Elizabethtown Independent Schools – Elizabethtown High School Restroom Renovation
Elizabethtown Independent Schools – Elizabethtown High School Restroom Renovation
The project scope includes the renovation of student and staff restrooms in the
High School. All fixtures and toilet partitions are being replaced. Demolition and new construction of
walls and slabs are included related to plumbing work. Finishes are being replaced in each location.
Sanitary line replacement is required in two locations..
This project is to modernize Elevator 8C in Pavilion H on the UK Medical Center Campus.
The work will include replacement of existing control systems, car and lights, door operator, traveling cable and hoist way wiring.
Louisville Water Company is requesting proposals for the systematic dismantling and replacement of existing 48”, 60” and 78” discharge headers including valves and connecting piping with new 78” discharge headers and associated valves and connecting piping. Includes electric and controls. Includes buried PCCP yard piping. Includes interior building modifications such as supports, handrails, floors, gratings and coatings. Includes lead based paint abatement. Includes carbon fiber interior pipe wrap/lining. Includes miscellaneous plumbing, piping, small hydro-pneumatic system replacement, and accessories and appurtenances.
A pre-bid/proposal meeting to discuss the Project and to tour the work site will be held on October 13, 2021 at 9:00 a.m. EST/EDT. At the Louisville Water Company Crescent Hill Filter Plant – Training Center, Louisville, KY. (Check-in with Guard; requires ID, PPE of high-vis vest, hardhat, safety glasses, safety shoes, ear plugs, and Covid mask). Attendance at this meeting is mandatory.
Questions or inquiries relating to this RFP/Bid must be submitted through the Louisville Water Company web-based portal for this RFP/Bid by the date and time indicated on the web portal for this RFP.
The Company’s Project Manager’s estimate for the Contract plus Company supplied materials for this Project is $10,000,001 –
$25,000,000. If the Company’s Project Manager’s estimate for the Contract plus Company supplied materials exceeds $250,000 a Bid Bond is required. For this Contract, a Bid Bond of $45,000.00 is required.
Proposals will only be accepted from Prime Proposers who have been pre-qualified by the Company in the pre-qualification category or categories that apply to this RFP and shall have a prequalification bid limit of at least $14,000,000. This RFP requires Prime to be prequalification in the Heavy Construction – Plant Work Category or 16”-60” Steel Water Mains. Contractors/Subcontractors performing specialty items of work such as electrical work must be prequalified in the Electrical Category, field coating/painting work must be prequalified in the Painting or Water Tank Coating Category, water main installation must be prequalified in the 24”-60” Prestressed Concrete Water Mains Category, and carbon fiber wrap lining on interior mains must be prequalified in 24”-60” Pipeline Carbon Fiber Wrap Lining Category. For information about pre-qualification, contact the Buyer listed above.
Sealed Proposals for the material or service specified above shall be accepted by Louisville Water Company until 11:00 a.m. Eastern Time on the RFP Submittal Due Date cited above. Louisville Water Company is using a web-based portal for accepting and evaluating bid proposals digitally https://louisvillewater.bonfirehub.com/portal for this Request for Proposal (RFP). Documents may be uploaded at any time during the open period indicated for each RFP. Specifications are on file and may be obtained from the Louisville Water Company designated web portal at https://louisvillewater.bonfirehub.com/portal. Proposals may not be submitted by other means.
RFP/Bid Documents may be obtained from Lynn Imaging located at 11460 Bluegrass Pkwy, Louisville, KY 40299, (502) 499-8400 and www.lwckyplanroom.com. One copy of the RFP/Bid Documents (includes technical specifications and a full set of plans) will be available at no charge (not including shipping/delivery charges) to Prime Contractors that are prequalified with Louisville Water in the category(ies) specified for this bid with a bid limit of at least $14,000,000. Contractors that are not prequalified may purchase the RFP/Bid Documents for $150.00 (not including shipping/delivery charges and sales tax).
Bids are requested by Western Kentucky University, from eligible firms located within a 125-mile radius of Bowling Green, KY to establish price contracts for the furnishing of labor, materials, and services for a Job Order Contract for Paint Contractor on facilities utilized by Western Kentucky University. The Paint Contractor shall be capable of providing qualified and skilled tradesmen as may be required. All jobs are to include but are not limited to the Contractor acquiring any necessary permits, inspections, and Performance Bonds where required. For question regarding this bid, please select “Messages” tab in Unimarket to send a message to your WKU contact, Marci Morehead
Floyd County Board of County Commissioners – Floyd County Bridge No. 506
Floyd County Board of County Commissioners – Floyd County Bridge No. 506
JOB NO. 13009, FLOYD COUNTY BRIDGE NO. 506 which consist of the
replacement of the existing single span bridge with a precast three-sided reinforced concrete
bridge structure and precast concrete wingwalls, all supported on a concrete footing on steel
HP piles. The bridge will provide a clear waterway opening of 9.0 feet high by 22 feet wide
with concrete sidewalk, concrete curb and gutter, concrete railing and approximately 100 feet
of approach work consisting of surface milling, pavement reconstruction with asphalt and
compacted aggregate, concrete curb and gutter replacement, install concrete guardrail
transition, steel guardrail with guardrail end treatments, scour stop, seeding, signing and
pavement markings, and all other items shown on the plans and mentioned in the contract
specifications for a complete project.
The Newtown Campus of Bluegrass Community & Technical College located at 500 Newtown Pike in Lexington (Fayette County) seeks to expand provide additional campus signage for identifying buildings and streets within the campus. There will be grounted mounted signs, building mounted signs and regulatory signs.
Under base bid, remove two existing steam boilers and all steam system components in central mechanical room, including feed tank, heat exchanger, steam and condensate piping, etc. Provide two new condensing heating hot water boilers to feed building’s existing heating hot water loop. New boilers will operate via their own on-board controls, no integration to building automation system. New boilers will include new PVC flues and combustion air intakes. Replace two existing base mounted circulation pumps. There are two addtiive alternates and they will be accepted as funds permit.
Louisville Water Company is requesting Bids for Limits of the referenced project include sections of eight (8) neighborhood streets
located in eastern Jefferson County in the Tucker Station Road area; Brookgreen Drive, Echo Bridge Road, Marengo Drive, Live Oak
Drive, Farmbrook Drive, Rockbridge Road, Creekvalley Road, and Edenwood Drive. The referenced project consists of the supply
and install a total of 6,655 LF of water main, including supply and install of 5,540+/- linear feet of 6-inch DR-18 C900 PVC, 565+/-
linear feet of 8-inch DR-18 C900 PVC, 370+/- linear feet of 6-inch Pressure Class 350 ductile iron water main, and 180+/- linear feet
of 8-inch Pressure Class 350 ductile iron water main, using traditional trench installation techniques. Also included with the project is
the supply and installation of 9 fire hydrants, and the supply and transfer, renewal, relocation, or discontinue of 123+/- customer
services. Fire hydrant removal, main cut and plugs, and restoration on and along Project Limits as stated above shall be included.
Contractor shall supply and install all materials required for the completion of this project.
Questions or inquiries relating to this project must be submitted in writing via email at least seven (7) calendar days prior to the bid
opening date. All questions and inquiries must be sent to the Buyer, Renee Fromme, email at rfromme@lwcky.com.
The Company’s Project Manager’s estimate for the Contract plus Company supplied materials for this Project is $1,000,001 –
$3,000,000. If the Company’s Project Manager’s estimate for the Contract plus Company supplied materials exceeds $250,000: a Bid
Bond is required. For this Contract, a Bid Bond is required.
Bids will only be accepted from Bidders who have been pre-qualified by the Company in the pre-qualification category or categories
that apply to this Bid. This Bid requires prequalification in all of the following categories: 4” – 16” Ductile Iron Water Mains, 4” –
16” PVC Water Mains, and 1” & Smaller Water Services, with a minimum prequalification limit of $1,000,000. The Bidder may
submit a bid that exceeds the amount of the Bidder’s monetary pre-qualification limit set by the Company. For information about prequalification,
contact the Buyer listed above.
Award of the Contract will be based on base bid pricing and is at the Company’s sole discretion. Alternate bid(s) may or may not be
awarded. The Company will award the Contract to the Bidder presenting a Bid that is responsive to the Specifications, is in
substantial compliance with the Contract requirements, and presents the lowest and best price for performing the Work making up the
base bid. The Company may accept the Bid that the Company determines is in the Company’s best interest, which may not necessarily
be the least expensive Bid.
Bid Documents may be obtained from Lynn Imaging located at 11460 Bluegrass Pkwy, Louisville, KY 40299, (502) 499-8400 and
www.lwckyplanroom.com. One copy of the Bid Documents (includes technical specifications and a full set of plans) will be available
at no charge (not including shipping/delivery charges) to Contractors that are prequalified with Louisville Water Company in the
category(ies) specified for this bid. For details regarding the charges that apply to non-prequalified contractors, go to
www.lwckyplanroom.com.
Louisville Water Company is requesting Bids for a project that includes sections of six (6) neighborhood streets located in southwestern Jefferson County in the Terry Road area; Rutledge Road, Dale Road, Wood Road, Capella Lane, Memory Lane, and Sylvania Road. The referenced project consists of the supply and install of a total of 6,860 LF of water main, including supply and install of 25+/- linear feet of four (4)-inch DR-18 C900 PVC, 2,460+/- linear feet of six (6)-inch DR-18 C900 PVC, 565+/- linear feet of eight (8)-inch DR-18 C900 PVC, 1,640+/- linear feet of six (6)-inch Pressure Class 350 ductile iron water main, and 2,170+/- linear feet of eight (8)-inch Pressure Class 350 ductile iron water main, using traditional trench installation techniques. Also included with
the project is the supply and installation of eight (8) fire hydrants, and the supply and transfer, renewal, relocation, or discontinue of 87+/- customer services. Fire hydrant removal, main cut and plugs, and restoration on and along Project Limits as stated above shall be included. Contractor shall supply and install all materials required for the completion of this project.
Questions or inquiries relating to this project must be submitted in writing via email at least seven (7) calendar days prior to the bid opening date. All questions and inquiries must be sent to the Buyer, Terri Young, email at tyoung@lwcky.com.
The Company’s Project Manager’s estimate for the Contract plus Company supplied materials for this Project is $1,000,001 – $3,000,000. If the Company’s Project Manager’s estimate for the Contract plus Company supplied materials exceeds $250,000: a Bid Bond is required. For this Contract, a Bid Bond is required.
Bids will only be accepted from Bidders who have been pre-qualified by the Company in the pre-qualification category or categories that apply to this Bid. This Bid requires prequalification in all of the following categories: 4” – 16” Ductile Iron Water Mains, 4” – 16” PVC Water Mains, and 1” & Smaller Water Services Category, with a minimum prequalification limit of $1,000,000. The Bidder may submit a bid that exceeds the amount of the Bidder’s monetary pre-qualification limit set by the Company. For information about pre-qualification, contact the Buyer listed above.
Bid Documents may be obtained from Lynn Imaging located at 11460 Bluegrass Pkwy, Louisville, KY 40299, (502) 499-8400 and www.lwckyplanroom.com. One copy of the Bid Documents (includes technical specifications and a full set of plans) will be available at no charge (not including shipping/delivery charges) to Contractors that are prequalified with Louisville Water Company in the category(ies) specified for this bid. For details regarding the charges that apply to non-prequalified contractors, go to www.lwckyplanroom.com.
Louisville Water Company is requesting Bids for Limits of the referenced project include sections of seven (7) neighborhood streets
located in southern Louisville in the Hikes Lane area; Butler Court, Mamaroneck Road, Chatham Road, Tyson Place, Briarbridge
Way, Brinkey Way, and a Public Utility Easement (between Klondike Lane and Brinkey Way). The referenced project consists of the
supply and install a total of 5,780 LF of water main, including supply and install of 450+/- linear feet of 4-inch DR-18 C900 PVC,
2,725+/- linear feet of 6-inch DR-18 C900 PVC, 570+/- linear feet of 8-inch PVC, 1,230+/- linear feet of 6-inch Pressure Class 350
ductile iron water main, 950+/- linear feet of 8-inch Pressure Class 350 ductile iron water main, 45+/- linear feet of 8” HDPE DIPS
SDR-11, and 10+/- linear feet of 16-inch Pressure Class 350 ductile iron water main, using traditional trench installation techniques.
Also included with the project is the supply and installation of 6 fire hydrants, and the supply and transfer, renewal, relocation, or
discontinue of 124+/- customer services. Fire hydrant removal, main cut and plugs, and restoration on and along Project Limits as
stated above shall be included. Contractor shall supply and install all materials required for the completion of this project.
Questions or inquiries relating to this project must be submitted in writing via email at least seven (7) calendar days prior to the bid
opening date. All questions and inquiries must be sent to the Buyer, Renee Fromme, email at rfromme@lwcky.com.
The Company’s Project Manager’s estimate for the Contract plus Company supplied materials for this Project is $1,000,001 –
$3,000,000. If the Company’s Project Manager’s estimate for the Contract plus Company supplied materials exceeds $250,000: a Bid
Bond is required. For this Contract, a Bid Bond is required.
Bids will only be accepted from Bidders who have been pre-qualified by the Company in the pre-qualification category or categories
that apply to this Bid. This Bid requires prequalification in ALL of the following categories: 4” – 16” Ductile Iron Water Mains, 4” –
16” PVC Water Mains, 4”-12” HDPE Water Mains, 1” & Smaller Water Services and 1.5” & Larger Water & Fire Services Category,
with a minimum prequalification limit of $1,000,000. The Bidder may submit a bid that exceeds the amount of the Bidder’s monetary
pre-qualification limit set by the Company. For information about pre-qualification, contact the Buyer listed above.
Award of the Contract will be based on base bid pricing and is at the Company’s sole discretion. Alternate bid(s) may or may not be
awarded. The Company will award the Contract to the Bidder presenting a Bid that is responsive to the Specifications, is in
substantial compliance with the Contract requirements, and presents the lowest and best price for performing the Work making up the
base bid. The Company may accept the Bid that the Company determines is in the Company’s best interest, which may not necessarily
be the least expensive Bid.
Bid Documents may be obtained from Lynn Imaging located at 11460 Bluegrass Pkwy, Louisville, KY 40299, (502) 499-8400 and
www.lwckyplanroom.com. One copy of the Bid Documents (includes technical specifications and a full set of plans) will be available
at no charge (not including shipping/delivery charges) to Contractors that are prequalified with Louisville Water Company in the
category(ies) specified for this bid. For details regarding the charges that apply to non-prequalified contractors, go to
www.lwckyplanroom.com.
Housing Authority of Richmond – 2020-21 Sewer Phase III
Housing Authority of Richmond – 2020-21 Sewer Phase III
The work to be performed consists of:
Robinson Terrace (20 units):
A. Sewer Replacement
1. Vinyl plank
2. Tub/Surround replacement
3. Paint entire unit
4. Plumbing fixture and vanity replacement
5. Cabinet and counter top/sink reinstallation/replacement
6. Wiring and receptacle replacement
Work includes providing all items, articles, materials, operations or methods herein listed, mentioned
or scheduled on the Project Documents and / or herein, including all labor, materials, equipment, services and
incidentals as necessary for their completion.
City of Jeffersonville – Wall Street Overflow Replacement
City of Jeffersonville – Wall Street Overflow Replacement
This project consists of the furnishing and installing of approximately 435’ of 60”
prestressed concrete cylinder pipe (PCCP), 23’ of 72” steel casing, 230’ of 8” PVC sanitary
sewer replacement with 14” steel casing, manholes, structures, sluice gate, asphalt pavement
restoration, penetration through existing Floodwall Closure Structure, and all other items
shown on the plans and mentioned in the specifications for a complete project.
Cave Run Water Commission – Raw Water Generator Pad & Chemical Feed Improvements
Cave Run Water Commission – Raw Water Generator Pad & Chemical Feed Improvements
Project consists of permanent placement of an existing mobile generator on a new concrete pad and chemical feed improvements near the raw water intake including associated electrical work.
West Shelby Water District – Old Veechdale Road Apartments Waterline Relocation
West Shelby Water District – Old Veechdale Road Apartments Waterline Relocation
This contract consists of installing approximately 630 L.F. of
10” PVC, SDR-21 waterline, a directional bore and all necessary appurtenances. The
engineer’s estimate is $158,000.
This package involves the installation work for Bid Package # 01 – Level B Support Services Renovation. The work will be performed under contract with the Construction Manager, Turner Construction Company.
1. Repaint all brick areas of existing building façade of UK Good Samaritan Hospital.
Scope of work:
1.1 Remove any loose or flaking paint or face of brick
1.2 Pressure wash and clean existing surfaces per paint manufacturer’s recommended
prep instructions
1.3 Clean rust, ect. From any steel items (Lintels, Glass block, shelf angles ect…) and
apply one coat of primer prior to painting of finish coat
1.4 Mask all glazing (including aluminum frames) and any other objects like wall
mounted light fixtures, security cameras, alarms, utility meters ect …
1.5 Temporarily remove any surface mounted banners, ect …
1.6 Recaulk around perimeter of ALL window openings including where window has
been removed and infilled, and along entire height of glass block
1.7 Apply paint to exterior surfaces per manufacturer’s recommended instructions for
film thickness etc …
Fayette County Public Schools – New Middle School at Polo Club Blvd
Fayette County Public Schools – New Middle School at Polo Club Blvd
Work of the Project includes Building and Site Work for the construction of a new 170,000 GSF Middle
School designed for 1,200 students. Included in the scope of the work is site work and paving for the site.
A portion of the site is reserved for the construction of an elementary school to be constructed in the
future. The project is constructed of masonry veneer and metal paneling on ICF, CMU walls. This multistory
facility will be supported by spread footings with slab on grade. Roofing systems will be a 2-ply
modified bitumen roof, with select areas of roof sanding seam metal panel. An ICC 500 compliant tornado
shelter will be provided. The project is a high-performance building with geothermal heating and cooling
and enhanced building envelope commissioning. Site work will encompass extensive earthwork,
permeable surfaces, seating walls, signage, utility work, landscaping, seeding and sodding, parking,
drives and traffic control devices.
Carroll County Public Library Phase IV – Entry Door Project
Carroll County Public Library Phase IV – Entry Door Project
Scope of Work consists of, but is not limited to the following:
• Selective Demolition for Walls
• Installation of Aluminum Storefront Door system
• Installation of Concrete Pad, Ramp and Stairs with support walls and
Railings
• Patching of CMU, Brick Veneer, and Interior Walls
• Installation of LVT Flooring
• Site Improvement – Turf & Grasses
This Project consists of asphalt paving of approximately 1,485 linear feet of roadway, pavement base failure repairs, roadway & parking lot widening, asphalt pavement milling, approximately 85,000 square yards of asphalt pavement sealing, and the replacement of storm water culvert pipes with headwalls.