Estimated Length of Project:
(Substantial Completion) + October 31,2023 (Final Completion)
The Project 22048BFPFMPO Pond Creek 889-0046 is a bond forfeiture project in Muhlenberg County Kentucky in the community of Beech Creek located at 37°10’26.437’N & 87°4’12.722’W. This project consists of removing 3 basins containing acidic water. The water in the basins will be treated prior to release then the basins will be filled in to a level to which no water will be held in the future. The water from the basins will need to have a pH of greater than 6 and an iron level less than 5 mg/L prior to release. Clearing of trees around the basins will be necessary to push the necessary dirt to fill in the basins. Mowing of areas adjacent to hotspots and the location for three ECB ditches will be necessary to work the approximately 12 acres of this type of work. Agricultural limestone will be spread over all disturbed areas at a rate of 50 tons per acre and subsequently incorporated into the acidic material. The hotspots,
if appropriate, will have the first 50 tons of lime applied and subsequently mixed into the soils first two or so feet and then an additional 25 tons of lime will be incorporated prior to seeding. Exploratory hours are to be used to determine areas in which soil quality at two feet is good enough that this method can be used and effective. Hot spot areas will be worked through the gradework and lime bid items prior to any seeding. If mixing of the soil is not appropriate for an area 75 tons of lime per acre will be added and incorporated into the substrate prior to seeding.
Three ECB ditches will be created above basin B to catch acidic seeps that are currently running into the basin. Three 4 foot flat bottom riprap ditches will be added to carry water from the basins removed to the appropriate drain ways. Seeding of all disturbed areas will be performed in a timely manner and will use the AML acidic seed mix. Fertilizer will be spread at a rate of 0.375 tons per acre and will be an 18-46-60 mix. Mulch will be applied at a rate of 2 tons per acre and will be crimped in. Throughout the project AML best management practices will be used to keep silt and water quality under control. Silt fence or bales will be installed above basin B to protect any silt from entering this basin. After all work on the main project area has been completed roadway stone will be applied to the access road.
The project consists of demolition of the existing slab-on-grade concrete pavement and construction of a new slab-on-grade concrete paving in the courtyard at the Southeast Community & technical College, as shown on the attached documents.
Work includes demolition of existing slab-on-grade concrete pavement and associated reinforcement; placement of new slab-on-grade concrete pavement and associated reinforcement; and the installation of new surface water drainage and associated piping to an existing catch basin.
The goal of the project is to remove and replace the concrete pavements in the courtyard with dimensions being approximately 145’-0” long by 40’-0” wide, less two raised planting areas to remain (12’-0” X 24’-0”). In addition, the project requires the replacement of the existing 6-inch drains with three larger drains for easier cleaning, including a new 6-inch drain line from each drain to the catch basin discharge point.
The extent of the construction area is depicted on the attached sketches and will be detailed during the walkthrough pre-bid scheduled for this project.
23-0425 – Collection System Professional / Technical Services
23-0425 – Collection System Professional / Technical Services
REQUEST FOR QUALIFICATIONS (RFQ)
Statement of Qualifications (SOQs) will be received by the Louisville and Jefferson County Metropolitan Sewer District until 2:00 PM, local time, April 25, 2023. MSD is using a web-based portal for accepting and evaluating SOQs: http://louisvillemsd.bonfirehub.com/portal. Documents may be uploaded at any time during the open period indicated for the RFQ.
Pre-submittal meeting will be held at 11:00 a.m. on March 14, 2023 via TEAMS. The link to join the meeting is:
City of Graymore – Devondale Drainage Improvement Project
City of Graymore – Devondale Drainage Improvement Project
Sealed Bids addressed to the Louisville and Jefferson County Metropolitan Sewer District, 700 West Liberty Street, Louisville, Kentucky 40203 for the construction of the City of Graymore – Devondale Drainage Improvement Project Contract No. 2023-026, Budget ID No. C23083, will be received at the office of MSD until 10:00 a.m., Local Time, Tuesday, March 21, 2023, and will be publicly opened and read at that place and time. The public may attend the bid opening via teleconference call.
Description and location of Project: To perform the drainage improvements within The City of Graymore – Devondale. All work shall be done in accordance to MSD’s Standard Specifications.
There will be no pre-bid meeting held for this project.
The Engineer’s Construction Cost Estimate for this project is between $500,000.00 and $550,000.00.
The bid documents will be available on March 3, 2023, online at www.msdbids.com. The charge for each set of bid documents is outlined on the above-referenced web site.
Persons wishing to view the bid documents may do so online at www.msdbids.com or at the following locations: Builders Exchange of Louisville, Inc., 2300 Meadow Drive; Associated Builders & Contractors of Kentuckiana, 1810 Taylor Avenue; and F. W. Dodge, 1812 Taylor Avenue; all located in Louisville, Kentucky; and the Associated General Contractors of Kentucky, 2321 Fortune Drive, Suite 112, Lexington, Kentucky.
The Project Manager for this Invitation to Bid is Joseph Exely. All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s Procurement Buyer Barry Pickett at Barry.Pickett@louisvillemsd.org. Questions received less than two days prior to the date for opening of bids may not be answered. Only answers by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. All inquiries and questions between the bid opening and the contract awarding shall be directed, in writing, to MSD’s Chief Engineer, David W. Johnson, P.E.
MSD SUPPLIER DIVERSITY MINORITY AND WOMAN BUSINESS ENTERPRISE PROGRAM POLICY AND PROCEDURES MANUAL (MBE/WBE PROGRAM) – FOR CONSTRUCTION CONTRACTS $150,000 AND GREATER for Minority Business Enterprise (MBE) and Woman Business Enterprise (WBE) subcontracting participation. Effective June 1, 2020, MSD has adopted and implemented the revised MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual, modifying the MBE and WBE participation goals on construction services and construction-related services, in accordance with the MSD Disparity Study (Study). The Study provided the factual predicate for MSD to establish new MBE and WBE goals in MSD contracting. The MSD MBE\WBE Program modified subcontracting goals are listed below:
If selected as applicable below, the Contractor must subcontract at least 18.0% of the total amount of the Contract Bid price to certified African American minority-owned businesses, at least 2.0% of the total amount of the Contract Bid price to a certified Asian-Indian American minority-owned businesses, and at least 15.0% total amount of the Contract Bid price to certified Caucasian Female businesses. If the Contractor is unable to meet the goals, they must demonstrate adequate “GOOD FAITH EFFORTS” in accordance with the MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual (MBE/WBE Program) – (see MSD MBE/WBE Program – Construction Subcontracting Goal Documents and Forms at http://louisvillemsd.org/SupplierDiversity/forms.
All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s Procurement Buyer, Barry Pickett at Barry.Pickett@louisvillemsd.org. For this Bid Opening, MSD will be hosting a Teleconference call in place of a face-to-face public opening. MSD will also post the As-Read Bid Summary as soon as available. To take part in the Bid Opening Teleconference Call, please call 502-654-8113 and enter code 859 715 333#.
MSD SUPPLIER DIVERSITY PROGRAM: Applicable
The revised MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual (MBE/WBE Program) is effective June 1, 2020. If applicable, the goals are as follows:
18.0% MBE – African American, 2.0% MBE – Asian-Indian American and
15.0% WBE – Caucasian Female participation respectively required for this project.
MBE and WBE businesses are encouraged to bid on this project as a prime contractor.
MSD BID DISCOUNT: Not Applicable
This MSD construction project is bid and advertised as: check applicable below
Construction Services: X
Construction-related Services:
LOCAL LABOR COMMITMENT PREFERENCE: No
COMMUNITY BENEFITS PROGRAM: No
The contract will be awarded on the basis of the lowest, responsive, responsible bid, subject to the approval of the MSD Board. MSD reserves the right to reject any or all bids or waive any informality in any bid.
LOUISVILLE AND JEFFERSON COUNTY
METROPOLITAN SEWER DISTRICT
David Johnson, P.E.
Chief Engineer
Rene’ Lindsay, CPPO
One Water Chief Procurement Officer
Project Description:
The project consists of the removal of existing asphalt shingle roofing, sheet metal and existing SBS modified bitumen roofing membrane systems and the installation of new asphalt shingle roofing, sheet metal and new SBS modified bitumen roofing membrane systems. Masonry cleaning and sealing to occur at parapet walls. New roof hatch and roof hatch access ladder to also be installed
Project Description:
The Project Scope consists of exterior improvements and construction at the corner of Morgantown Road and Loop Avenue – the traditional entrance to the campus. The “campus fence” will be extended from the recently completed Gate 1 around to the first entrance of the Fire & Rescue Building. A monument sign structure with mounted, illuminated panel signage will be constructed just inside the fence at the intersection. The existing monument sign at the same location will be demolished.
This project is a 12’ tall elevated archery shooting platform. A wooden deck structure used to simulate an elevated hunting position for target practice and conservation education. Shooting lanes above and below the platform to accommodate multiple archers. This work consists of earthwork, concrete, exterior framing, and retaining wall construction.
RFB-210-23 KCTCS – Main Campus Entry Site Modifications – Southcentral KY CTC
RFB-210-23 KCTCS – Main Campus Entry Site Modifications – Southcentral KY CTC
Estimate:
$104,470.00
Estimated Length of Project:
Phase 1: May 15, 2023; Phase 2: (35) thirty five calendar days beyond Substantial Completion for Phase 1 (Substantial Completion) + 20 (Final Completion)
Project Description:
The Project Scope consists of exterior improvements and construction at the corner of Morgantown Road and Loop Avenue – the traditional entrance to the campus. The project scope includes the construction of a cap structure over a natural cave feature. The cave feature exists in the right-of-way, outside of the SKYCTC campus property line, and is under the jurisdiction of the Kentucky Department of Transportation.
The project intends to cover the existing fenced in pipe outlet/cave opening approximately 40 feet northeast from the planned new sign at the intersection of Morgantown Road (US 231) and Loop drive for the KCTCS Campus. The design and construction scope will include removal of the existing fence, installation of an accessible concrete cap around the perimeter of the cave surface opening. The final cap/box structure will require provisions to maintain existing drainage to this feature. All disturbed areas around the cave cap impacted by construction will require standard erosion control measures and final seeding/sodding.
Project Description:
This Work includes the construction of a 2,000 sf office building at 340 N Mayo Trail, Pikeville, KY 41501. The building is slab-on-grade with wood framed walls on C.M.U. stem walls on poured concrete spread footings, with vinyl clad double hung wood windows, R-19 batt insulation, shop-fabricated wood trusses, asphalt shingle roofing, and fiber cement siding. Typical floor finish to be Luxury Vinyl Tile (Solid Vinyl Tile) with ceramic tile in the restrooms, typical wall finish to be painted gypsum board, typical ceiling to be suspended acoustical tiles. Typical ceiling height to be 8’-0″, typical bearing wall and interior partitions to be 10′-1″.
Please note the bid date has been changed to March 14, 2023, 10:00 A.M. Local Time.
Sealed Bids addressed to the Louisville and Jefferson County Metropolitan Sewer District, 700 West Liberty Street, Louisville, Kentucky 40203 for the construction of 4th St Hoist Replacement, Contract No. 16979, Budget ID No. F19126, will be received at the office of MSD until 10:00 AM, Local Time, March 14, 2023, and will be publicly opened and read at that place and time. The public may attend the bid opening via in person at MSD’s Main Office (700 West Liberty St, Louisville, Ky).
Description and location of Project: Replacing existing crane hoist in the 4th street flood pump station All work shall be done in accordance to MSD’s Standard Specifications.
All work shall be done in accordance to MSD’s Standard Specifications.
There will be non-mandatory pre-bid meeting held for this project. On Tuesday February 28th, 2023 at 10:00 am.
The Engineer’s Construction Cost Estimate for this project is between $30,000.00 to $60,000.00.
The bid documents will be available on, February 22, 2023, online at www.msdbids.com. The charge for each set of bid documents is outlined on the above-referenced web site.
Persons wishing to view the bid documents may do so online at www.msdbids.com or at the following locations: Builders Exchange of Louisville, Inc., 2300 Meadow Drive; Associated Builders & Contractors of Kentuckiana, 1810 Taylor Avenue; and F. W. Dodge, 1812 Taylor Avenue; all located in Louisville, Kentucky; and the Associated General Contractors of Kentucky, 2321 Fortune Drive, Suite 112, Lexington, Kentucky.
The Project Manager for this Invitation to Bid is Josh Dickerson. All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s Project Manager, Josh Dickerson at Josh.Dickerson@louisvillemsd.org. Questions received less than five days prior to the date for opening of bids may not be answered. Only answers by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. All inquiries and questions between the bid opening and the contract awarding shall be directed, in writing, to MSD’s Chief Engineer, David Johnson, P.E.
MSD SUPPLIER DIVERSITY MINORITY AND WOMAN BUSINESS ENTERPRISE PROGRAM POLICY AND PROCEDURES MANUAL (MBE/WBE PROGRAM) – FOR CONSTRUCTION CONTRACTS $150,000 AND GREATER for Minority Business Enterprise (MBE) and Woman Business Enterprise (WBE) subcontracting participation. Effective June 1, 2020, MSD has adopted and implemented the revised MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual, modifying the MBE and WBE participation goals on construction services and construction-related services, in accordance with the MSD Disparity Study (Study). The Study provided the factual predicate for MSD to establish new MBE and WBE goals in MSD contracting. The MSD MBE\WBE Program modified subcontracting goals are listed below:
If selected as applicable below, the Contractor must subcontract at least 18.0% of the total amount of the Contract Bid price to certified African American minority-owned businesses, at least 2.0% of the total amount of the Contract Bid price to a certified Asian-Indian American minority-owned businesses, and at least 15.0% total amount of the Contract Bid price to certified Caucasian Female businesses. If the Contractor is unable to meet the goals, they must demonstrate adequate “GOOD FAITH EFFORTS” in accordance with the MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual (MBE/WBE Program) – (see MSD MBE/WBE Program – Construction Subcontracting Goal Documents and Forms at http://louisvillemsd.org/SupplierDiversity/forms).
All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s Project Manager, Josh Dickerson.
MSD SUPPLIER DIVERSITY PROGRAM: Not Applicable
The revised MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual (MBE/WBE Program) is effective June 1, 2020. If applicable, the goals are as follows:
18.0% MBE – African American, 2.0% MBE – Asian-Indian American and
15.0% WBE – Caucasian Female participation respectively required for this project.
MSD BID DISCOUNT: Applicable
This MSD construction project is bid and advertised as: check applicable below
Construction Services: X
Construction-related Services:
LOCAL LABOR COMMITMENT PREFERENCE: No
COMMUNITY BENEFITS PROGRAM: No
The contract will be awarded on the basis of the lowest, responsive, responsible bid, subject to the approval of the MSD Board. MSD reserves the right to reject any or all bids or waive any informality in any bid.
MBE and WBE businesses are encouraged to bid on this project as a prime contractor.
LOUISVILLE AND JEFFERSON COUNTY
METROPOLITAN SEWER DISTRICT
David Johnson, P.E.
Chief Engineer
Rene’ Lindsay, CPPO
One Water Chief Procurement Officer
Sealed Bids addressed to the Louisville and Jefferson County Metropolitan Sewer District, 700 West Liberty St., Louisville, Kentucky 40203 for the construction of DRGWQTC WWPS & WWSB Rehabilitation Contract No. 18677, Budget ID No. D18132, Drawing Record No. 18677, Sheet No. 1-72, will be received at the office of MSD until 10:00 AM, Local Time, March 24, 2023, and will be publicly opened and read at that place and time. The public may attend the bid
opening via Microsoft Teams Meeting. The phone number is (502) 654-8113 and the Conference ID is 771 980 695. This
info will also be posted at the bid box on the day of the bid opening.
Description and location of Project: The principal features of the work to be performed under this contract include, but are not
limited to the following:
1. Demolition of existing Boiler system
2. Selective Demolition of existing AHUs, fans, and ducts
3. Installation of new ducts, fans, and grilles
4. Installation of split air units
5. Installation of indirect fire gas heater
6. Elimination of U3/U4 Transformers
7. Installation of new MCC
8. New Power Feed to WWPS and WWSB
9. Electrical modifications for HVAC
10. Installation of Gas Detection system
11. Repair of existing pipe penetrations
12. Roof replacements
13. Gas line installation
14. Mold abatement and painting
15. Replace exterior wall panel caulk and window repair.
All work shall be done in accordance to MSD’s Standard Specifications.
There will be a non-mandatory pre-bid meeting held for this project. Pre Bid meeting to be held at the Derek R.
Guthrie Water Quality Treatment Center (DRGWQTC), 11601 Lower River Road, Louisville, KY 40272. The meeting
will be held on Wednesday, March 1, 2023 at 10:00 a.m. Meeting will start in the Administration Building then
continue to the site. All visitors will be required to furnish their own PPE to visit the site.
The Engineer’s Construction Cost Estimate for this project is between $4,800,000.00 and $6,500,000.00.
The bid documents will be available on February 21, 2023, online at www.msdbids.com. The charge for each set of bid documents is outlined on the above-referenced web site.
Persons wishing to view the bid documents may do so online at www.msdbids.com or at the following locations: Builders Exchange of Louisville, Inc., 2300 Meadow Drive; Associated Builders & Contractors of Kentuckiana, 1810 Taylor Avenue; and F. W. Dodge, 1812 Taylor Avenue; all located in Louisville, Kentucky; and the Associated General Contractors of Kentucky, 2321 Fortune Drive, Suite 112, Lexington, Kentucky.
The Project Manager for this Invitation to Bid is Darryl Evans.. All inquiries and questions prior to the bid opening shall be Directed, in writing, to MSD’s Project Manager, Darryl Evans. at darryl.evans@louisvillemsd.org. Questions received less than five days prior to the date for opening of bids may not be answered. Only answers by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. All inquiries and questions between the bid opening and the contract awarding shall be directed, in writing, to MSD’s Chief Engineer, David Johnson, P.E.
MSD SUPPLIER DIVERSITY MINORITY AND WOMAN BUSINESS ENTERPRISE PROGRAM POLICY AND PROCEDURES MANUAL (MBE/WBE PROGRAM) – FOR CONSTRUCTION CONTRACTS $150,000 AND GREATER for Minority Business Enterprise (MBE) and Woman Business Enterprise (WBE) subcontracting participation. Effective June 1, 2020, MSD has adopted and implemented the revised MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual, modifying the MBE and WBE participation goals on construction services and construction-related services, in accordance with the MSD Disparity Study (Study). The Study provided the factual predicate for MSD to establish new MBE and WBE goals in MSD contracting. The MSD MBE\WBE Program modified subcontracting goals are listed below:
If selected as applicable below, the Contractor must subcontract at least 18.0% of the total amount of the Contract Bid price to certified African American minority-owned businesses, at least 2.0% of the total amount of the Contract Bid price to certified Asian-Indian American minority-owned businesses, and at least 15.0% total amount of the Contract Bid price to certified Caucasian Female businesses. If the Contractor is unable to meet the goals, they must demonstrate adequate “GOOD FAITH EFFORTS” in accordance with the MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual (MBE/WBE Program) – see MSD MBE/WBE Program – Construction Subcontracting Goal Documents and Forms at https://louisvillemsd.org/SupplierDiversity/forms
All inquiries and questions prior to the bid opening shall be directed, in writing, to MSD’s Project Manager, Darryl Evans.
MSD SUPPLIER DIVERSITY PROGRAM: Applicable
The revised MSD Supplier Diversity Minority and Woman Business Enterprise Program Policy and Procedures Manual (MBE/WBE Program) is effective June 1, 2020. If selected as applicable above, the goals are as follows:
15.0% WBE – Caucasian Female participation respectively required for this project.
The MBE subcontracting goal for this bid is waived, however, the WBE subcontracting goal is applicable as set forth above.
MBE and WBE businesses are encouraged to bid on this project as a prime contractor.
MSD BID DISCOUNT: Not Applicable
This MSD construction project is bid and advertised as:
Construction Services: NO Construction-related Services: YES
LOCAL LABOR COMMITMENT PREFERENCE: YES
COMMUNITY BENEFITS PROGRAM YES
The contract will be awarded on the basis of the lowest, responsive, responsible bid, subject to the approval of the MSD Board.
MSD reserves the right to reject any or all bids or waive any informality in any bid.
LOUISVILLE AND JEFFERSON COUNTY
METROPOLITAN SEWER DISTRICT
David Johnson, P.E.
Chief Engineer
Rene’ Lindsay, CPPO
One Water Chief Procurement Officer
Project Description:
This project consists of removing brick masonry veneer and brick mass screenwall in front of Kerr Hall and replacing in kind. The new brick veneer will require proper expansion joint installation, flashing, weep hole locations, and ties to existing concrete wall backup. All existing materials removed are to be removed and properly disposed of. New brick veneer is to be cleaned, then sealed.
Project Description:
The project scope includes the addition of a standby diesel generator, docking station, load bank, and associated controls work at Kentucky Correctional Institute for Women in Peewee Valley, KY. The project includes concrete work associated with equipment pads. Underground trenching will require patching of landscaped areas.
Estimated Length of Project:
(Substantial Completion) + 550 Calendar Days (Final Completion)
The primary slide abatement planned, includes construction of three (3) retaining walls (Walls A, B, & C); a fourth (4th) retaining wall, Wall D, is called for to ensure access during normal reclamation activities and to provide long-term access to the community once reclamation is complete.
The project involves the complete removal of the existing HVAC system on the West side of the bldg. This will include removal of the existing indoor and outdoor units and their controls, also a new rooftop HVAC unit to air condition the Drill Hall is to be included under the Add Alternate #1. This contractor will need to make all of the control wiring interlocks between indoor and outdoor equipment for control plus all T-stats.
This project also has an allowance of $75,350.00 to interface all of the existing and new HVAC equipment and schedules, also a $7,500.00 allowance for Add Alternate #1 for adding the RTU-1 unit to the Drill Hall.
Estimated Length of Project:
June 30, 2023 (Substantial Completion) + July 31, 2023 (Final Completion)
1. Provide all labor, equipment, materials, permits, inspections, insurance, etc. to remove existing, 3 – outdoor heat pumps and 11 – indoor wall mount units, thermostats, drain and refrigerant piping (VRF HVAC systems)
2. Install 3 – new LG (or equal) new heat pumps and 11 – indoor, one-way cassette units with new thermostats, drain and refrigerant piping (VRF systems). All work to include but not limited to all wiring, piping, etc. for fully operational systems.
3. Indoor cassettes shall be hung using angle brackets mounted to the wall. (No drilling into the ceiling)
4. Install white metal shroud around the top of the unit to the ceiling for finished appearance.
5. Replace the electric floor heater in the main entrance with like kind and include a factory thermostat not to be connected to the building automation controls system.
6. Include a 5-year parts and labor warranty to all work proposed.
7. Secure state HVAC permit if required.
Project Description:
This project provides for the renovation of existing areas on the first floor of the Personal Care Home at Eastern State Hospital in order to utilize the space for the EmPATH program. The work will involve renovation work to include new doors, a new combination toilet/shower room, replacement of existing architectural, electrical, mechanical, fire protection and plumbing appurtenances with anti-ligature designed equipment.
The work scope will involve the following features:
• Provide and install new doors into existing space and at end of corridor in for control into renovated area.
• Removal of existing drywall covering on one side of one room in order to replace it with sound attenuating material.
• Removal and replacement of layin ceiling systems in the area of renovation with anti-ligature ceiling grid and tile system.
• Replacement of existing HVAC diffusers in the area of renovation with anti-ligature diffusers.
• Construction of a new bathroom/shower room, with tile and new anti-ligature plumbing fixtures and bathroom accessories.
• Replace all existing plumbing fixtures and bathroom accessories in an existing restroom with anti-ligature fixtures and accessories.
• Replace existing plumbing fixture and all cabinet hardware in resident waiting area with anti-ligature fixture and hardware.
• New casework and drywall work to incorporate a new med prep station.
• New paint for the entire renovated spaces.
• The existing vinyl floor is to remain. Include laying protecting covering over the existing vinyl floor to ensure that it is not damaged in the course of the project work.
• Replace the existing door hardware on various doors leading into the renovated area in order to provide controls.
• Install new reflective film on portions of the existing window systems on the front and rear of the building.
• Replace existing fire sprinkler heads in designated areas with new anti-ligature type sprinkler heads.
• Include miscellaneous electrical wiring to support mechanical and access control work scopes.
Estimated Length of Project:
(Substantial Completion) + 120 Calendar Days (Final Completion)
The project will construct a foundation at an alternate site as determined by geotechnical investigation and as determined by the ENGINEER, and the house will be moved onto said foundation. Due to the depth of excavation needed a basement will be constructed beneath the residence.
The Scope of this Project shall include all labor, materials, tools, equipment, and services required to construct and install the complete and operational systems described herein and on the Drawings. The Project includes clearing, grubbing, and disposal of all debris from the path of the indicated utility easement areas. All earthwork and grading necessary to construct the new Force Main, Lift Station, & Water Line according to the project plans and specifications. Subgrade preparation, rock base, Lift Station installation, pipe work & testing according to the project plan and specifications is to be included. The contractor is responsible for all general and special conditions associated with this project as described in the project plans and specifications.
Project Description:
The project consists of a series of focused interior laboratory renovations within the Kentucky Central Laboratory Facility. The facility will be occupied and operational while this project is ongoing.
1. Remove existing wood shakes and underlayment to decking.
2. Remove any roof decking that has been damaged and deteriorated.
3. Remove existing gutters and downspouts.
4. Install new ice and water shield at perimeters and penetrations
5. Install new wood shake shingles and components.
6. Install new copper gutters, downspouts, valleys and trim where indicated on Drawings.
The project is an HVAC upgrade to Building 15 on Western State Hospitals campus. The project consists of removal of the existing HVAC systems including two split system air conditioners, electric unit heaters, and an electric furnace. Provide two nominal 5-ton packaged heat pump units with supplemental electric heat. Provide ductwork, grilles and diffusers and controls.
Project Description:
This project consists of the fit-up of approximately 3,300 sf shell spaces inside the existing Student Center building. Spaces to include office space and a computer classroom. Construction to include flooring, metal stud and gypsum walls, ceiling tiles, new lights, data and extension of mechanical and plumbing systems to service spaces.