Housing Authority of Harlan – HVAC Upgrades
Housing Authority of Harlan – HVAC Upgrades
The project consists of:
HVAC Upgrades
Project Location: Harlan, Kentucky
Housing Authority of Harlan – HVAC Upgrades
The project consists of:
HVAC Upgrades
Project Location: Harlan, Kentucky
RFB-190-20 DOCJT – Weber Building HVAC Repair
Estimate:
$540,093.00
Estimated Length of Project:
180 (Substantial Completion) + 30 (Final Completion)
This project entails replacement of an 80 ton air-cooled scroll chiller, two (2) 1000 MBH boilers and flue, four (4) hydronic pumps, and retrofit of new LED lights with automatic controls. All new equipment will be reintegrated into the existing building automation system.
Project Location: Richmond
CCK-2471-20 PAV HA G0011 Replace High Voltage Switchgear
Replacement of high voltage switchgear including service entrance meter, main circuit,
breaker sections, motor control sections and the feeder breaker section that is located in
University of Kentucky Medical Center PAV HA G0011.
Project Location: Lexington, Kentucky
Grayson County Water District – East-West Interconnect Project
Project consists of approximately 6,400 LF of 12”, 1,650 LF of 6” HDPE Directional Bore, 6,200 LF of 6” and
1,300 LF of 4” water main, two new master meter and all related appurtenances
Project Location: Leitchfield, Kentucky
Whitley County Board of Education – Whitley County Middle School – HVAC Replacement/Upgrades
The project scope includes the demolition of 38 existing rooftop units and curb
adaptors and replacement with new rooftop units, curb adapters, controls and thermostats at the
Whitley County Middle School.
Project Location: Williamsburg, Kentucky
RFB-189-20 Plymale Branch Slide AML
Estimate:
$251,257.50
Estimated Length of Project:
(Substantial Completion) + 90 Calendar Days (Final Completion)
The Plymale Branch Slide AML Reclamation Project consists of one site and an adjacent Waste
Earth Fill Area, totaling approximately 9.0 acres of disturbance. Reclamation at this site includes the
excavation of two nearly adjacent landslide areas threatening to both encroach upon a public road and to
damage a residence. Also to be completed are the installation of two permanent closures at a pair of
abandoned underground mine portals. A small rock overhang will be mitigated by filling the space
beneath it with heavy stone, eliminating the shelter area beneath it.
The landslide areas will be excavated to rock. This will result in the removal of up to an
estimated 10,000 cubic yards of earthen material to the fill area. One internally collapsed abandoned
mine entry located on the will be fitted with a non-wildlife-accessible portal closure. A second fully
collapsed and draining adit, located immediately above the landslide area, will be reopened and
permanently closed following installation of a drainage structure. After placement of excess earth in the
fill area (which is a reclaimed and completely released Title-V surface mine area) has been completed, the
area will be revegetated according to standard AML practices. Existing access roads leading to and from
the fill site will be maintained to allow passage of conventional wheeled vehicles.
All areas disturbed by the project will be revegetated using the AML standard General
Reclamation Mixture seed mix by means of standard agricultural tillage techniques, except for the
landslide areas that are excavated to rock. Such areas will be revegetated by means of hydroseeding
Project Location: Pike
Housing Authority of Prestonsburg – Bathroom Upgrades & Window Replacements
Project consists of Bathroom Upgrades & Window Replacements
Project Location: Prestonsburg, Kentucky
Housing Authority of Ashland – Erosion Control & Drainage Improvements
Project consists of Erosion Control & Drainage Improvements
Project Location: Ashland, Kentucky
Housing Authority of Springfield – Flooring, Lighting and Door Replacement
The work to be performed consists of:
Unit Renovations
VCT Flooring Replacement
Light Fixture Replacement
Interior Door Replacement
Work includes providing all items, articles, materials, operations or methods herein listed, mentioned or
scheduled on the Project Documents and / or herein, including all labor, materials, equipment, services and
incidentals as necessary for their completion.
Project Location: Springfield, Kentucky
Hart County Public Library – New Book Mobile / Outreach Facility
Project consists of a two-story, 5088 square foot, book mobile
garage with second floor book storage. First floor will be CMU and brick exterior with a metal framed
and brick second floor. Wood roof trusses and shingle roof. This is a turn-key project including all site
work.
Project Location: Munfordville, Kentucky
Housing Authority of Cumberland – Tubs & Tub Surrounds
The Scope of Work includes the following:
Tubs & Tub Surrounds
Project Location: Cumberland, Kentucky
RFB-191-20 KSFB – KEC Electric Repair 4160 Replacement
Estimate:
$180,000.00
Estimated Length of Project:
4/17/20 (Substantial Completion) + 4/27/20 (Final Completion)
The primary purpose of this project is to replace the existing underground electrical feed from the site electrical substation to the Freedom Hall electrical substation.
Project Location: Louisville
Pikeville Medical Center – Pharmacy Renovation at Pain Management
Project consists of Specialty Pharmacy expansion of approximately 8,700 square footage,
Project Location: Pikeville, Kentucky
Blue Grass Airport – 2002 / Parking Garage Stairwells Rehabilitation
The Project consists of concrete repair, rust removal, painting, stair and tread repair, caulking,
and pedestrian traffic coatings in the Parking Garage at Blue Grass Airport.
Project Location: Lexington, Kentucky
City of Middletown – Kratz Lane Sidewalks
The Project consists of
construction and replacement of various sidewalk and handicap ramps throughout the city.
Construction of sidewalk improvements 0.35 mile between
Shelbyville Road and Old Shelbyville Road including some
minor drainage improvements along Kratz Lane.
Project Location: Middletown, Kentucky
CCK-2468-20 Interventional Services – Final Cleaning & Signage
This package involves the installation work for Bid Package # 03 – Interventional
Services Project. The work will be performed under contract with the Construction
Manger, Turner Construction Company.
TC-171 FINAL CLEANING
TC-172 SIGNAGE
Project Location: Lexington, Kentucky
CCK-2469-20 PAV H Replace Diesel Tank and Pumps
Replace the above-ground, diesel tank and fuel pump set at PAV H., University of Kentucky
Medical Center.
Project Location: Lexington, Kentucky
Southern Madison Water District – Berea Bypass Waterline Relocation Phase 2
This contract consists of installing approximately 7,000 L.F. of
4”, 6” and 8” waterline, two new master meter vaults and all necessary appurtenances.
The engineer’s estimate is $540,000.
Project Location: Berea, Kentucky
Hazard-Perry Co Airport Board – Wendell H. Ford Airport – Airfield Pavement Rehabilitation Project
Project consists of furnishing all labor, materials and equipment and performing all
work necessary to complete the Airfield Pavement Rehabilitation
Project Location: Chavies, Kentucky
LFUCG – Town Branch Wastewater Treatment Plant Aeration Improvements
This project includes the following:
a. Removal of four 1250 HP aeration blowers and one 150 HP channel aeration blower
and appurtenances.
b. Installation of seven new 500 HP high speed aeration blowers and appurtenances.
c. Installation of two new 75 HP high speed aeration blowers and appurtenances.
d. Installation of new fine bubble aeration diffusers.
e. Aeration piping improvements.
f. Structural improvements.
g. HVAC and plumbing improvements.
h. Electrical and SCADA improvements.
Project Location: Lexington, Kentucky
RFB-187-20 Parks – Lake Barkley Golf Greens Bermuda Conversion
Estimate:
$ 95,000.00
Estimated Length of Project:
June 19, 2019 (Substantial Completion) + July 4, 2020 (Final Completion)
Project will consist of planting Ultradwarf bermudagrass sprigs on 100,000 square feet of existing golf course greens and expansion areas at Lake Barkley State Park Golf Course in Cadiz, Kentucky. The Park is located at 3500 State Park Road, Cadiz, Kentucky 42211.
Project Location: Cadiz
Hardin Memorial Hospital – Medical Office Build-Out
Subcontractors Only
Hardin Memorial Hospital – Medical Office Build-Out
Project Location: Elizabethtown, Kentucky
City of Jeffersonville – Ewing Lane Sanitary Sewer Ph 1 – Along Flood Control Levee Rebid
This project consists of the furnishing and installing of approximately 1,500’ of 18” gravity sanitary sewer parallel to a U.S. Army Corps of Engineers Flood Control Levee, manholes, safeloading of existing sanitary sewer pipe, reinstatement of existing sanitary service laterals, dewatering, and all other items shown on the plans and mentioned in the specifications for a complete project.
Project Location: Jeffersonville, Indiana
RFB-186-20 DOC – KCIW Lonnie Watson Chiller Replacement
Estimate:
$ 77,000.00
Estimated Length of Project:
90 (Substantial Completion) + 14 (Final Completion)
This project is for the replacement of the air cooled chiller at the Lonnie Watson Building at the Kentucky Correctional Institution for Women (KCIW) located at 3000 Ash Avenue, Pewee Valley, KY 40056. All work necessary for the removal of the existing chiller and installation and start-up of a new replacement chiller is to be included in this scope.
Project Location: PeWee Valley
Boyle County Board of Education – Woodlawn Elementary School – Renovation of Former Boyle County Middle School
Project Summary:
Existing one-story facility located in Danville, Kentucky. Approximately 69,566 S.F. renovation includes
remodeling of specific areas including the main office, library, gymnasium, restrooms, etc.; abatement of
existing hazardous materials; sitework, and associated mechanical and electrical work.
Estimate:
$4,276,781.00
Estimated Length of Project:
230 (Substantial Completion) Access to Site: May 29,2020
Project Location: Danville, Kentucky