnect. The Contractor shall construct a new discharge line as indicated on the plans including all necessary fittings and line markers. When appropriate, the Contractor shall demolish and remove the existing Lift Station. The Contractor shall install a new combination air valve in the approximate location shown on the plans. Discovery in the field of the existing force main shall be accomplished by the Contractor after consultation w/ appropriate KYTC officials (see KYTC Contacts on Sht. C02 of Plans). The Contractor shall ensure that this air valve is installed at the local high point in the force main. All surveying on the job is the Contractors responsibility.
The project shall be constructed wholly within KYTC rights of way as indicated.

Project Location: Woodford

More Details

RFB-56-19 Tim Malone and Chris Johnson AML

RFB-56-19 Tim Malone and Chris Johnson AML

Estimate:
$153,000.00
Estimated Length of Project:
(Substantial Completion) + 120 Calendar Days (Final Completion)

The proposed project consists of a coal seam fire reclamation in Pike County. The project area is located on the United States Geological Survey (USGS) 7.5’ Pikeville quadrangle (see the attached project and site maps).
The Tim Malone Seam Fire Site consists of covering up the coal seam fire using on-site material. The site is located off Melvina Drive on Chloe Creek, near the community of Pikeville, KY. The project area is centrally located at N 37° 28’ 48.36”, W 82° 30’ 7.44”. To reach the site from the Prestonsburg Regional Field office, travel to Pikeville on US 23 South, take exit ramp onto KY-1384 toward downtown Pikeville, turn right onto KY-1426 (Lower Chloe Creek) for 0.8 miles, turn left across a concrete bridge onto Melvina Drive, last house in the hollow is Mr. Malone’s.
The Chris Johnson Seam Fire Site consists of covering up the coal seam fire using on-site material. There are exposed auger holes on an upper bench that is not on fire that will be backfilled. The site is located near the community of Pikeville, KY. The project area is centrally located at N 37° 29’ 6.9”, W 82° 30’ 8.2”. To reach the site from the Prestonsburg Regional Field office, travel to Pikeville on US 23 South, take exit ramp onto KY-1384 toward downtown Pikeville 0.6 miles, turn left onto KY-1426 for approximately 0.5 miles past shopping center, turn right for 0.1 miles to a locked gate on your left. Mr. Johnson lives in a trailer across from the gate access entrance.
Entry to the work areas will be accessed by the county road. Reclamation work consist of covering the seam fire using smothering methods to minimize the fire. When necessary water and/or foam will be pumped to quenching the burning material. There is an existing access road that will be used and maintained with roadway stone. A section of road will have to be constructed from the Chris Johnson site to the Tim Malone site. The waste material generated during project work shall be used on site in the smothering and grading portions of the project boundaries.
During the process of these construction activities, trees over 3 inches in diameter at breast height will have to be removed in the AML problem area. A sediment and erosion control program, consisting of such measures as constructing hay bales/silt fence to be maintained throughout the life of the project and prompt re-vegetation using agricultural limestone, fertilizer, seed, and mulch will be implemented on all areas disturbed by this project.

Project Location: Pike

More Details

Louisville Metro Housing Authority – 1475 Will E. Seay Plaza – Chiller and Boiler Upgrades

Louisville Metro Housing Authority – 1475 Will E. Seay Plaza – Chiller and Boiler Upgrades

Please Note: Addendum 02 has changed the Bid Date

PROJECT DESCRIPTION:
Work under this contract includes all labor, materials, equipment and related items required to replace, disposal of existing roof top chiller, boilers and water heaters.

LMHA PROPOSAL #1475

Project Location: Louisville, Kentucky

More Details

RFB-54-19 Stephen McKinney Slide Phase II AML

RFB-54-19 Stephen McKinney Slide Phase II AML

Estimate:
$166,740.00
Estimated Length of Project:
(Substantial Completion) + 90 Calendar Days (Final Completion)

The Stephen McKinney site is located at 1402 Branhams Creek, Grethel, KY 41631 in Floyd County, KY at coordinates N 37° 28′ 40.90”, W 82° 38′ 39.60”. A portion of the bench on which the house sits has slid down toward Branhams Creek. This has made access to the other structures on the property potentially hazardous and could cause those structures to be lost if it continues to slide. Also, the material (trees, soil, debris, etc.) that is sliding could block the creek and cause flooding, including causing damage to the bridge used to access the McKinney property. The site was first inspected on 2/27/2018 and was referred to the AML design branch.
To address these concerns, the slide material will be excavated until a solid rock bench can be located. The material will be stockpiled on the bench for later use, and 120 L.F. of 21’ long W8x40 steel beams 6’ O.C. will be driven 10’ into the rock bench with sheet steel lagging between them. The soil will then be placed back behind the beams in compacted 1’ lifts with high strength uniaxial geogrid placed every 2’. Further details on this are shown in the plans. Some slide material and debris will be excavated from the area by reaching across Branhams Creek from the opposite bank. A rock silt check will be placed in the stream to mitigate issues from material entering the creek.
Additionally, several ditches and drains will be used to keep water off the slide area. A 280’ long, 1’ deep ECB ditch will be installed at the top of the hill behind the house, and two 1’ deep combination ECB ditch-drains will be installed directly behind the house (265’ long) and behind the storage structure on top of the slide (130’ long). The locations for these ditches/drains are listed on the plans. All three ditches will meet and be combined in a junction box with a steel grate which will outlet into an 18” HDPE pipe. The pipe will then outlet into an existing excavated rock ditch that runs down the hillside into the creek.
The contractor shall provide access to the site by either:
a) Installing a low water crossing (AML 50-10-7) on the downstream side of the existing bridge, or
b) Cribbing the bridge in the center and providing protective measures to the deck with steel plates or wooden runners.
If a low water crossing is chosen as the preferred method, a floodplain permit, which has already been obtained by AML, will be required. Other access to the site will be via the existing driveway and through the yard.
The waste areas for the project are located on either side of the McKinney driveway and are marked on the plans. Both waste areas may require tree removal, as may the slide area.

Project Location: Floyd

More Details

Frankfort Sewer Department – Rolling Acres Sewer Rehabilitation Phase 2

Frankfort Sewer Department – Rolling Acres Sewer Rehabilitation Phase 2

PROJECT DESCRIPTION:
The Work includes approximately 7,820 feet of pipe liner installed in existing 8-inch vitrified clay pipe, approximately 6,020 feet of open excavation replacement of 8-inch sewer pipe, approximately 9 open excavation repairs of existing 8-inch vitrified clay pipe, and rehabilitation of approximately 41 manholes.

Project Location: Frankfort, Kentucky

More Details

WKU-10157 Improvements at Horse Barn #3

WKU-10157 Improvements at Horse Barn #3

WKU invites you to bid on AG EXPO CENTER BARN #3 IMPROVEMENTS. The project
consists of grading and drainage improvements at Barn #3 located at the LD Brown Ag Expo Center.
Area of disturbance is between one and two acres. Includes underground storm drainage pipe, minor concrete and asphalt work, site re-grading.

Project Location: Bowling Green, Kentucky

More Details

Shelby County Courthouse – Sidewalk & Drainage Project Phase 2

Shelby County Courthouse – Sidewalk & Drainage Project Phase 2

PROJECT DESCRIPTION:
The work to be bid will be described as follows in approximate quantities:
Demolition of 2520 square feet of sidewalk
Concrete sidewalk construction
2520 square feet
Demolition reconstruction of existing steps
115 linear feet of storm drain and appurtenances
50 linear feet of 1 inch pipe for receiving air conditioner condensate
Waterproofing and foundation drain for west side of existing courthouse
Sealing new concrete surface for protection from de-icing chemicals

Project Location: Shelbyville, Kentucky

More Details

LFUCG – Cooling Tower Rigging and Replacement REBID

LFUCG – Cooling Tower Rigging and Replacement REBID

PROJECT DESCRIPTION:
Consisting of the construction and/or furnishing of items as listed in the Bid Schedule for the Cooling Tower Rigging and Replacement Reissued, Lexington-Fayette County, Kentucky.

Project Location: Lexington, Kentucky

More Details