Fayette County Public Schools – Henry Clay High School – Synthetic Turf Replacement & Running Track Repairs
Fayette County Public Schools – Henry Clay High School – Synthetic Turf Replacement & Running Track Repairs
The Scope of Work intent of the project is to renovate and replace the existing synthetic field turf
system & repair, renovate, with new latex spray finish + restripe existing urethane resilient track
surface as well as provide for new resilient latex track system for the entire high jump surface area
(that currently is only paved surface).
This work includes excavation, demolition, minor asphalt paving + concrete work, and rework of finish
lawn surfaces, along with other miscellaneous related work to complete the aforementioned project in
accordance with the Construction Documents. The fields will NOT be occupied during construction work.
The contractor shall have full use of the field during the construction time.
The turf portion of the project includes the removal and partial possible recycling of the existing synthetic
turf athletic field, reworking of existing perimeter drainage, addition of storm drain piping, installation of
long jump sand catcher and cover system, installation of new football field goal posts, installation of discus
pole eyebolts + sleeve supports, reworking of the existing gravel subbase and final laser grading,
installation geotextile fabric, shock drainage pad, and synthetic turf system, with rubber/sand mix infill. The area of field replacement is the total area inside the existing perimeter track system – totaling
(approximately 120,500 SF). All existing track surfaces and other existing appurtenances shall be
protected and not damaged during construction of the turf replacement. The existing running track will
have repair work and [2] finish coatings applied and track restriped, as well as the high jump pad
expanded and new track surface applied to the area of (approximately 5,020 SF), Work is to be
completed over Seventy Two, (72) days starting approximately May 20, 2019 and completed prior
to 1 August 2019. Upon Execution and after Notice to Proceed Contractor shall prepare all
submittals in order to have all materials approved, ordered and to be available at the Start of Work.
Project Location: Lexington, Kentucky