RFB-209-12
The proposed Glen Cornett AML Reclamation Project consists of stripping a slide to rock, construction of drainage structures and a gabion wall, in Perry County. For continued project description see Special Conditions.
RFB-213-12
1) The project will remove the existing concrete box culvert and pipe system located in the rear parking lot behind buildings 32 & 33 that outlets on the west side of the maintenance building and construct a new 36″ RCP storm sewer system with drainage structures. The areas of parking lot that are removed during construction of the storm sewer system will be paved with asphalt. There are also some concrete sidewalk and curb that are going to be removed and replaced with this project.
2) The project will also remove and replace the storm sewer system in the ambulance access area. A new storm sewer system with drainage structures will be installed to accommondate the new concrete pavement in this area.
3) The project will be done in four (4) phases that are shown on sheet C3 and A-3.
RFB-214-12
This project involves the replacement of existing sanitary and storm sewage pumps. Furnishing pumps for future kitchen waste will be an Alternate.
This project is an underground duct bank project which includes digging and excavation. This includes but is not limited to installation of underground electrical and communications concrete encased duct bank. Installation will include approximately 8 communications and 8 electrical man holes, and each to be grounded. This will also include site restoration in its many forms.
RFB-208-12 New Boiler Room Building Boiler Relocation
RFB-208-12
Construct new concrete and masonry boiler room with tunnel access to existing structure at the
L&N Building, 908 West Broadway, Louisville, Kentucky. Relocate 4 existing “Lochnivar”
condenser type boilers from existing basement boiler room to new boiler room. Replacement of
two (2) system hot water pumps and replacement of an existing 3000 gallon underground diesel
fuel system serving an emergency generator is included. All attendant demolition, mechanical
piping and materials, plumbing, fire suppression, electrical including fire alarm and lightning
protection systems shall be furnished and installed for a complete and fully operational boiler
plant. An allowance for “InnerSpace” to provide automatic temperature controls in the amount of
$23,000 shall be included in form of proposal.
Repair work is generally categorized as follows:
a. Exterior precast concrete façade connection repairs and recoating (Levels 1-3)
b. Interior precast concrete panel connection repairs and recoating (Levels 1-3)
c. Overhead and vertical concrete repairs (Levels 1-3)
d. Exterior EIFS panel façade repairs, including metal stud framing replacement (Levels 4-6)
e. Repainting of areas around perimeter of deck (all levels)
f. Repainting of doors and frames (all levels)
g. Application of elastomeric waterproofing membrane to EIFS panel facades (Levels 4-6)
h. Vertical sealant replacement (all levels)
i. Installation of bird control spikes and sign installation (Level 6)
j. Repair and painting of steel emergency barrier cable support (Level 3)
This project includes the site development and construction of a new, 600-student high school on a property in Springfield, KY previously used as farmland. The 99,000 SF construction will include both one and two-story areas, and will be comprised of concrete foundation, exterior ICF bearing walls, interior CMU partitions, bar joists and steel decking, with both thermoplastic membrane roofing and metal roofing panels. The base-bid HVAC system will consist of a boiler and cooling tower, with add-alternate for a geothermal well field. Plumbing, fire protection, and electrical are also included.
Old Harrods Creek Road and Tucker Station Road Water Main Replacement
Old Harrods Creek Road and Tucker Station Road Water Main Replacement
Louisville, KY
Louisville Water Company is requesting Bids for the installation of 2,005 linear feet of 8-inch PVC water main, 370 linear feet of 8-inch DPW water main, 75 linear feet of 6-inch DPW water main, and 30 linear feet of 6-inch PVC water main along Old Harrods Creek Road between Cox Avenue and Roberts Road and along Tucker Station Road between Brookmoor Drive and 518 Tucker Station Road. Also included with the project is the installation of 3 fire hydrants, the transfer/renewal/relocation of 37 customer services, 2 service discontinues, and 3 meter exchanges.
Contract 2 – 500,000 Gallon Elevated Water Tank Farmdale Water District
Contract 2 – 500,000 Gallon Elevated Water Tank Farmdale Water District
A 500,000 gallon elevated water storage tank including tank, tank foundation, site prep, excavation, valve vault, access road, demolition and all appurtenances as shown.
Demolition and removal of existing 155,000 gallon standpipe, including foundation.
DUC Renovation: BP 5 Temporary Dining Foundations & Fit Up
DUC Renovation: BP 5 Temporary Dining Foundations & Fit Up
WKU will be constructing a temporary dining facility on the South Lawn of Campus. The Pre-engineered metal building will be provided and erected by others. This bid package includes the following for the facility: Site grading, concrete foundations and slabs, utilites to the site, interior wall construction and finishes, and final connections of owner-furnished equipment.
RFB-204-12 Sprinkler System & Building Renovations
RFB-204-12
The work consists of fire suppression on all floors of buildings 31, 32 and 33;
construction of two utility towers and upgrade the electrical service. There are three
add alternates.