This project involves the cleaning, repairs, and treatment of the Jefferson Davis Monument with a penetrating water-repellant sealer. The Jefferson Davis Monument is a 351 ft. tall concrete obelisk measuring approximately 35 ft. square at its base. The work includes providing all access to the exterior of the monument, fencing and other controls for the work area. Repairs to the exterior concrete surfaces of the monument include removal and replacement of damaged concrete, repair of selected lift line sealants, and repairs to selected cracks, etc. The monument shall also receive detergent cleaning of the monument surfaces, final rinse cleaning of the monument surfaces and the application of a penetrating-water-repellant sealer to the exterior of the monument. Additional repairs include restoration of the historic bronze windows at the observation level as well as replacement of the security bars at these windows.
CCK-2109-16 Multi-Disciplinary Research Lab #3 RTU Replacement Unit #3 and #4
CCK-2109-16 Multi-Disciplinary Research Lab #3 RTU Replacement Unit #3 and #4
PROJECT DESCRIPTION:
THIS PROJECT REPLACES THE ORIGINAL ROOFTOP UNITS NO.3 AND NO.4 ON THE RESEARCH LAB 3 BUILDING. INSTALLATION WILL BE DONE SEQUENTIALLY. THE NEW UNITS MATCH THE CAPACITY OF THE ORIGINAL UNITS, CONNECT TO THE ORIGINAL OUTSIDE AIR DUCT, AND FIT THE EXISTING SUPPLY AND RETURN OPENINGS. A NEW ROOF CURB SHALL BE PROVIDED FOR EACH UNIT.
PROJECT DESCRIPTION:
The scope of the work is for the construction of grade, drainage, paving, and structures associated with the new roadway, Alpha Way. Also included in the project is the construction of a “4” in Force Main, Water-line Encasement Pipe and a Traffic Signal at KY 480. The project work areas begin at existing Ohm Drive and extend north to a new intersection with KY 480, a distance of approximately 5844 feet.
PROJECT DESCRIPTION:
The work includes the renovation of the existing library with a new addition. The existing library has approximately 58,360 SF; 7,270 to be renovated. The new addition is 23,690 SF. The scope of work for this project includes. but is not limited to: selective, systems, and building demolition, mechanical systems including installation new air handling units in the new addition, electrical, fire protection, and fire alarm systems, interior partitions and finishes, door hardware, site improvements and paving. The building will be occupied during all phases of construction work
Spencer County Schools – New Spencer County Elementary School
Spencer County Schools – New Spencer County Elementary School
PROJECT DESCRIPTION:
Furnishing of all labor. materials, supplies, tools, services, etc., necessary for:
NEW SPENCER COUNTY ELEMENTARY SCHOOL
TAYLORSVILLE, KENTUCKY
City of Glasgow – Construction/Demolition Debris Landfill Cell No 4
City of Glasgow – Construction/Demolition Debris Landfill Cell No 4
PROJECT DESCRIPTION:
The program of work consists of, but is not limited to, the following:
Construction of a Construction/Demolition Debris Landfill Liner System for Cell 4.
The Elevators will be repaired per Kentucky Elevator Code, per Kentucky Revised Statue Chapter 198B-4009, which requires all elevator work to be performed by a KY Licensed Elevator Contractor or Mechanic, the National Electrical Code, as well as the National Fire Alarm and Signaling Code at the Eastern Kentucky Correctional Complex, located in Morgan County, West Liberty, Kentucky. The exterior Passenger Elevator and the interior Passenger Elevator are used extensively on a daily basis, are rapidly deteriorating with age, and are in need of repair. The structure of the elevator cabs are in good condition and suitable for reuse. In addition, the operating rails are heavy duty, in excellent shape and are to be reused. At the time the elevators were installed, there was no code requirement for a door restrictor, but will be added in this project. The elevator power units, controls, controller software, floor landing system will be replaced by the Contractor. The elevator machine rooms are in good condition with adequate access, HVAC, ventilation, and lighting. Likewise the elevator pits are acceptable, with no hydraulic oil leaks present. A dedicated HVAC unit for the interior elevator machine room will be provided by the Contract. The elevators will comply with all manufacturers’ requirements and shall interface with the Fire Alarm System for elevator recall.
CCK-2107-16 – Miller Hall Renovation of Rooms 101-103
CCK-2107-16 – Miller Hall Renovation of Rooms 101-103
PROJECT DESCRIPTION:
THIS PROJECT IS THE FOR THE RENOVATION OF ROOMS 101, 101A, 102, AND 103 INTO OFFICE SPACE. ROOM 101 IS CURRENTLY A CLASSROOM AND WILL BE RELOCATED ACROSS THE HALL TO ROOM 102. ROOM 101 WILL BE DIVIDED INTO AN ADMINISTRATION/WAITING AREA AND A PRIVATE OFFICE WITH A CONFERENCE TABLE BY A NEW INTERIOR WALL. THE WALL BETWEEN ROOM 101A AND 103 WILL BE DEMOLISHED AND THE NEW ROOM WILL BECOME OFFICE 101A. NEW FINISHES AND FURNITURE WILL BE INSTALLED IN 101, 101A, 101B, AND 102. NEW CEILING WILL BE INSTALLED IN THE NEW OFFICE lOlA. THE REMAINING CEILING WILL HAVE NEW TILES, FIXTURES, AND DIFFUSERS INSTALLED INTO THE EXISTING GRID.
PROJECT DESCRIPTION
Construction of Phase 3B of the Hardin County Contained Landfill which involves the development of approximately 10 acres of landfill area including excavation. access road, synthetic liner components, leachate collection system, drainage structures, and HDPE pipe
PROJECT DESCRIPTION:
The work entails relocation of approximately 650 linear feet of Sidewalk/Ramps on the east side of Rose Street from Euclid Avenue to Rose Lane.
CCK-2104-16 New Neonatal Intensive Care Unit BP02 Early Site Packages – 2402.3
CCK-2104-16 New Neonatal Intensive Care Unit BP02 Early Site Packages – 2402.3
PROJECT DESCRIPTION:
This package involves the installation work for the Phase 1 F NEW NEONATAL INTENSIVE CARE UNIT. The work will be performed under contract with the Construction Manger, Turner Construction Company
PROJECT DESCRIPTION:
Site work is to include installation of concrete pavement, pre-fabricated tent strap anchors in concrete pavement and minimal grading. Sod is to be installed at lawn areas disturbed by construction activities. No construction activities will be permitted to take place under the driplines of existing trees or within existing parking areas. Site utility work is to include installation of electrical lines and new power boxes. Scope also includes power to new light poles (light poles to be purchased by owner and installed by contractor)
PROJECT DESCRIPTION:
Project consists of new geothermal well field, complete HVAC replacement, lighting and ceiling replacement, interior and exterior signage, new markerboards and tackboards, and new security vestibule.
Construction Contract: Bids will be received for the following Work:
1. General Contract (all trades).
PROJECT DESCRIPTION:
The project includes approximately 54,160 square feet of roofing system replacement. The demolition includes removing the existing metal roofing, gutters and some downspouts as well as some EIFS repair. New work includes installing a vented nailbase insulated panel along wilh felt and asphalt shingles.
PROJECT DESCRIPTION:
The project is generally described as complete building construction and necessary site improvements for the New Rowan County Detention Center.
The Division of Abandoned Mine Lands wishes to receive bids to perform reclamation work on approximately 38 acres of mine land in Clay to do light and regular reclamation earthwork, install ditches and culverts, apply roadway stone to access road as needed, and revegetation on 6 bond forfeiture permit(s).
Oldham County Detention Center – Special Inspections Bid Package
Oldham County Detention Center – Special Inspections Bid Package
PROJECT DESCRIPTION:
Special Inspections Bid Package
Special inspections services relative to the construction of the new Oldham County Detention Center.